ACME Solar Holdings Ltd Q3 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/ldiuc25scuqbx3mgsxs5bory.pdf

Key Takeaways


The 1,200 MW Commissioning & Scale Shift

Manoj K Upadhyay: "This quarter has been a very, very important thing for us because this 1,200 MW, one of the biggest projects we were making and it was important for us to achieve it."

PPA Pipeline & Revenue Visibility


Balance Sheet & Funding Strategy

Nikhil Dhingra: "on this capacity, we don't think we will need to raise equity because these commissionings are taking us to 2028... the cash flows and the securitization, the EPC margins from these three years will hold us in good stead in terms of funding these projects."

Growth Roadmap & Bidding Strategy

Manoj K Upadhyay: "I have seen in many interaction that people had some concern on FDRE, although, yes, FDRE is not this thing because we have been forecasting our power under deviation settlement mechanism for last four, five years. So, technically it is the same deviation settlement mechanism and forecasting with the battery inside which will improve it further."

Regulatory & Policy Landscape

Manoj K Upadhyay: "if there is a delay or if there is an embargo in US, I think there are two, three advantages what IPP will be able to get... people who are selling module at higher price in the US... those modules will be available cheaper to IPP even in India... some of the ESG fund... if there is a slowness in US deployment, maybe they will come and do some project here."

Execution & Organizational Build-Out


Guidance & Commitments

CommitmentSpecificsTimeline
Operational run-rate₹1,750-₹1,800 crores annual revenue from 2,540 MW baseCurrent run-rate
Pre-tax ROCEMaintain 14.5%Ongoing
Capacity target6,970 MW operatingBy FY27-28, efforts to prepone
350 MW commissioningCommission 350 MW (300 MW merchant + 50 MW wind)Q4 FY25; April spillover worst case
100 MW wind commissioningCommission 100 MW windBest case June-September quarter
PPA signing for 2,090 MWSign remaining PPAs (380 MW, 350 MW FDRE, NTPC, others)Top ones shortly; rest in max couple of months
Tariff adoption ordersCERC orders on reserved statusNext couple of months
Net debt-to-EBITDA ceilingStay below 5.5XOngoing; currently ~5X
ALCM tariff resetTemporary shift into ALCM regime, tariff reset on solar sideExpected by March or so
10 GW targetProjects finished, commissioning in 2026 and 2027By calendar 2028
Land for PPA-signed projectsFully in placeIdeally 6 months, worst case 9-12 months from PPA signing
FDRE pilot projectSet up one small FDRE projectNext 3-4 months

Key Metrics

MetricQ3 FY25
Total revenue₹401 cr, up 45% on adjusted basis and 10% on reported basis YoY
EBITDA₹359 cr, up 59% on like-to-like basis and 15% on reported basis YoY
EBITDA margin~90% on reported basis, driven by higher operating leverage
PAT₹112 cr, up 152% on reported basis and 317% on like-to-like asset basis YoY
PAT margin28%, compared to 12% in Q3 FY24
Cash PAT₹189 cr, up 52% on reported basis and 149% on like-to-like asset basis YoY
Net debt₹6,882 cr, down from ₹8,755 cr in Q2 FY25; net debt-to-equity at 1.6X
Net operational debt-to-annual EBITDA~5X, below guided range of 5.5X
Operational capacity2,540 MW, up 90% from 1,340 MW after commissioning 1,200 MW SECI project
Total contracted portfolio6.97 GW, with 1,900 MW won in FY25 (FDRE 1,000 MW, solar 600 MW, hybrid 300 MW)
PPAs signed (under-construction portfolio)2,340 MW out of 4,430 MW under-construction capacity
Tariff adoption completed2,500 MW, more than 50% of under-construction capacity
CUF23.7%, improved YoY; expected to increase further with higher-CUF projects in portfolio
Plant availability99.4%; grid availability at 99.6%
Units generated (9M FY25)~250 crore units, a jump of 34.5% YoY
Operational project EBITDA run rate₹1,750–₹1,800 cr annually from 2,540 MW operational assets
Pre-tax ROCE14.5% on operational project gross block
Greenfield debt sanctioned₹16,500 cr, covering ~40% of under-construction project debt
Debt refinanced~₹5,500 cr (50–55% of total debt) at average rate of 8.8% per annum, reducing cost by ~70 bps
Securitization proceeds raised (9M FY25)₹650 cr from refinancing of ₹5,500 cr
CAPEX incurred (9M FY25)~₹3,500 cr; ~₹800 cr CAPEX expected over next two quarters
1,200 MW SECI project gross block₹4,600 cr, net of EPC margin
1,200 MW SECI project Q3 revenue contribution₹80 cr, with 90% EBITDA margin; annual EBITDA potential ~₹720 cr at 30% CUF
Merchant capacity300 MW; SECI PPA won at tariff of ₹3.05 for 25 years
Standalone employee benefits (9M FY25)₹36 cr, up from ₹24 cr YoY, including ~₹12 cr RSU charge
Standalone taxes paid (Q3)₹6 cr