Key Takeaways
- 20% revenue and EBITDA growth, execution on track: Revenue and EBITDA from power supply both rose 20% YoY, while cash profit surged 27% YoY, driven by capacity additions and operational excellence.
- 6 GW FY25 capacity addition target reaffirmed: Management committed to adding 6 GW this year, with one-third expected this quarter and the remainder by year-end, despite a monsoon-related delay that was within the planned construction S-curve.
- Khavda wind performance is a positive signal: Wind turbines in stabilization phase delivered CUF north of 44% in the last two months, and management forecasts full-year wind CUF in excess of 35%, with solar CUF above 32% from next year onward.
- Minority interest is rising structurally, not a problem: The sequential increase reflects older, higher-tariff assets in JVs where debt has amortized significantly, a feature of the project finance model that will recur as other projects mature.[10-11]
- What to watch next quarter: Whether the 2 GW of capacity addition targeted for Q3 materializes on schedule, the trajectory of merchant realizations as hydropower supply normalizes, and any further clarity on the 5 GW Maharashtra PPA timeline.
Execution & Capacity Addition
- H1 was deliberately back-end loaded: Only 200-300 MW was added in H1 because management plans and line-balances construction activity over two to three years; the monsoon extended by a month, reducing the active working period in Khavda, but this was budgeted in the overall plan.
- Q3 ramp-up is the critical milestone: One-third of the 6 GW annual target is committed for this quarter, with teams fully back on site and catching up after the monsoon.
- Post-addition EBITDA run-rate: Management expects run-rate EBITDA in excess of INR16,000 crores on an install base of 17 GW once the 6 GW is added.
- Future run-rate ambition: A minimum run-rate of 6 GW per year going forward for Khavda and Rajasthan.
- Evacuation is de-risked through next year: Clear line-of-sight on evacuation until end of next year means none of the projects will face bottling or delays from transmission constraints.
- 50 GW evacuation visibility: The next 2-3 years have absolute 100% clarity; beyond that, active projects by AESL and Power Grid are being watched, and management feels well set for 50 GW.
Raj Kumar Jain: "There has been lot of discussions they had with a lot of players in the market, but they are finding that execution and the timely delivery of power is a big differentiator, which they value and that's where our track-record really gives them comfort in terms of tying up with us."
Khavda: The Performance Engine
- Wind CUF is exceeding expectations early: The 250 MW of 5.2 MW WTGs, the largest onshore wind turbines in India, delivered CUF north of 44% in the last two months of operation, even while still in the stabilization phase.
- Full-year wind forecast: Management forecasts full-year CUF in excess of 35% for the Khavda wind turbines.
- Solar CUF to lift portfolio from next year: Khavda solar CUF is expected above 32% on a full-year basis from next year onward, which will lift the overall portfolio CUF.
- Merchant wind benefits from strong pricing: New wind capacity additions are on the merchant side, where price realization in H1 has been very attractive.
Amit Singh: "Even though the wind plant in Khavda is still under stabilization phase, we have seen a very good CUF of these machines, north of 44% for the last two months that it has been operational."
Commercial & Industrial (C&I) and New Business
- Google deal opens the C&I door: The first C&I agreement supplies 61 MW of renewable energy to power a Google data center, advancing its 24/7 carbon-free energy goal; supplies are expected to start in Q3 calendar year 2025.
- C&I positioning is built on scale and diversification: Management is upbeat on the C&I pipeline, citing a big footprint of solar and wind plus good geographical diversification, which customers demand for reliable round-the-clock solutions.
- Pricing and tenure are guarded: Management declined to disclose the Google deal's pricing or specific tenure, calling both commercially sensitive, and described it only as a "long-term deal."
- Merchant portfolio is material: Out of the 11.2 GW operating portfolio, between 2.5-3 GW operates between infirm and merchant, benefiting from current market conditions; 1.8 GW of the 6 GW construction plan is merchant, and that plan still holds.
- Merchant realizations outlook: Realizations tend to improve in the next quarter and the following quarter; the last quarter was uniquely soft because of very high hydropower delivery into the grid.
- Merchant funding is available: Financial institutions, both ECB lenders and domestic, are willing to finance merchant projects at 70-30 or 75-25 debt structures, based on the company's track record, CUF generation, and portfolio combination of PPA and merchant. [13-14]
Amit Singh: "We are one of the companies with such a big footprint of solar wind. And also, we have very good geographical diversification, which our C&I customers are asking to make sure that they have a very reliable RTC solution. So we are very uniquely positioned actually to deliver on those aspirations they have."
Amit Singh: "Look, I think, all the banking institutions we work with, they are very happy with our track record of delivery. And they have understood our numbers. They know our capex and our CUF we generate from these plants. This gives a lot of confidence for them when we go for merchant finance as well."
Storage: Batteries and Pumped Storage
- Battery storage opportunities are near-term: Management is actively pursuing several battery storage opportunities expected to materialize in the next financial year, curating solutions and planning to participate both in the market and in merchant opportunities, leveraging utility scale in Khavda.
- Battery prices are falling fast: Prices have fallen rapidly in the last six to nine months, benefiting from international developments especially in China; research on battery chemistry to improve cycle life will also improve unit cost.
- PSP is structurally cheaper than BESS: On an LCOE basis, PSP can be almost half the price of battery systems; PSP can also provide longer-duration power, not limited to four hours like batteries, and avoids the disposal issues batteries face after roughly 12 years of life.
- PSP pipeline is large but early-stage: The company has access to north of 20 GW scale of different PSP sites; numbers will be shared as these are tied up.
- PSP storage cost is withheld: Management declined to give an opinion on the storage cost per unit from PSP, saying it would rather keep those numbers for tenders. [15-16]
Raj Kumar Jain: "PSP has its own merit and you have seen more tenders in the market apart from a particular case, I'm sure the utility which a PSP provides to a DISCOM is valued because as Amit mentioned earlier, it is still cheaper than -- significantly cheaper than what a battery-based BESS can provide you as a number."
Minority Interest: The Mechanics
- The increase is a feature, not a bug: Minority interest rose sequentially from INR183 crores to INR239 crores because older assets in the 2.3 GW JV portfolio formed in 2020 have systematically amortized their debt, so profit attributable to those assets keeps increasing; for newer assets, interest is higher because debt amortization has not reached that level.[10-11]
- Debt-to-EBITDA is falling on mature projects: As debt is paid down, debt-to-EBITDA is moving towards 3 or less, causing higher profitability for mature projects, which flows through to minority interest.
- Trajectory is upward: PAT attributable to minority interest will now be in the same range going forward or slightly higher; on an accelerated trend, INR240-250 crores per quarter can be assumed, and it will keep going up as under-construction projects in JVs become operational and start generating cash.[16-17]
- No precise steady-state number given: Management gave directional quarterly guidance but declined to provide a precise annual steady-state figure when asked.
Partnerships, Financing & Land Bank
- TotalEnergies JV deepens the partnership: A new JV comprising a 1.15 GW renewable portfolio was formed, with TotalEnergies investing USD44.4 crore; TotalEnergies will continue investing further equity for under-construction projects in the JV.[16-17]
- No automatic future JV optionality: There is no optionality on either side for future JV investments; any further deal would require discussion and Board approval at the right time.
- Holdco bond fully redeemed: The USD75 crore Holdco bond was completely redeemed in line with commitment, resulting in systematic deleveraging.
- Refinancing tailwind: Refinancing completed last December has further reduced interest cost, contributing to the PAT increase.
- Land bank is being actively diversified: The company is acquiring and adding to its portfolio in Rajasthan, Gujarat, and looking at sites in Karnataka, Andhra, Tamil Nadu, and Madhya Pradesh for both solar and wind, aiming for a diversified set of land banks.
Amit Singh: "We want to make sure that we have a diversified set of land banks and we want to make sure that we tie them up."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY25 capacity addition | 6 GW total, with one-third (approx. 2 GW) in Q3 | FY25, with Q3 milestone |
| Post-addition EBITDA run-rate | In excess of INR16,000 crores on 17 GW install base | Upon 6 GW addition completion |
| Future annual capacity run-rate | Minimum 6 GW per year | Going forward for Khavda and Rajasthan |
| Khavda wind full-year CUF | In excess of 35% | FY25 |
| Khavda solar full-year CUF | Above 32% | From next year onward (FY26) |
| Google C&I supply start | 61 MW to Google data center | Q3 calendar year 2025 |
| Minority interest quarterly run-rate | INR240-250 crores per quarter on accelerated trend | Going forward |
| Maharashtra 5 GW PPA execution | Commissioning timeline close to 4 years | Approx. 4 years from finalization |
| Evacuation line-of-sight | No projects face bottling or delays | Until end of next year |
| Battery storage opportunities | Expected to materialize | Next financial year (FY26) |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Revenue from power supply | ₹4,836 cr, +20% YoY |
| EBITDA from power supply | ₹4,518 cr, +20% YoY |
| Cash profit | ₹2,640 cr, +27% YoY |
| Group PAT (Adani shareholders) | ₹276 cr, down from ₹372 cr YoY |
| Attributable EBITDA run rate (full year) | ~₹10,800 cr, on 11.2 GW operational capacity |
| Run rate EBITDA post 6 GW addition | >₹16,000 cr, on 17 GW installed base |
| Energy sales | 1,410 cr units, +20% YoY |
| Total operational capacity | 11.2 GW, added 2.9 GW greenfield capacity over last one year |
| FY25 capacity addition target | ~6 GW, one-third in Q3, remainder towards year-end; wind ~1 GW, solar ~5 GW |
| FY25 capacity addition, merchant portion | 1.8 GW, plan unchanged |
| Overall portfolio CUF | 24% |
| Khavda wind CUF (last two months) | >44%, full year forecast >35% |
| Khavda solar CUF forecast (full year, from next year) | >32% |
| Merchant revenue (H1 FY25) | ₹1,070 cr |
| Solar merchant realization (H1 FY25) | ₹2.85/unit, Q2: ₹2.59, Q1: ₹3.11 |
| Wind merchant realization (H1 FY25) | ₹5.43/unit, Q2: ₹5.06, Q1: ₹5.81 |
| Maharashtra State Discom LOA | 5 GW solar, 25-year fixed tariff PPA |
| First C&I agreement | 61 MW to power data center, supplies expected Q3 CY25 |
| TotalEnergies JV portfolio | 1.15 GW, investment of USD44.4 cr received |
| Holdco bond redeemed | USD75 cr |
| Land bank | >70 GW |
| PSP site pipeline | >20 GW scale |
| Battery storage price decline (past two years) | 66% |
| Minority interest | ₹239 cr, up from ₹183 cr QoQ |
| Other financial liabilities | ₹4,600 cr, up from ₹1,600 cr QoQ, primarily capex-related |