Key Takeaways
- Execution on track, monsoon a drag: Capacity rose 49% YoY to 16.7 GW, but an erratic monsoon pushed solar CUF down and grid availability fell to 89% as new projects await transmission infrastructure.
- 5 GW FY26 target reaffirmed: Management is "wholly committed" to adding 5 GW this year despite a seasonally weak Q2, with 2.4 GW already delivered in H1.
- Leverage stays elevated through FY29: Net debt to run-rate EBITDA will remain in the 4x-5x range for another 2-3 years before falling sharply as capex moderates and commissioned assets generate full-year EBITDA.
- BESS ambition flagged, details pending: The company is developing battery storage at "unprecedented" scale, outside the 50 GW target, with a full strategy promised shortly.
- What to watch next quarter: Whether the 5 GW target stays on track after a soft Q2, the BESS strategy reveal, and any clarity on the Nexus-Google data center role.
Capacity Execution & Operations
- Khavda scale-up: The world's largest renewable energy plant now has 7.1 GW of solar, wind and hybrid assets operating, with evacuation capacity reaching ~10 GW by year-end.
- H1 delivery: 2.4 GW commissioned in H1, roughly 74-75% of last year's pace, achieved despite a heavy monsoon that limited Q2 to 800-900 MW.
- Solar CUF dip: Q2 solar CUF fell as an extended monsoon dragged H1 to ~24.5%; full-year CUF is still expected to be 100-200 bps higher than last year.
- Wind softer YoY: Wind performance has not matched last year's "phenomenally good" levels, though management expects to at least meet last year's full-year figure.
- Grid availability lag: Solar grid availability dropped from 97% to 89% because newly commissioned capacity was included before its external transmission infrastructure was ready, a timing mismatch that resolves as evacuation catches up.
- Curtailment contained: Total curtailment impact is under 5% of generation and primarily hits infirm/merchant power; PPA power that is curtailed earns deemed generation compensation.
Khanna: "In spite of a heavy monsoon, coming close to more than 800-megawatt and close to 900-megawatt in a quarter is no small thing. Take my word on this as well as the solar and otherwise is concerned."
PPA Strategy & Revenue Mix
- Non-PPA margin boost: Higher contribution from merchant, C&I and CFD sales lifted EBITDA margin to 92%, with infirm power sold as merchant acting as an add-on to the PPA book.
- PPA conversion not guaranteed: Management declined to confirm that all infirm power would convert to long-term PPAs by fiscal year-end, citing dependence on evacuation system elements being operationalized in sequence.
- PSP kept flexible: The Chitravathi pumped storage project (500 MW, 57% complete) is deliberately not locked into a PPA; the strategy is to preserve optionality for peak power markets and contract later at better returns.
- Tender selectivity: Management pushed back on the idea that it lost recent tenders, stating it chose not to win them for strategic reasons, and expects more storage-plus-peak-power tenders ahead rather than pure-play solar.
- Solar's evolving role: Solar will increasingly serve as the least-cost input for storage over the next five years, so even if pure-play solar tenders decline, solar capacity demand continues through the storage route.
Khanna: "Wherever we get an opportunity to earn a handsome return on a PPA, the assets are important to be in place. Once the opportunity comes, we will take full advantage of that particular opportunity to have the maximum return."
Leverage & Capital Allocation
- Capex run-rate: INR 30,000-35,000 crores annually for the next two years, supporting 5-6 GW of capacity additions each year, with more capacity back-ended into FY29 and FY30.
- Leverage trajectory: Net debt to run-rate EBITDA stays in the 4x-5x band for 2-3 years; operational and run-rate EBITDA growth outpaces the debt impact, but the ratio only falls sharply from FY29 onward as capex moderates.
- PSP capex back-ended: The Uttar Pradesh PSP project has a six-year timeline with spending concentrated in the last three years; the first three years involve mainly land and pre-development costs, so near-term capex is light.
- Receivables tight: Overdue receivables stand at just four days, with teams monitoring continuously for further improvement.
New Business: BESS & Data Centers
- BESS at scale: Adani Green is developing battery energy storage systems at a scale management calls "unprecedented in this country," separate from the 50 GW renewable target, with a full strategy announcement coming shortly.
- Nexus-Google role unclear: On the Vizag AI data center campus partnership with Google, management said it is "too premature" to define Adani Green's specific role, though the group can offer multiple solutions including 24x7 green power.
Khanna: "please be reassured in this timeframe that Adani Green is working and developing BESS and also at a scale which I shared with you will be unprecedented in this country as of now."
Module Sourcing & Regulatory Context
- Import flexibility retained: For solar-plus-manufacturing PPAs, Chinese modules can still be imported; for Maharashtra PPAs, the domestic cell/module requirement does not apply given the bid timing.
- ALMM cutoff: Bids placed before early 2021 permit Chinese module imports; bids after that require ALMM compliance if commissioned after April 1, 2024.
- ISTS waiver window used: Many projects were commissioned before June to capture the ISTS transmission charge waiver, a move management described as rational for the entire industry.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 capacity addition | 5 GW | Current fiscal year |
| Annual capex | INR 30,000-35,000 crores | Next two years |
| Net debt to run-rate EBITDA | 4x-5x range | Next 2-3 years |
| Leverage reduction | Sharp decline begins | FY29 onward |
| First PSP commissioning | Chitravathi (500 MW) online | Coming calendar year |
| Khavda evacuation capacity | ~10 GW | By end of this year |
| Full-year solar CUF | 100-200 bps higher than last year | FY26 |
| Full-year wind CUF | At least match last year's level | FY26 |
| Exact capacity guidance for next year | To be provided | Q3 or Q4 FY26 results |
| BESS strategy announcement | Full strategy reveal | "Shortly" |
Key Metrics
| Metric | Q2 FY26 |
|---|---|
| Revenue from power supply | ₹6,088 cr, +26% YoY |
| EBITDA | ₹5,651 cr, +25% YoY |
| EBITDA margin | 92%, best-in-class |
| Cash profit | ₹3,093 cr, +17% YoY |
| EBITDA excluding other income | ₹2,600 cr, vs ₹3,000 cr in Q1 FY26 |
| Run rate EBITDA from power sales | ~₹14,100 cr |
| Energy sales | 1,960 cr units, +39% YoY |
| Renewable energy capacity | 16.7 GW, +49% YoY |
| Greenfield capacity added in H1 FY26 | 2.4 GW, 74% of total FY25 additions |
| Full-year capacity addition target | 5 GW |
| Capex for FY26 | ~₹30,000 cr, of which 2.4 GW achieved |
| Capex guidance for next two years | ₹30,000 cr to ₹35,000 cr per year |
| PPAs in hand | ~27 GW |
| LOAs to be converted to PPAs | >4 GW |
| Net debt to run rate EBITDA (operational assets) | 4.4x |
| Net debt to run rate EBITDA (including under-construction debt) | 5.1x |
| Gross block (operational portfolio) | ₹94,000 cr for ~16.7 GW |
| CWIP | ₹16,000 cr |
| Infirm or pre-COD power capacity | 4.8 GW |
| Average merchant realization, solar | ₹2.1 per unit plus RECs of ₹0.35 per unit |
| Average merchant realization, wind | ₹5.13 per unit plus RECs |
| Blended merchant price | ~₹3.5 per unit |
| Solar CUF, H1 FY26 | ~24.5% |
| Khavda wind CUF | 42% |
| Overdue receivables beyond due date | 4 days |
| Chitravathi PSP physical progress | 57% completed, total project cost ~₹2,600 cr |
| PSP cost per MW | ₹5.1 cr to ₹5.2 cr |
| Solar capex per MW | ₹4 cr to ₹4.5 cr |
| Solar tariff range | ₹2.4 to ₹2.5 per unit |