Key Takeaways
- 59% revenue growth, battery just getting started: FY26 revenue hit INR 2,507 crores, but the 2.3 GWh of commissioned BESS contributed almost nothing in Q4, setting up a material new revenue stream for FY27.
- 90%-plus EBITDA margins are structural, not a one-off: Operating leverage and efficiency delivered over 90% margins for both Q4 and the full year, with the portfolio now shifting toward 100% central offtakers that pay in ~10-15 days.
- The battery arbitrage window is wide open and management expects it to stay that way: Merchant BESS is earning ~INR 2.2 crores/day at ~75-80% EBITDA margins by charging from the grid and selling at peak, a strategy management believes can run for 4-5 years.
- A capex deferral playbook is protecting returns while CTU infrastructure catches up: When substations are delayed, ACME defers module procurement (60% of solar capex) and instead charges batteries from the grid for merchant sales, saving interest during construction.
- What to watch next quarter: The pace of battery commissioning toward the 10 GWh target, whether peak power prices hold through the monsoon, and progress on signing the 850 MW of older PPAs still in discussion.
The Battery Story: Merchant Arbitrage Now, FDRE Later
- 2.3 GWh commissioned, negligible Q4 revenue: Battery assets were just getting started in the March quarter, so the INR 2.2 crores/day run-rate is a forward indicator, not a Q4 contributor.
- Merchant strategy is deliberate and margin-rich: ACME is purposely charging batteries from the grid and selling at peak merchant prices before connecting solar panels, deferring solar capex to save interest and avoid module storage costs; at an assumed INR 6 arbitrage (sell at INR 8, buy at INR 2), EBITDA margins run ~75-80%.
- Regulatory tailwind makes this possible: MNRE clarified that BESS charged from conventional power under FDRE bids can sell in merchant mode without buyer NOC until the corresponding RE is commissioned, removing a key bottleneck.
- Curtailment becomes an opportunity, not a cost: CTU-connected plants are installing batteries; when curtailment occurs, ACME charges the battery with free power while still getting compensated for the curtailment, then sells that stored power at peak.
- The arbitrage window is expected to last years: Peak power prices have been INR 7-8 for years, gas constraints have elevated prices, and peak demand is much higher than last year; management sees this sustaining for at least 4-5 years, with India needing 200-300 GWh of battery as more daytime solar gets added.
Manoj Upadhyay: "Right now, the current calculation of CEA is you need around 200 gigawatt hour of battery to come to this if you don't add any more solar. But what is happening is also another 40, 50 gigawatt of FDRE and this one where the tender has happened, they will get added in the daytime. So technically, what is happening as long as you are adding more and more daytime solar, you need a more battery in the unit."
Revenue Quality: Central Offtakers Are Reshaping the Balance Sheet
- DSO collapsed to 14 days, and it is structural: The portfolio is shifting toward 100% central offtakers who take cash discounts and pay in ~10-15 days; this is not a one-off improvement but a permanent feature of the new mix.
- Legacy DISCOM pain is resolved: Higher receivable days from FY23 and earlier were driven by lower central offtaker contribution and payment issues from Telangana and Andhra DISCOMs; those dues are now settled under the LPS scheme, which enforces strict payment discipline.
- Other income is recurring and covenant-linked: Q4 other income of INR 157 crores primarily comprises recurring interest from cash generated at SPVs before upstreaming, plus interest from DSRA balances maintained per debt covenants; DSRA is largely funded from debt proceeds with corresponding finance costs accounted for separately.
- Curtailment is a non-issue for the CTU portfolio: Only ~INR 5-6 crores of real curtailment for the full year; most of the portfolio is on the central grid where regulatory compensation applies, and state-grid projects in Rajasthan saw only INR 3 crores of curtailment.
Nikhil Dhingra: "all our CTU connected projects with CTU connected substations, where you are regulatory protected from the customer payments are there irrespective of, you can say, the grid curtailment."
Commissioning Pipeline: 1.5 GW + 10 GWh in FY27
- FY27 target is back-end loaded but fully connected: 1.5 GW of generation assets and ~10 GWh of battery are targeted for commissioning; of the 10 GWh, ~8.5 GWh will run on merchant basis and ~1.5 GWh in FDRE format.
- Connectivity is the binding constraint, and ACME has it: 2,500 MW of ready substations and connectivity are already available for selling battery power at night; management states it can hit the 10 GWh target because connectivity, financing, and supply tie-ups are in place, with the only uncertainties being material supply and geopolitics.
- Key substation milestones are near-dated: Neemuch substation will be charged in June, commissioning NHPC and Tata FDRE plants; Fatehgarh will have SJVN's full 570 MW with long-term open access by March '27; NTPC's solar is ready with LTA slated for December '26.
- Under-construction portfolio extends through FY28: 3,280 MW plus 12 GWh BESS is the total under-construction envelope, to be fully commissioned by FY28.
- CTU delays are factored in at ~6 months: ~60% of substations are on time; maximum delay is typically 6 months due to transmission line interconnection and right-of-way issues; ACME defers module procurement during delays but keeps service work and substation construction ready.
- No penalty risk from CTU delays: Developers are not penalized for CTU-caused delays, and ISTS waiver eligibility is based on the original declared substation date, not actual commissioning.
Bid Strategy: Peak Power Is the Only Game That Sells
- Plain solar is the hardest to sell: Management was explicit that standalone solar finds few buyers; the market has shifted to peak-power products that bundle generation with storage.
- Battery-linked solar is becoming mandatory: CERC connectivity rules under regulation 5.2 make battery installation mandatory under certain guidelines; pure battery installations will be very limited, and the procurement configuration is changing toward solar-with-storage that mimics thermal power.
- Industry bids will be fewer but PPAs faster: Management expects 20-30 GW of total bids (state and central) next year, lower than last year, but PPA signing should accelerate; bids focused on peak power will succeed.
- Solar deployment stays at 40-50 GW despite lower nameplate bids: The configuration shift means each bid carries a large solar component behind the battery, so overall capex and solar deployment remain high even as bid volumes drop.
- 850 MW of older LOAs are in play: If PPAs are not signed, the strategy is to repurpose the connectivity for future bids or battery-connected projects; management does not foresee surrendering LOAs.
- Substation readiness drives PPA priority: Developers with substations charging in 2027 get better priority from DISCOMs than those with 2029 connectivity; ISTS waiver expiry in 2028 adds urgency.
Manoj Upadhyay: "the overall solar or overall the capex requirement will be higher than the last year because what is going to happen in the plain vanilla solar will be INR3 crores, INR4 crores, INR4 crores per megawatt. But the current bid, which is happening, for example, mimicking the thermal power or mimicking that long hour duration storage, solar storage, they will be – actually they will carry a very large solar behind the battery."
Returns & Capital Allocation: High Teens With Battery Included
- Battery inclusion does not dilute project returns: For the SECI ISTS hybrid tranche approved at INR 3.25, adding 1 hour of battery keeps returns in the high teens; it is a customer requirement for peak power, not a return diluter.
- Standalone BESS IRR is mid-to-high teens: Management cited this range but noted that zero date has not started, capex is not finalized, and end-of-life value depends on PPA cycles, so the number is indicative rather than locked.
- Gross block vs EBITDA mismatch is temporary: Gross block increased ~INR 3,400 cr but run-rate EBITDA is only ~INR 2,000 cr because wind projects commissioned at year-end have not yet performed for 12 months, and ~INR 1,000-1,100 cr of gross block is battery that also did not operate for the full year.
- Debt refinancing is actively lowering cost: INR 3,300 crores of operational project debt was refinanced, reducing interest rates by ~150 bps; 2.2 GW of operational projects carry an AA- stable credit rating.
- INR 15,000 crores of new debt secured: Financing is in place for various under-construction projects, de-risking the FY27-28 buildout.
Nikhil Dhingra: "So basically, it is -- what happens is most of the states want battery installation along with the project. So it basically keeps the return in high teens only. So it does not impact really the returns from this thing. But of course, we need to satisfy the customer requirement in terms of the power mix they want because everybody needs peak power now. So that is where we need to offer that 1 hour of battery, yes."
Regulatory & Policy Tailwinds
- SECI named single REIA: SECI has been notified as the single Renewable Energy Implementing Agency by MNRE, expected to drive a more streamlined and focused bidding framework.
- CERC SCOD extension provides relief: A draft suo moto order extends SCOD timelines under connectivity and GNA regulations by up to 1 year with compensation, giving regulatory certainty to delayed projects nearing connectivity deadlines.
- CERC discussion paper on LOA-based connectivity: A new mechanism proposes a surrendering exit option for capacities delayed by 1 year; management views it as a welcome move that adds flexibility.
- CTU processing BESS connectivity under RoFR: CTU has started processing BESS connectivity requests under Right of First Refusal, with 36 months of grid charging allowed from the GNA effective date, speeding up commissioning.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Generation commissioning | 1.5 GW of generation assets | FY27 |
| Battery commissioning | ~10 GWh total (~8.5 GWh merchant, ~1.5 GWh FDRE) | FY27 |
| Under-construction portfolio completion | 3,280 MW + 12 GWh BESS fully commissioned | By FY28 |
| Battery arbitrage sustainability | Peak power prices elevated, merchant strategy viable | At least 4-5 years |
| Neemuch substation charging | Commission NHPC and Tata FDRE plants | June (next quarter) |
| Fatehgarh long-term open access | SJVN 570 MW FDRE ready | March '27 |
| NTPC project commissioning | Solar ready, wind a couple of quarters later; all commissioned | By March '27 |
| Debt refinancing impact | Interest rate reduction of ~150 bps on INR 3,300 cr | Completed (Q4 FY26) |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue | ₹705 cr, +31% YoY; FY26 revenue ₹2,507 cr, +59% YoY |
| Other income | ₹157 cr in Q4, primarily recurring interest from SPV cash and DSRA balances |
| EBITDA margin | Over 90% for Q4 and full year, driven by operating leverage and operational efficiency |
| PAT | ₹138 cr for Q4, margin 19.6%; FY26 PAT ₹498 cr, margin 19.9% |
| Units generated | 172 crore units in Q4, +13% YoY; FY26 646.4 crore units, +61% YoY |
| CUF | 26.9% in Q4; full-year portfolio CUF close to 26% |
| Grid and plant availability | Over 99% for the year |
| Operational generation contracted capacity | 2,990 MW |
| BESS capacity commissioned to date | ~2.3 GWh, delivering net realization of ~₹2.2 cr per day, round trip efficiency 88–90% |
| Under construction portfolio | 5.1 GW total, PPA signed capacity 3,280 MW; will require ~17 GWh BESS |
| Total portfolio | 8,071 MW |
| Committed total capex | ₹12,475 cr, including ₹6,445 cr incurred during FY26 and ₹6,030 cr in purchase orders |
| Financing secured during FY26 | ~₹15,000 cr for under construction projects |
| Debt refinanced | ₹3,300 cr for operational projects, reducing interest rate by ~150 bps |
| Weighted average cost of debt (operational projects) | 8.4% per annum |
| Credit rating | AA- stable assigned to 2.2 GW of operational projects |
| Curtailment impact (full year) | ₹5–6 cr real curtailment; ₹3 cr on STU in Rajasthan; ₹2–3 cr from grid maintenance |
| DSO | 14 days, down from 180 days historically; trade receivables down 13% YoY |
| FY27 commissioning target | 1.5 GW generation assets and ~10 GWh battery; ~8.5 GWh of battery to start on merchant basis |