Key Takeaways
- Capex doubled, set to double again: FY25 capex hit Rs 11,444 crores, and management guided Rs 16,000-18,000 crores for FY26, signaling an execution-heavy year ahead.
- Smart metering inflection reached: Daily installations surged from ~2,000 in Q1 to ~27,000 in April, with 70 lakh new meters targeted in FY26, putting the business on a steep ramp.
- Transmission pipeline is deep and visible: Rs 54,000 crores under bidding at ISTS level plus state-level TBCB activity, including Maharashtra's ~Rs 150,000 crore plan, supports multi-year growth.
- UP DISCOM privatization is the next catalyst: The state plans to split two DISCOMs into five companies of ~1,200 crore units each, with an RFP expected within a month.
- What to watch next quarter: Whether the UP DISCOM RFP actually drops, the pace of smart meter installations sustaining above 27,000 per day, and progress on commissioning seven transmission projects worth ~Rs 15,000 crores.
Capex & Execution Ramp
- Capex trajectory: FY25 capex of Rs 11,444 crores doubled from Rs 5,613 crores in FY24, driven by execution across transmission, distribution and smart metering. FY26 is guided at Rs 16,000-18,000 crores.
- Segment split for FY26: Transmission will absorb ~Rs 12,000-13,000 crores (funded 70-75% through project debt), smart meters ~Rs 4,000 crores (roughly 50% debt-funded, rest from internal accruals and working capital), and distribution ~Rs 1,600 crores (self-funded).
- Capitalization bridge: Out of Rs 11,400 crores total capex, Rs 7,600 crores went into transmission assets. Of that, roughly Rs 1,000 crores remains CWIP, so ~Rs 6,000 crores was capitalized, feeding the 19% full-year transmission EBITDA growth.
- Project selection guardrail: Management will not chase order book for its own sake, accepting only projects that fit financial and execution metrics. If capex delivery capacity is lower than expected, the company would probably not take the project.
Kandarp Patel: "We will add projects only if that fits within our financial and execution metrics. We will not be taking projects just because we wanted to build an order book."
Transmission: Pipeline & Commissioning
- Order book and visibility: A ~Rs 60,000 crore order book built from seven project wins across geographies, to be executed over the next 4-5 years. The bidding pipeline at ISTS level stands at Rs 54,000 crores, with absolute visibility for at least a couple of years.
- State-level TBCB opening up: Maharashtra has a ~Rs 150,000 crore transmission plan over six years, with many projects routed through TBCB. MP recently issued 3-4 TBCB bids, and REC published a bid document and tender notice.
- FY26 commissioning slate: Seven transmission projects aggregating ~Rs 15,000 crores are expected to be commissioned, including Khavda Phase II Part-A, Khavda-1 pooling station, North Karanpura Transco Ltd (delayed by environmental issues but aimed for FY26 completion), WRSR, Halvad, and Mumbai HVDC.
- HVDC milestones: The recently won Khavda HVDC project has a signed transmission service agreement and an order placed with Hitachi, targeting first pole in 48 months and second pole in 54 months. Fatehpur-Bhadla HVDC is under execution with Hitachi and BHEL. Mumbai HVDC is on schedule for Q3 FY26 commissioning.
- Khavda-Olpad HVDC status: Bid submission has not yet happened; the final schedule is expected soon, with the bidding process likely to complete within three months up to reverse bidding.
- Project delays are external: Some under-construction transmission projects are delayed by a few months due to dependencies on other system components, not the company's own execution. Change-in-law provisions apply for the lost period.
- Incentive income trajectory: Near-perfect 99.7% availability generated Rs 132 crores in incentive income. Once all projects are commissioned by FY27, incentive income could reach ~Rs 200 crores, with the first full year of operation in FY27.
Smart Metering: Inflection & Outlook
- Installation ramp: Deployments rose from ~2,000 meters per day in Q1 to ~18,000 in Q4, and reached ~27,000 per day in April. Issues around public resistance, manpower, training and supply chain have been resolved.
- FY26 target: At least 70 lakh new meters to be deployed, taking the cumulative installed base to ~1 crore by end-FY26.
- Market share ambition: Management wants to maintain a 22-23% market share, targeting at least 2.2-2.3 crore additional meters over the medium term.
- Unit economics: Estimated EBITDA of ~Rs 1,350 per meter per annum. The business has a one-year construction timeline and starts generating cash flow within a year.
- Remaining opportunity: Three to four major states have yet to finalize contracts: Tamil Nadu (tender floated), MP (only a few cities floated), Telangana, Karnataka, and half of Andhra Pradesh.
Kunjal Mehta: "around Rs 1,350 per meter per annum is the annual estimated for smart metering business."
Distribution: Mumbai, Mundra & the UP Catalyst
- Mumbai utility performance: AEML ranked the number one distribution utility in the country for the third consecutive year. Distribution loss improved to 4.7% from 5.29%, a ~0.5% reduction on the base. Energy sales grew 6%.
- Mundra growth: Energy sales grew 44%, driven by increasing demand in the region.
- UP DISCOM privatization structure: The state plans to privatize two of its four distribution companies, splitting them into five companies of ~1,200 crore unit volume each to make the size manageable. A transaction adviser (Grant Thornton) has been appointed, and the RFP is expected within a month.
- Capex treatment: Any capex for UP privatization would be over and above the Rs 16,000-18,000 crore FY26 plan.
- Precedent potential: If the UP privatization proceeds, management believes it will set an example for other states, potentially unlocking a wave of similar distribution company initiatives.
- Bidding limits unknown: It is too early to say how many of the five UP companies a single player can bid for, as the RFP has not yet been issued.
Financial Health & Funding
- EBITDA growth ambition: EBITDA grew 23% in FY25, and management aims to outgrow this level for at least the next 4-5 years.
- Operating vs reported EBITDA bridge: A gap of ~Rs 500-600 crores each year exists between operating EBITDA and reported EBITDA, explained by EPC businesses, certain treasury income, and trading income from power businesses.
- Funding capacity: Capital is not a constraint. The EBITDA-to-FFO conversion ratio across projects is ~50%. Transmission projects have a 3-4 year construction timeline; smart metering generates cash flow within a year; distribution is self-funding.
- Post-construction financing benefit: Once projects become operational, ratings improve and borrowing costs drop below 9%. For AAA and AA+ rated entities, the cost of debt is around 8-8.5%.
- AEML dividend policy: Dividends will follow bond covenants. The company is looking to further deleverage, using available surplus for either dividends or repayment of existing loans including shareholder loans.
- 2026 bond refinancing: All options are on the table; the company will activate refinancing options about 6-9 months before the actual maturity.
- US tariff immunity: The company is a homegrown utility with no exported services and no dependence on US-sourced goods or services, so US tariffs have no impact.
Kandarp Patel: "So U.S. tariff doesn't impact us because we are a homegrown utility and no services of us is either getting exported or we are not dependent on any services or goods that comes from U.S. So there is no impact on us."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capex | Rs 16,000-18,000 crores | FY26 |
| Smart meter installations | At least 70 lakh new meters, cumulative ~1 crore | FY26 |
| Transmission commissioning | Seven projects aggregating ~Rs 15,000 crores | FY26 |
| Mumbai HVDC commissioning | Project completion | Q3 FY26 (December) |
| EBITDA growth | Outgrow 23% FY25 level | At least next 4-5 years |
| Order book execution | Rs 60,000 crores | Next 4-5 years |
| Incentive income | ~Rs 200 crores, first full year of operation | FY27 |
| Khavda HVDC | First pole commissioned | ~48 months |
| Khavda HVDC | Second pole commissioned | ~54 months |
| Smart meter market share | Maintain ~22-23% share; target 2.2-2.3 crore additional meters | Medium term |
| UP DISCOM RFP | Bidding document issuance | ~1 month |
| Khavda-Olpad HVDC bidding | Bidding process completion up to reverse bidding | ~3 months |
| 2026 bond refinancing | Activate options | 6-9 months prior to maturity |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Consolidated revenue | Not explicitly stated for Q4; FY25 EBITDA grew 23% YoY to ₹4,400 cr (from ₹3,800 cr) |
| EBITDA growth | 23% YoY for FY25 |
| Transmission operating EBITDA | ₹1,108 cr, +5% YoY |
| Total capex incurred | ₹11,444 cr in FY25, vs ₹5,613 cr in FY24 |
| FY26 capex guidance | ₹16,000 cr to ₹18,000 cr |
| Order book | ~₹60,000 cr, to be executed over next 4–5 years |
| Tariff-to-capex ratio on order book | 13.77%, translating to ~₹8,250 cr revenue |
| Transmission availability | 99.7% in FY25 |
| Incentive income from availability | ~₹132 cr in FY25 |
| Total circuit kilometers | 27,000 circuit kilometers |
| AEML Mumbai energy sales growth | 6% YoY |
| Mundra Utility energy sales growth | 44% YoY |
| AEML Mumbai distribution loss | 4.7%, improved from 5.29% in FY24 |
| Renewable penetration in Mumbai Utility | 36% in FY25 |
| Smart meters installed | 32 lakh meters by end of FY25 |
| Smart meter installation run-rate | ~27,000 meters per day in April 2025 |
| FY26 smart meter deployment target | At least 70 lakh new meters, cumulative ~1 crore by FY26-end |
| Smart meter EBITDA estimate | ~₹1,350 per meter per annum |
| Transmission projects to commission in FY26 | 7 projects, aggregating ~₹15,000 cr project cost |
| Mumbai HVDC project cost | ₹7,000 cr, commissioning targeted by December 2025 |
| Halvad project cost | ₹2,700 cr |
| Total asset base | ~₹42,000 cr, of which transmission ~₹32,000 cr and distribution ~₹10,000 cr |
| Capitalized amount in FY25 | ~₹9,500 cr (total); transmission ~₹6,000 cr capitalized |
| Under-construction project borrowing cost | ~9.5% |
| Post-construction borrowing cost | 8% to 8.5% for AAA/AA+ rated transmission projects |
| Smart meter market share target | 22% to 23%, targeting 2.2–2.3 cr additional meters |