ACME Solar Holdings Ltd Q4 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/0yzs7vd9upie8w461tl3cps2.pdf

Key Takeaways


The Battery Story: Merchant Arbitrage Now, FDRE Later

Manoj Upadhyay: "Right now, the current calculation of CEA is you need around 200 gigawatt hour of battery to come to this if you don't add any more solar. But what is happening is also another 40, 50 gigawatt of FDRE and this one where the tender has happened, they will get added in the daytime. So technically, what is happening as long as you are adding more and more daytime solar, you need a more battery in the unit."

Revenue Quality: Central Offtakers Are Reshaping the Balance Sheet

Nikhil Dhingra: "all our CTU connected projects with CTU connected substations, where you are regulatory protected from the customer payments are there irrespective of, you can say, the grid curtailment."

Commissioning Pipeline: 1.5 GW + 10 GWh in FY27


Bid Strategy: Peak Power Is the Only Game That Sells

Manoj Upadhyay: "the overall solar or overall the capex requirement will be higher than the last year because what is going to happen in the plain vanilla solar will be INR3 crores, INR4 crores, INR4 crores per megawatt. But the current bid, which is happening, for example, mimicking the thermal power or mimicking that long hour duration storage, solar storage, they will be – actually they will carry a very large solar behind the battery."

Returns & Capital Allocation: High Teens With Battery Included

Nikhil Dhingra: "So basically, it is -- what happens is most of the states want battery installation along with the project. So it basically keeps the return in high teens only. So it does not impact really the returns from this thing. But of course, we need to satisfy the customer requirement in terms of the power mix they want because everybody needs peak power now. So that is where we need to offer that 1 hour of battery, yes."

Regulatory & Policy Tailwinds


Guidance & Commitments

CommitmentSpecificsTimeline
Generation commissioning1.5 GW of generation assetsFY27
Battery commissioning~10 GWh total (~8.5 GWh merchant, ~1.5 GWh FDRE)FY27
Under-construction portfolio completion3,280 MW + 12 GWh BESS fully commissionedBy FY28
Battery arbitrage sustainabilityPeak power prices elevated, merchant strategy viableAt least 4-5 years
Neemuch substation chargingCommission NHPC and Tata FDRE plantsJune (next quarter)
Fatehgarh long-term open accessSJVN 570 MW FDRE readyMarch '27
NTPC project commissioningSolar ready, wind a couple of quarters later; all commissionedBy March '27
Debt refinancing impactInterest rate reduction of ~150 bps on INR 3,300 crCompleted (Q4 FY26)

Key Metrics

MetricQ4 FY26
Revenue₹705 cr, +31% YoY; FY26 revenue ₹2,507 cr, +59% YoY
Other income₹157 cr in Q4, primarily recurring interest from SPV cash and DSRA balances
EBITDA marginOver 90% for Q4 and full year, driven by operating leverage and operational efficiency
PAT₹138 cr for Q4, margin 19.6%; FY26 PAT ₹498 cr, margin 19.9%
Units generated172 crore units in Q4, +13% YoY; FY26 646.4 crore units, +61% YoY
CUF26.9% in Q4; full-year portfolio CUF close to 26%
Grid and plant availabilityOver 99% for the year
Operational generation contracted capacity2,990 MW
BESS capacity commissioned to date~2.3 GWh, delivering net realization of ~₹2.2 cr per day, round trip efficiency 88–90%
Under construction portfolio5.1 GW total, PPA signed capacity 3,280 MW; will require ~17 GWh BESS
Total portfolio8,071 MW
Committed total capex₹12,475 cr, including ₹6,445 cr incurred during FY26 and ₹6,030 cr in purchase orders
Financing secured during FY26~₹15,000 cr for under construction projects
Debt refinanced₹3,300 cr for operational projects, reducing interest rate by ~150 bps
Weighted average cost of debt (operational projects)8.4% per annum
Credit ratingAA- stable assigned to 2.2 GW of operational projects
Curtailment impact (full year)₹5–6 cr real curtailment; ₹3 cr on STU in Rajasthan; ₹2–3 cr from grid maintenance
DSO14 days, down from 180 days historically; trade receivables down 13% YoY
FY27 commissioning target1.5 GW generation assets and ~10 GWh battery; ~8.5 GWh of battery to start on merchant basis