Key Takeaways
- Capacity-led earnings surge: Revenue rose 73% YoY and EBITDA 119% YoY in Q4, driven by the partial commissioning of the 1,200 MW Rajasthan portfolio and strong plant performance.
- Merchant strategy unlocks value: The 300 MW Sikar plant will initially sell into the merchant market at ~₹3.1/unit before moving to a PPA, a deliberate bet on execution speed over aggressive bidding.
- Balance sheet transformed by refinancing: A ₹7,700 crores debt refinancing at 8.8% cut interest costs by ~75 bps, with further compression expected as credit ratings improve and base rates fall.
- Wind risk is being engineered out: Battery price declines have reduced wind’s strategic role in FDRE plans; solar-plus-battery now competes well, and wind components are kept low in new projects.
- What to watch next quarter: Whether the three PPAs aggregating ~750 MW actually get signed, the pace of commissioning for the remaining ~135 MW at Sikar and the 100 MW wind project, and any update on the Omega Urja 300 MW PPA delay.
Capacity Ramp-Up & Execution
- Near-commissioning pipeline: 450 MW is near commissioning, headlined by the 300 MW Sikar solar plant where 165 MW and 112.5 MW are already online; the remaining ~135 MW is expected within 30 days. A 50 MW wind project is under commissioning with 26.5 MW approved, and the balance 100 MW wind is at an advanced stage with equipment on site.
- Operational scale tipping point: Total operational capacity will touch ~3 GW once these near-commissioning projects come online, up from ~1,365 MW currently.
- Generation growth powered by Rajasthan: 401 crore units generated in Q4, a 55% YoY increase, as the 1,200 MW SECI ISTS project in Rajasthan’s high-radiation Fatehgarh zone began contributing. That project achieved 32% CUF in its first quarter, lifting the overall portfolio CUF to 25.6% for the year.
- CUF has further room to run: The 25.6% full-year CUF includes only three months of the 1,200 MW plant; a full-year run in FY26 will push the number higher. Rajasthan plants already deliver 29.4% CUF, and the new 300 MW Sikar plant is also in Rajasthan.
- Commissioning friction is real: The Sikar plant slipped ~60 days past its 31 March target, partly due to India-Pakistan tensions that forced a temporary shutdown of installation work. Regulatory requirements for power factor correction, harmonics and flickering are also increasing, as the government enforces grid stability compliance.
Upadhyay: "PPA signing, we were expecting to sign 400 to 500 megawatt last quarter, but unfortunately it shifted to this quarter. So, this forecasting of signing the PPA is one learning I think we have to build inbuilt in our system."
PPA Signing & Revenue Visibility
- Three PPAs at the final stage: Agreements aggregating ~750 MW are in advanced discussions and management is hopeful of signing them very soon. Two of these are partially signed: a 190 MW FDRE and a 200 MW solar-plus-battery project at ~₹3.42/unit.
- Omega Urja delay remains unexplained: The 300 MW pure solar project won at a ₹2.52 tariff, one of the few remaining pure solar tenders, has still not been signed. Management cited structural reasons (utilities now prefer evening/morning power from solar-plus-battery or FDRE, and the ISTS waiver is tied to commissioning date not PPA date) but offered no specific trigger for the holdup.
- Policy tailwind on PPA timelines: New bidding policies now require tariff adoption within a month of the bid and a binding timeline for PPA signing, which should reduce future forecasting risk.
- Construction gated by PPA: The company will not deploy capex on projects until a PPA is signed, even where construction has begun. Roughly 2 GW of capacity will shift beyond FY27 for this reason.
Dhingra: "What we are trying to do, rather than being aggressive on the bids, is being aggressive on the execution ahead of time, like we have already built a merchant plant in Sikar. So, that plant is a very big strategic advantage for us because we can plug into any of these PPAs which we get or which we have not got still and commission it immediately."
Merchant & Battery Strategy
- Sikar as a strategic option: The 300 MW plant will operate in the merchant market initially, where management has realized an average price of ~₹3.1/unit. The plant benefits from an ISTS waiver and can be moved into a PPA when an attractive opportunity arises.
- Battery procurement advantage: Batteries are sourced from tier-1 Chinese suppliers at prices well below initial bid budgets. The large proportion of operational capacity (60-70%) connected to the central grid allows faster execution and the ability to play the merchant market on the battery side.
- Battery financing hurdle cleared: ₹16,500 crores of financing has been obtained for battery components, with leading lenders now comfortable with the technology. Government support through the PLI scheme and state-level battery procurement has improved lender understanding.
- Battery commissioning timeline: A 200 MW pilot project at existing operational sites is targeted for the latter part of Q2, with large-scale battery commissioning following in Q3.
- Wind’s diminished role: Battery price declines mean solar-plus-battery now competes well with wind, whose output has significantly underperformed in two of the last five years. Wind components are kept very low in FDRE projects; in hybrid tenders, only the mandatory minimum one-third wind component is included.
Dhingra: "The good thing about batteries is that and good thing about our portfolio is that we have a large proportion of that in the central connected projects, right? So, out of our operational capacity, more than 60%-70% is now connected to the central grid. And that allows us to maybe, if we are able to execute faster, play the merchant market on the battery side."
Balance Sheet & Cost of Capital
- Refinancing delivers immediate relief: ₹7,700 crores of project debt was refinanced at an average rate of 8.8%, reducing interest cost by ~75 bps. Only one project (300 MW of the 1,200 MW ISTS portfolio) has been refinanced so far, leaving further headroom.
- Credit rating trajectory improving: Crisil upgraded the corporate rating to A+ with a positive outlook in February 2025. The 750 MW operational portion of the 1,200 MW project received an AA- rating within two to three months of commissioning, reflecting strong operational performance and the AAA-rated counterparty.
- Leverage metrics comfortable: Net operational debt to EBITDA stands at 4.4x, better than the guided 5.5x. Net debt to net worth improved to 1.7x, and the gross block expanded by ₹4,100 crores to ₹15,500 crores, with cash of ₹2,900 crores on hand.
- Cost of debt has further to fall: The current borrowing rate for AA-rated assets is 8.5-8.6%. Further reduction depends on macroeconomic rate cuts and credit rating upgrades across the remaining 1,200 MW portfolio. Already-refinanced debt is locked in for a year.
Dhingra: "This refinancing would yield a significant benefit, reducing the average interest rate on these projects by about 75 basis points, and we expect this refinancing benefit to compound further, given the interest rate trajectory and the credit rating profile of our assets, which is improving."
Project Pipeline & FY30 Ambition
- FY26 capacity addition: 450 MW AC (600 MW DC peak) is scheduled for commissioning per PPA timelines.
- FY27 capacity addition: 1.89 GW is coming up, with all PPAs already signed. Under-construction projects include 190 MW of a 380 MW FDRE (COD June 2026) and 570 MW of SJVN projects (timeline May 2026 per PPA). Management may try to prepone FDRE commissioning by building on a short-term open access basis, though this yields lower realization.
- 10 GW target by FY30: The target is 7 GW of contracted capacity, with installed capacity reaching 20 GW+. The mix will be FDRE and hybrid, staggered across years to avoid concentration.
- Land is the binding constraint: Large contiguous land parcels are the primary execution bottleneck. The company is trying to secure large portions of government land to improve per-year execution capacity.
- PSP project progressing slowly: A 600 MW/6-hour pumped storage project in Uttar Pradesh is close to stage-one forest approval and in discussions with CEA for DPR approval. Management will not build it on a merchant basis, only with a PPA, and will factor in approval timelines.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Sikar plant full commissioning | Remaining ~135 MW online | Next 30 days |
| Wind project commissioning | 26.5 MW this week; balance 100 MW in phases | Early Q2 to later Q2 |
| Operational capacity milestone | Touch ~3 GW | Soon after near-commissioning projects complete |
| PPA signing | Three PPAs aggregating ~750 MW at final stage | Hopeful to sign very soon |
| Balance PPA signing | Two partially signed PPAs (190 MW FDRE, 200 MW solar+battery) | Hopeful in about a month |
| BESS pilot commissioning | 200 MW pilot at operational sites | Latter part of Q2 |
| Large-scale BESS commissioning | Large-scale project | Q3 |
| FDRE project COD | 190 MW of 380 MW FDRE | June 2026 |
| SJVN project COD | 320 MW and 250 MW (~570 MW) | May 2026 per PPA |
| FY26 capacity addition | 450 MW AC (600 MW DC peak) | Per PPA timelines |
| FY27 capacity addition | 1.89 GW (all PPAs signed) | FY27 |
| FY30 contracted capacity target | 7 GW contracted (20 GW+ installed) | FY30 |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Total revenue (like-to-like) | ₹539 cr, up 73% YoY |
| EBITDA (like-to-like) | ₹488 cr, up 119% YoY |
| EBITDA margin (full year) | Over 89% |
| PAT | ₹122 cr |
| Cash PAT | ₹238 cr |
| Full-year total revenue | ₹1,575 cr, up 32% YoY |
| Full-year EBITDA | ~₹1,400 cr, up 43% YoY |
| Full-year PAT | ₹251 cr, up 290% YoY |
| Full-year cash PAT | ₹559 cr, up 155% YoY |
| Operational capacity | ~2,700 MW, expected to reach ~3 GW soon |
| Capacity utilization factor (CUF) | 25.6% for FY25 |
| Rajasthan portfolio CUF | 29.4% on an annualized basis |
| Generation | ~401 crore units, up 55% YoY |
| Plant availability factor | 99.5% |
| Under construction locked-in capacity | 4.3 GW, of which 2.2 GW PPA signed and 2.1 GW LOA awarded |
| Net operational debt to EBITDA | 4.4x, within guided range of 5.5x |
| Net debt to net worth | 1.7x |
| Cash and bank balances | ~₹2,900 cr as of FY25 |
| Refinancing sanctions secured | ~₹7,700 cr at 8.8% average interest rate, reducing rates by ~75 bps |
| Credit rating (Crisil) | A+ with positive outlook, upgraded February 2025 |
| FY26 capacity addition target | 450 MW AC, ~600 MW DC peak |
| FY27 capacity addition target | 1.89 GW |
| Sikar merchant tariff realized | ~₹3.1 per unit |
| Sikar run-rate top line (fully operational) | ₹230 to ₹240 cr |