Key Takeaways
- Execution beat, guidance raised: Revenue rose 54% YoY to ₹617 crore while the BESS commissioning target was doubled from 1 GWh to 2 GWh for Q4 FY26, with another 2 GWh now promised in Q1 FY27.
- The battery pivot is real and early: 1,150 MWh of BESS already delivered across three sites, and management now targets 10 GWh of BESS commissioned by calendar year 2027, pulling forward value from the FDRE pipeline.
- PPA backlog is deep but lumpy: Near-term visibility of 770 MW in PPA signings sits on top of 2.6 GW already signed, yet the pace of conversion depends on state-level decision-making that management cannot control.
- Margins are structurally high but curtailment risk is unresolved: EBITDA margin reached 91.5%, though a one-time ₹17.5 crore curtailment hit at Sikar and open questions about structural curtailment as renewables penetration rises leave the durability of that margin untested.
- What to watch next quarter: Whether the 770 MW of PPAs actually get signed, the pace of BESS commissioning against the upgraded 2 GWh target, and any clarity on the DSM regulation impact from April 2026.
Battery Energy Storage: The New Growth Engine
- Guidance doubled mid-year: BESS commissioning target raised from 1 GWh to 2 GWh operational in Q4 FY26, with an additional 2 GWh in Q1 FY27, reflecting faster site readiness and procurement execution.
- Early delivery de-risks the pipeline: 1,150 MWh of BESS already delivered at three sites and at advanced stages of commissioning; CEA approval secured for over 580 MWh with 1.2 GWh of equipment lying at sites.
- 10 GWh by CY2027: Management is fast-tracking BESS installation across its 10 GW FDRE project pipeline, aiming for more than 10 GWh of BESS commissioned by calendar year 2027 to unlock value early.
- Economics are attractive and modular: Each 1 GWh of battery operated for 12 months yields approximately ₹170 crore of EBITDA, assuming a ₹5 arbitrage between buy and sell price; batteries are designed for 1.6 cycles per day, charging during cheap solar hours for evening peak and nighttime for morning peak.
- Procurement advantage is real but narrow: Global battery capacity exists, but only developers with operational connectivity can take delivery quickly since batteries degrade after six months; ACME can order at short notice while few competitors can take deliveries in the March-May window.
- Infrastructure is the moat: Transmission infrastructure, the long lead item, is already in place at all sites; battery installation is modular and CEA approval can be obtained in phases with seven-day prior notice.
Nikhil Dhingra: "1 gigawatt hour of battery results in around 170 crores of EBITDA if operated for 12 months and this is assuming a Rs. 5 arbitrage between buy and sell price."
PPA Signing: The Conversion Challenge
- Near-term visibility is substantial but not guaranteed: 770 MW of additional PPA signing expected in the near term, backed by PSA consent already secured from Discoms for 640 MW with regulatory approval at an advanced stage.
- A deeper pipeline sits behind it: Approximately 700 MW more under advanced discussion but without written buyer approval, plus roughly 750 MW of FDRE hybrid PPA at a very advanced stage, suggesting the total near-term opportunity could exceed 2 GW.
- The bottleneck is buyer decision-making, not supply readiness: Concurrent offerings from multiple bidding agencies create a glut of supply, making choice difficult for state buyers; power demand trends and state elections also cause delays.
- ISTS waiver creates a closing window: The ISTS waiver expiring in phases between 2026 and 2028 makes CTU-connected projects increasingly attractive to states without good renewable resources, combining supply-side preparedness with demand-side urgency.
- Project planning hedges the lumpiness: Sites are developed continuously with land and transmission lines in place before PPA signing; long lead items like power transformers are ordered in advance, while batteries, modules, and financing wait until the PPA is signed.
- Signed backlog stands at 2.6 GW: Around 2.6 GW of signed PPAs underpin the FY27 and FY28 commissioning plans, with 1.5 GW of contracted capacity targeted for installation in FY27 and 1.1 GW in FY28.
Nikhil Dhingra: "The only hitch which was coming was, there are concurrent offerings of similar kind outstanding from various bidding agencies, which is making the choice difficult for these buyers."
Curtailment: Contained Today, Unresolved Tomorrow
- Sikar hit was material but resolved: A one-time curtailment loss of ₹17.5 crore at the Sikar 300 MW project occurred due to operations under temporary GNA during the quarter; with the Narela Khetri line commissioned from December 14, 2025, Sikar is now operating at full capacity without curtailment.
- Revenue protection exists, but volume risk does not: Under TRAS-Down regulations for grid stability, the state must pay for the same amount of units it was supposed to get, so revenue is protected; however, management did not directly address whether the quantum of curtailment could increase to problematic levels as renewables penetration rises.
- State-level curtailment is minor for now: Curtailment at the state level is less than ₹1 crore; regulators are described as sympathetic, and states are aggressively picking up batteries which management expects will reduce the problem.
- DSM regulations are a known unknown: New DSM regulations are coming in phases till 2030; solutions being contemplated include making them prospective rather than retrospective, installing batteries at existing plants, and allowing excess battery capacity to be sold in the merchant market, but management gave no specific assessment of impact on ACME.
- The structural question was deflected: When asked whether curtailment could become a structural 5-10% revenue impact given supply-demand mismatch, management pointed to regulatory revenue protection without addressing whether curtailment volumes themselves could escalate.
Nikhil Dhingra: "So, in terms of our revenue, because of the regulations, there is no impact. Because this was made keeping in mind the must-run status of renewables, keeping in mind that the revenue needs to be paid because nobody is at fault."
Operational & Financial Performance
- Revenue growth driven by capacity and efficiency: Total revenue of ₹617 crore, up 54% YoY, driven by capacity addition and higher CUF which improved to 24.3% from 22.7% last year.
- Margin expansion from operating leverage: EBITDA margin improved to 91.5% from 89.6% last year on account of favorable operating leverage and optimized operational efficiency.
- Debt cost falling: Weighted average cost of debt for the operational portfolio reduced to 8.45% per annum, down by over 100 bps from December 2024, through successful refinancing and credit rating upgrades.
- China VAT impact is manageable and temporary: The withdrawal of China's VAT export rebates on modules impacts landed cost by not more than ₹1-1.5 per unit; 50% of modules were already procured before the change, so only 30-40% of additional capacity faces the impact, and management expects it to last no more than a couple of months due to supply-demand dynamics.
- Project costs remain within budget: Equipment is being ordered within budgeted cost; April delivery post-regulation is at a price much less than the budgeted cost which assumes high-teen returns.
- Wind project delay overcome: The wind project was delayed due to a sand mining ban in Gujarat and extended rains impacting pathway construction; the issue has been overcome and the project is expected to reach COD in early February.
Nikhil Dhingra: "So, this is temporary because there is, of course, a glut there and we do not see this impact of even Rs. 1 lasting for more than a couple of months."
Capacity Build-Out & Capex
- FY26 commissioning on track: On track to achieve FY26 commissioning guidance of 450 MW, with the balance 28 MW at advanced stages of construction; 72 MW of wind capacity already commissioned during Q3 to date.
- FY27 is the inflection year: Intend to execute approximately 1.5 GW of contracted renewable capacity in FY27, with commissioning starting from Q2 FY27; BESS commissioning of 4 GWh planned for FY27.
- FY28 follows with 1.1 GW: An additional 1.1 GW of capacity targeted for commissioning by FY28, including the 250 MW NHPC FDRE project signed under the Greenshoe option at ₹4.33 per unit.
- Capex is back-end loaded: ₹12,000 crores planned for FY27 capacity and ₹10,000 crores for FY28, inclusive of BESS cost; financing is not drawn until PPAs are signed, with equity pushed through during development.
- Connectivity inventory provides visibility to 2030: About 7.5 GW of secured and applied connectivity inventory available for upcoming bids, coming live in phases till FY33.
- 10 GW operational target by 2030: Management reiterated the target of 10 GW operational capacity by 2030, underpinned by the connectivity inventory and PPA pipeline.
Nikhil Dhingra: "When we plan a project, we plan a particular set of sites, which we keep on developing. Of course, we don't order batteries, we don't order modules, and we don't take any financing, till then we push through our equity, and this is not sudden."
Technology & Competitive Positioning
- Patent applications signal IP ambition: Applied for patents in 2-3 areas related to optimization of battery and renewable wind, aiming to provide base load power similar to nuclear and cheaper than thermal or nuclear.
- Next-generation technology in testing: Already testing Perovskite technology, which management believes will be useful in coming years.
- Robotics to solve the scaling problem: Created a special team focusing on automation and implementing robotics for module installation, addressing the challenge of scaling from 2 GW to 5-6 GW per year of execution.
- Battery life assumptions are conservative: Modern batteries are designed for 18-20 years, but the business model assumes replacement at 12-13 years; replacement is cell replacement only, with associated infrastructure not needing replacement, so early revenue realization generates good IRR on that capex.
- Green hydrogen remains a promoter-level call option: The green hydrogen business sits in a promoter entity; the GAPA is not yet signed but may get signed in a quarter or so; no decision has been made on whether ACME Solar will supply power to that entity, and management has not yet evaluated in detail whether it makes sense to do so.
Manoj Kumar Upadhyay: "We are also creating a policy framework for the entire industry and we are also doing something on the technology side."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| BESS commissioning | 2 GWh operational | Q4 FY26 |
| BESS commissioning | Additional 2 GWh operational | Q1 FY27 |
| BESS commissioning | More than 10 GWh cumulative | Calendar year 2027 |
| FY26 renewable commissioning | 450 MW (balance 28 MW at advanced stages) | FY26 |
| FY27 renewable commissioning | Approximately 1.5 GW of contracted capacity | FY27 |
| FY28 renewable commissioning | 1.1 GW | FY28 |
| Wind project COD | 72 MW (balance to complete) | Early February |
| FDRE project COD | 190 MW | FY27 |
| NHPC project COD | 250 MW | FY28 |
| Operational capacity target | 10 GW | By 2030 |
| PPA signing | 770 MW near-term (buyer approval obtained) | Near term (no date) |
| Capex | ₹12,000 crores for FY27 capacity | FY27 |
| Capex | ₹10,000 crores for FY28 capacity | FY28 |
| Project return threshold | High-teen returns (minimum 16% IRR) | Ongoing |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue | ₹617 cr, +54% YoY |
| EBITDA margin | 91.5%, vs 89.6% last year |
| PAT | ₹114 cr, margin of 18.4% |
| Cash ROE | 20.6% for December '25 |
| Net operational debt to EBITDA | 4.2x |
| Net debt to net worth | 2x |
| Weighted average cost of debt (operational portfolio) | 8.45% per annum, down over 100 bps from December '24 |
| Weighted average cost of debt (total outstanding) |