Adani Energy Solutions Ltd Q4 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/myfvjjyfz94uocec21ajdqz5.pdf

Key Takeaways


The INR 1.1 Lakh Crore Transmission Pipeline

Mehta: "There are very few players in the market who can do certain types of the projects or certain high-value projects especially certain niche projects like HVDC."

Smart Metering: Execution Phase Begins

Mehta: "Adani Energy Solutions is the only company currently in India or the private player in India which has an experience of running a distribution company and actually installing smart meters and making those smart meters work."

Mumbai Distribution: Operational Gains & Structural Moves


Project Execution & Capex

Mehta: "Earlier it was planned to get completed in September. It got pushed to financial year end. We were looking it to bid out by March. Thereafter, this event of election got announced, and therefore, it has got delayed because of these two months."

Capital Management & Funding


Guidance & Commitments

CommitmentSpecificsTimeline
Transmission pipeline tenderingINR 1.1 lakh crore pipeline begins biddingNext 3 months, post-elections
Pipeline tender completionFull INR 1.1 lakh crore tenderedNext 12-15 months
Market share target20-25% of INR 1.1 lakh crore pipelineOver the tender period
Under-construction project completionINR 17,000 crore pipeline completedNext financial year
Mumbai HVDC project completionProject operationalQ1 FY26
Mumbai HVDC remaining spendINR 5,500-5,800 crores incurredNext 15 months
Smart meter deploymentAggressive deployment of all won contractsNext 12-18 months
CapexAround INR 6,000 crores (incl. INR 1,200-1,500 crores for distribution)Next financial year
Equity IRR benchmark14-15% for transmission; same philosophy for smart metersOngoing discipline
AEML Mumbai debtNo fresh borrowing requiredNext financial year
Dahanu plant carve-outProcess ongoing, announcement when completedNo timeline given

Key Metrics

MetricQ4 FY24
Full-year revenue₹14,200+ cr, +17% YoY
Full-year operational EBITDA₹5,695 cr, +7% YoY
Full-year comparable PAT+12% YoY, excluding one-time items
Transmission system availability99.6%
Transmission incentive income₹104 cr
Total transmission circuit kilometers20,509 ckm, after adding 1,244 ckm
Mumbai distribution losses5.29%, improved from 5.93%
Mumbai regulated asset base₹8,500 cr, up from ₹5,500 cr at acquisition in 2018
Under-construction project pipeline₹17,000 cr
Transmission bidding pipeline₹1.1 lakh cr, up from ₹40,000–50,000 cr a year ago, includes three HVDC lines worth ~₹50,000 cr
Smart metering contracts won2.28 cr meters, total contract value ₹27,000 cr
FY25 consolidated capex guidance~₹6,000 cr, comprising ~₹1,200–1,500 cr distribution, ~₹5,000 cr transmission, ₹1,000–2,000 cr smart metering
Target equity IRR (transmission and smart metering)14–15%
Mumbai HVDC project cost incurred to date₹1,200–1,500 cr of ~₹7,000 cr total, completion expected Q1–Q2 FY26