ACME Solar Holdings Ltd Q2 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/lhe5iydxk7uyyvx4teqaoqda.pdf

Key Takeaways


The BESS Engine: Performance, Margins & Self-Financing

Upadhyay: "On a rolling basis, we expect to operate around 10 gigawatt-hour of BESS subject to tariff realization. Its cash flows fund our growth and reduce the equity needed for new projects, making this a self-financing platform."

Commissioning & Capacity: Partial Is the Story

Dhingra: "Tracking the full commissioning does not mirror the revenue generation, because the BESS comes online early."

The BESS Market Opportunity: Displacing RTC

Dhingra: "In terms of the tariffs, of course the RTC at INR7 or INR6 is much more expensive than BESS at INR10, because you are buying unnecessary volume of power which you don't need to during the day when you contract out this RTC. And that volume is huge. Basically, the 85% of the near-term power is RTC, which is waiting to be disrupted."

PPA Portfolio & Bid Environment

Dhingra: "They are not coming up with bids where there is no customer, and there is a pre-tie-up of customers because otherwise you cannot do these two months' bid-to-signing. It is impossible to do that otherwise."

Balance Sheet, Debt & Capex

Dhingra: "We don't foresee interest rate hikes from let's say INR 10,000 crores out of our INR 15,000 crores debt book, operational debt book, which is there."

Strategy 2.0 & Long-Term Targets

Upadhyay: "Megawatts matter, but the measure we would hold ourselves to is earnings growth and the quality of these earnings."

Guidance & Commitments

CommitmentSpecificsTimeline
FY27 BESS commissioning>12 GWh (raised from 10 GWh)FY27
Full commissioning1.5 GW, could slip by a quarter depending on GNAFY27
Partial commissioning2.5–3 GWFY27
H2 capexHigher than INR6,500 cr; full 12 GWh BESS capitalizedH2 FY27
Module charging (balance of 1.1 GW)900 MWp beyond the 200 MWp already chargedNovember–December 2026
FY28 capacity addition2.5–3 GW, driven by substations coming alive June–DecemberFY28
Contracted capacity12 GWEnd of calendar 2027
Incremental bid wins5 GWNext 12–18 months
2030 renewable target15 GW with 50 GWh BESS2030
Future disclosuresExact numbers to match 25% CUF benchmarking; external vs own solar for BESS chargingNext presentation

Key Metrics

MetricQ2 FY27
Total revenue₹1,007 cr, up 67.5% YoY
EBITDA₹874 cr, up 63.6% YoY
Blended EBITDA margin86.7%, comprising 90.8% from renewable generation and 78.3% from BESS operations
Profit after tax₹269 cr, up 133.5% YoY; PAT margin of 26.7%
Asset base₹28,462 cr, grew by ₹11,466 cr over the year
Gross debt~₹26,500 cr, up from ~₹20,000 cr in Q1 FY27
Weighted average cost of debt (operational projects)~8.4%
Cash balance₹10,000 cr, reflecting quarter-end debt disbursements
Capex spend in H1 FY27₹6,500 cr, of which ₹3,500 cr capitalized and ₹3,000 cr in CWIP
FY27 BESS commissioning guidance>12 GWh, raised from 10 GWh
2030 renewable target15 GW with 50 GWh of battery, raised from 10 GW and 25 GWh
Contracted portfolio8,370 MW, with 92% now under signed PPAs
FDRE PPAs signed in Q2430 MW, plus an additional 400 MW signed with NTPC post-quarter
Partially commissioned capacity1.9 GW of contracted projects
BESS capacity commissioned till date~5.2 GWh, second largest in India
CUF27.8%, improved from 24.1% YoY
Power generation184 crore units, up 19.6% YoY
Units sold via short-term peak power BESS contracts32.4 crore units
Short-term BESS revenue locked for FY27>₹1,600 cr for partial sale of FY27 capacity
Short-term BESS revenue locked for FY28>₹1,500 cr for partial sale of FY28 capacity
BESS capex capitalized₹90 lakh to ₹1 cr per MWh, benefiting from ~₹20 lakh per MWh savings via existing AC infrastructure
Credit ratingAA- positive, upgraded from AA- stable by CRISIL