ACME Solar Holdings Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/6ylzbdj28iumdkyargjti12z.pdf

Key Takeaways


Battery Energy Storage: The New Growth Engine

Nikhil Dhingra: "1 gigawatt hour of battery results in around 170 crores of EBITDA if operated for 12 months and this is assuming a Rs. 5 arbitrage between buy and sell price."

PPA Signing: The Conversion Challenge

Nikhil Dhingra: "The only hitch which was coming was, there are concurrent offerings of similar kind outstanding from various bidding agencies, which is making the choice difficult for these buyers."

Curtailment: Contained Today, Unresolved Tomorrow

Nikhil Dhingra: "So, in terms of our revenue, because of the regulations, there is no impact. Because this was made keeping in mind the must-run status of renewables, keeping in mind that the revenue needs to be paid because nobody is at fault."

Operational & Financial Performance

Nikhil Dhingra: "So, this is temporary because there is, of course, a glut there and we do not see this impact of even Rs. 1 lasting for more than a couple of months."

Capacity Build-Out & Capex

Nikhil Dhingra: "When we plan a project, we plan a particular set of sites, which we keep on developing. Of course, we don't order batteries, we don't order modules, and we don't take any financing, till then we push through our equity, and this is not sudden."

Technology & Competitive Positioning

Manoj Kumar Upadhyay: "We are also creating a policy framework for the entire industry and we are also doing something on the technology side."

Guidance & Commitments

CommitmentSpecificsTimeline
BESS commissioning2 GWh operationalQ4 FY26
BESS commissioningAdditional 2 GWh operationalQ1 FY27
BESS commissioningMore than 10 GWh cumulativeCalendar year 2027
FY26 renewable commissioning450 MW (balance 28 MW at advanced stages)FY26
FY27 renewable commissioningApproximately 1.5 GW of contracted capacityFY27
FY28 renewable commissioning1.1 GWFY28
Wind project COD72 MW (balance to complete)Early February
FDRE project COD190 MWFY27
NHPC project COD250 MWFY28
Operational capacity target10 GWBy 2030
PPA signing770 MW near-term (buyer approval obtained)Near term (no date)
Capex₹12,000 crores for FY27 capacityFY27
Capex₹10,000 crores for FY28 capacityFY28
Project return thresholdHigh-teen returns (minimum 16% IRR)Ongoing

Key Metrics

MetricQ3 FY26
Revenue₹617 cr, +54% YoY
EBITDA margin91.5%, vs 89.6% last year
PAT₹114 cr, margin of 18.4%
Cash ROE20.6% for December '25
Net operational debt to EBITDA4.2x
Net debt to net worth2x
Weighted average cost of debt (operational portfolio)8.45% per annum, down over 100 bps from December '24
Weighted average cost of debt (total outstanding)