Key Takeaways
- BESS drives a 67.5% revenue surge: Total revenue jumped 67.5% YoY, powered by short-term peak power BESS operations and renewable capacity additions; PAT rose 133.5% YoY to INR269 crores.
- BESS is now a self-financing growth engine: Management expects to operate ~10 GWh of BESS on a rolling basis, with cash flows funding growth and reducing equity needs for new projects.
- FY27 BESS target raised to >12 GWh: The commissioning guidance was lifted from 10 GWh, backed by an early deployment strategy and ~5.2 GWh already commissioned.
- The 2030 ambition just doubled: Renewable target raised from 10 GW with 25 GWh BESS to 15 GW and 50 GWh of battery, with management seeing a path to 12 GW contracted by end of calendar 2027.
- What to watch next quarter: Whether the 1.5 GW full-commissioning target for FY27 stays on track or slips a quarter, the pace of PPA signings to fill the uncontracted 40–50% of FY28 BESS capacity, and any update on the ~70 crore units of implied curtailment that management did not quantify.
The BESS Engine: Performance, Margins & Self-Financing
- Blended margin structure: EBITDA margin of 86.7% split into 90.8% from renewable generation and 78.3% from BESS operations, where the cost of power purchased to charge batteries sits within operating expenses.
- Short-term sales dominate: 32.4 crore units were sold through short-term peak power BESS contracts, locking in more than INR1,600 crores of revenue for partial sale of FY27 capacity and more than INR1,500 crores for partial sale of capacity for FY28.
- Curtailed solar cuts BESS charging cost: Where GNA is delayed, curtailed solar under PPA can now charge BESS for merchant sale; at Bikaner-III, ~90–100 MW AC of the 133 MW commissioned solar charges BESS, reducing cost of production and lifting BESS EBITDA.
- Capex advantage built in: BESS capex achieved below INR1 cr/MWh because installations reuse existing transformers and AC infrastructure at operational substations, saving ~INR20 lakh/MWh versus greenfield.
- Battery capex trend is down: Lithium carbonate prices are down, and while copper prices are up and a 6% Chinese export tax arrives in January, overall battery capex is expected to decline; magnitude depends on supply-demand and geopolitical factors.
- Contracting visibility is front-loaded but incomplete: FY27 BESS production is 90–95% contracted; FY28 is around 50–60% contracted, with no tie-ups yet for power purchase on the buying side, leaving exposure to IEX prices that own solar charging will increasingly reduce.
Upadhyay: "On a rolling basis, we expect to operate around 10 gigawatt-hour of BESS subject to tariff realization. Its cash flows fund our growth and reduce the equity needed for new projects, making this a self-financing platform."
Commissioning & Capacity: Partial Is the Story
- Partial commissioning unlocks early revenue: 1.9 GW of contracted projects are partially commissioned through a mix of solar and BESS; all except Acme Suryodaya are under PPAs and generating revenue even before full GNA availability.
- Full commissioning target carries a quarter of slippage risk: Management is hopeful of 1.5 GW of full commissioning in FY27, but acknowledges it could be more or less by a quarter depending on GNA commissioning; Fatehgarh-II is the critical path item.
- Partial commissioning could reach 2.5–3 GW: That figure is substantially higher because 2.5 GW of capacity is already charged in terms of AC commissioning.
- Capitalization follows power sales: Assets are capitalized wherever power is being sold, whether to the grid or to own BESS; partially commissioned projects are capitalized and expensed through the P&L.
- CUF benchmarking is not uniform: The 25% CUF benchmark does not apply where only battery is commissioned without solar; where solar is partially commissioned, 25% applies only to the charged portion. Management committed to provide matching data in the next presentation.
- Curtailment question left open: An analyst inferred ~70 crore units of curtailment from the gap between 1.9 GW partial commissioning at 25% PLF and 32.4 crore units of BESS supply; management did not confirm or deny the figure, explaining why 25% CUF does not apply uniformly.
Dhingra: "Tracking the full commissioning does not mirror the revenue generation, because the BESS comes online early."
The BESS Market Opportunity: Displacing RTC
- BESS is gaining trust as a distinct power category: Management says BESS has developed trust with maybe 10–12 governments, and states are growing confident about shifting their near-term power mix from RTC to batteries.
- The RTC-to-BESS disruption is an economic argument: RTC at INR6–7 is more expensive than BESS at INR10 because RTC includes unnecessary daytime volume; 85% of near-term power is RTC waiting to be disrupted.
- States are short on peak power and contracting aggressively: Large 5-year PPAs are being contracted, some states are looking at 20-year PPAs, and states are contracting surplus power due to scepticism about commissioning timelines of other plants.
- Nobody is building plain-vanilla solar anymore: Management observes that nobody is now installing solar and sending it to the grid; everybody is converting into peak power, and that is the intent with which states are also buying.
- Central aggregation is coming: SECI is already active in peak power procurement; management expects other agencies to follow with large battery procurement bids.
- Tender pipeline is deep: 20+ GW of upcoming tenders, 50 GWh of peak power builds rolled out till September 27th, another 20 GW to 250 GWh of short-term peak power contracts expected in the near to medium term, and 20 GWh of medium-term peak-only tenders expected shortly.
Dhingra: "In terms of the tariffs, of course the RTC at INR7 or INR6 is much more expensive than BESS at INR10, because you are buying unnecessary volume of power which you don't need to during the day when you contract out this RTC. And that volume is huge. Basically, the 85% of the near-term power is RTC, which is waiting to be disrupted."
PPA Portfolio & Bid Environment
- PPA portfolio now 92% contracted: Signed 430 MW of FDRE PPAs during the quarter and another 400 MW FDRE PPA with NTPC yesterday, taking the overall signed portfolio to 92% of total contracted 8,370 MW.
- Bid-to-signing speed has collapsed to ~2 months: SECI is now floating bids only after fully tying up power with DISCOMs, making fast PPA conversion possible; a recent bid was won and signed within ~2 months.
- Customer mix stays AAA-rated: Primary PPA counterparties will remain SECI, NTPC, and state governments; SECI is also procuring for green ammonia and data center demand.
- Contracted capacity trajectory: Management sees reaching 12 GW of contracted capacity by end of calendar 2027, with an incremental 5 GW of bids to be won in the next 12–18 months.
- ACME Cleantech demand is upside, not base case: The 15 GW target does not include any potential demand from ACME Cleantech for green ammonia or data centers; that could increase the target further.
- NTPC PPA tariff reduction disclosed: ~INR0.33/kWh reduction, split as INR0.11 tentative change in law and INR0.22 voluntary, while the battery was increased from 4 hours to 4.5 hours.
Dhingra: "They are not coming up with bids where there is no customer, and there is a pre-tie-up of customers because otherwise you cannot do these two months' bid-to-signing. It is impossible to do that otherwise."
Balance Sheet, Debt & Capex
- Debt cost stability is structural: 65% of borrowings are from PFC, REC, IREDA, and NaBFID, whose rates follow long-term cost of funds; these institutions have not increased base rates as frequently as MCLR-linked institutions over the last 5–10 years.
- Under-construction debt reprices on commissioning: Under-construction debt at 9%-plus is expected to move to substantially sub-9% post commissioning due to credit risk reduction, independent of the macro rate cycle.
- Refinancing is already underway: Two projects are being refinanced during the under-construction phase where the battery is commissioned and solar is near commissioning, because commissioning risk is largely out; good demand seen for such assets.
- Capex vs debt mismatch explained: Gross debt increased more than gross block in Q2 because disbursements were taken early on FDRE and peak power projects to push front-ended battery capex; there is a time delay between debt disbursement and utilization as LCs are opened at factory acceptance test, causing lumpy debt inflows before the corresponding capex hits gross block.
- No equity funding from operational debt: Management denied that more debt was taken on operational assets to fund equity for CWIP, stating this did not happen in the current or previous quarter.
- H2 capex to accelerate substantially: Expected to be higher than the INR6,500 crores spent in H1, driven by 5 GWh of batteries yet to be received and module deliveries at sites where batteries can be charged; the full 12 GWh of BESS is targeted for capitalization in FY27.
- 100% rupee book achieved: The entire book is now rupee-denominated after refinancing a higher-interest bond, with no dollar exposure, resulting in substantial interest saving this quarter.
Dhingra: "We don't foresee interest rate hikes from let's say INR 10,000 crores out of our INR 15,000 crores debt book, operational debt book, which is there."
Strategy 2.0 & Long-Term Targets
- Earnings quality over megawatt count: The new strategic plan focuses more on revenue and profit generation potential than absolute megawatt numbers.
- 15 GW and 50 GWh by 2030: Renewable target raised from 10 GW with 25 GWh BESS; management says the target is not at risk from GNA connectivity because target substations have timelines of 2028 to early 2029, and even a 6–12 month delay stays within the goal.
- FY28 capacity addition of 2.5–3 GW: Driven by substations coming alive from June to December; management is "very confident" of no further delays as elements are ready and work pace is good.
- Module procurement timed for FY28 commissioning: Plans to buy modules for new projects from June onwards next year, with commissioning targets of December to March 2028; initial ALMM 2 pricing negotiations indicate prices lower than INR17/W, with no risk of price increases from supplier shortage.
- Peak power project returns: On the INR6/kWh tariff project, management expects high-teen equity IRR factoring in 6–12 months of short-term operations; with ~24 months of early operations, returns could be higher.
Upadhyay: "Megawatts matter, but the measure we would hold ourselves to is earnings growth and the quality of these earnings."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 BESS commissioning | >12 GWh (raised from 10 GWh) | FY27 |
| Full commissioning | 1.5 GW, could slip by a quarter depending on GNA | FY27 |
| Partial commissioning | 2.5–3 GW | FY27 |
| H2 capex | Higher than INR6,500 cr; full 12 GWh BESS capitalized | H2 FY27 |
| Module charging (balance of 1.1 GW) | 900 MWp beyond the 200 MWp already charged | November–December 2026 |
| FY28 capacity addition | 2.5–3 GW, driven by substations coming alive June–December | FY28 |
| Contracted capacity | 12 GW | End of calendar 2027 |
| Incremental bid wins | 5 GW | Next 12–18 months |
| 2030 renewable target | 15 GW with 50 GWh BESS | 2030 |
| Future disclosures | Exact numbers to match 25% CUF benchmarking; external vs own solar for BESS charging | Next presentation |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Total revenue | ₹1,007 cr, up 67.5% YoY |
| EBITDA | ₹874 cr, up 63.6% YoY |
| Blended EBITDA margin | 86.7%, comprising 90.8% from renewable generation and 78.3% from BESS operations |
| Profit after tax | ₹269 cr, up 133.5% YoY; PAT margin of 26.7% |
| Asset base | ₹28,462 cr, grew by ₹11,466 cr over the year |
| Gross debt | ~₹26,500 cr, up from ~₹20,000 cr in Q1 FY27 |
| Weighted average cost of debt (operational projects) | ~8.4% |
| Cash balance | ₹10,000 cr, reflecting quarter-end debt disbursements |
| Capex spend in H1 FY27 | ₹6,500 cr, of which ₹3,500 cr capitalized and ₹3,000 cr in CWIP |
| FY27 BESS commissioning guidance | >12 GWh, raised from 10 GWh |
| 2030 renewable target | 15 GW with 50 GWh of battery, raised from 10 GW and 25 GWh |
| Contracted portfolio | 8,370 MW, with 92% now under signed PPAs |
| FDRE PPAs signed in Q2 | 430 MW, plus an additional 400 MW signed with NTPC post-quarter |
| Partially commissioned capacity | 1.9 GW of contracted projects |
| BESS capacity commissioned till date | ~5.2 GWh, second largest in India |
| CUF | 27.8%, improved from 24.1% YoY |
| Power generation | 184 crore units, up 19.6% YoY |
| Units sold via short-term peak power BESS contracts | 32.4 crore units |
| Short-term BESS revenue locked for FY27 | >₹1,600 cr for partial sale of FY27 capacity |
| Short-term BESS revenue locked for FY28 | >₹1,500 cr for partial sale of FY28 capacity |
| BESS capex capitalized | ₹90 lakh to ₹1 cr per MWh, benefiting from ~₹20 lakh per MWh savings via existing AC infrastructure |
| Credit rating | AA- positive, upgraded from AA- stable by CRISIL |