ACME Solar Holdings Ltd Q4 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/nk55x8fa7v19wsihxee1h61t.pdf

Key Takeaways


Capacity Ramp-Up & Execution

Upadhyay: "PPA signing, we were expecting to sign 400 to 500 megawatt last quarter, but unfortunately it shifted to this quarter. So, this forecasting of signing the PPA is one learning I think we have to build inbuilt in our system."

PPA Signing & Revenue Visibility

Dhingra: "What we are trying to do, rather than being aggressive on the bids, is being aggressive on the execution ahead of time, like we have already built a merchant plant in Sikar. So, that plant is a very big strategic advantage for us because we can plug into any of these PPAs which we get or which we have not got still and commission it immediately."

Merchant & Battery Strategy

Dhingra: "The good thing about batteries is that and good thing about our portfolio is that we have a large proportion of that in the central connected projects, right? So, out of our operational capacity, more than 60%-70% is now connected to the central grid. And that allows us to maybe, if we are able to execute faster, play the merchant market on the battery side."

Balance Sheet & Cost of Capital

Dhingra: "This refinancing would yield a significant benefit, reducing the average interest rate on these projects by about 75 basis points, and we expect this refinancing benefit to compound further, given the interest rate trajectory and the credit rating profile of our assets, which is improving."

Project Pipeline & FY30 Ambition


Guidance & Commitments

CommitmentSpecificsTimeline
Sikar plant full commissioningRemaining ~135 MW onlineNext 30 days
Wind project commissioning26.5 MW this week; balance 100 MW in phasesEarly Q2 to later Q2
Operational capacity milestoneTouch ~3 GWSoon after near-commissioning projects complete
PPA signingThree PPAs aggregating ~750 MW at final stageHopeful to sign very soon
Balance PPA signingTwo partially signed PPAs (190 MW FDRE, 200 MW solar+battery)Hopeful in about a month
BESS pilot commissioning200 MW pilot at operational sitesLatter part of Q2
Large-scale BESS commissioningLarge-scale projectQ3
FDRE project COD190 MW of 380 MW FDREJune 2026
SJVN project COD320 MW and 250 MW (~570 MW)May 2026 per PPA
FY26 capacity addition450 MW AC (600 MW DC peak)Per PPA timelines
FY27 capacity addition1.89 GW (all PPAs signed)FY27
FY30 contracted capacity target7 GW contracted (20 GW+ installed)FY30

Key Metrics

MetricQ4 FY25
Total revenue (like-to-like)₹539 cr, up 73% YoY
EBITDA (like-to-like)₹488 cr, up 119% YoY
EBITDA margin (full year)Over 89%
PAT₹122 cr
Cash PAT₹238 cr
Full-year total revenue₹1,575 cr, up 32% YoY
Full-year EBITDA~₹1,400 cr, up 43% YoY
Full-year PAT₹251 cr, up 290% YoY
Full-year cash PAT₹559 cr, up 155% YoY
Operational capacity~2,700 MW, expected to reach ~3 GW soon
Capacity utilization factor (CUF)25.6% for FY25
Rajasthan portfolio CUF29.4% on an annualized basis
Generation~401 crore units, up 55% YoY
Plant availability factor99.5%
Under construction locked-in capacity4.3 GW, of which 2.2 GW PPA signed and 2.1 GW LOA awarded
Net operational debt to EBITDA4.4x, within guided range of 5.5x
Net debt to net worth1.7x
Cash and bank balances~₹2,900 cr as of FY25
Refinancing sanctions secured~₹7,700 cr at 8.8% average interest rate, reducing rates by ~75 bps
Credit rating (Crisil)A+ with positive outlook, upgraded February 2025
FY26 capacity addition target450 MW AC, ~600 MW DC peak
FY27 capacity addition target1.89 GW
Sikar merchant tariff realized~₹3.1 per unit
Sikar run-rate top line (fully operational)₹230 to ₹240 cr