Key Takeaways
- 20 GW operational, curtailment the headline drag: H1 EBITDA would have been ~₹9,000 crores without curtailment, versus the ₹8,276 crores reported; the 3 GWh BESS addition at Khavda is the direct answer, and management expects H2 curtailment to be lower.
- BESS is now the strategic centerpiece: The firm is committed to surpassing 10 GWh this year, and management frames battery storage as "virtual transmission" that deconstrains solar and wind execution when transmission corridors are delayed.
- Phase 3 transmission corridor is the gate on 4.5–5 GW: All balance-of-system work is done; modules can be deployed at 20–30+ MW/day, but commissioning waits on a corridor now expected in Q4, not by year-end.
- Interest cost has structurally improved: AGEL-level rates fell from 11.1% in 2019 to 8.9% now, driven by five rating upgrades; 72% of project loans are fixed-rate for 3–5 years, insulating the book from rate-cycle moves.
- What to watch next quarter: Whether the Phase 3 transmission corridor actually arrives in Q4, the pace of BESS tie-ups beyond the 3.5 GWh already contracted, and whether H2 curtailment indeed falls as promised.
Curtailment, BESS & the Transmission Bottleneck
- Curtailment quantified: H1 EBITDA was ₹8,276 crores; management stated it would have been close to ₹9,000 crores without curtailment, implying a ~₹724 crores impact. Solar CUF fell to ~23% from 24.8% YoY, predominantly from higher curtailment, while resource was slightly better and operational efficiency was good.
- BESS as the mitigation engine: 3 GWh commissioned at Khavda in Q2 took total installed storage to 6.6 GWh, over half of India's operational BESS. Accelerated BESS development provides flexibility and enables use of otherwise-wasted power, and management expects H2 curtailment impact to be lower than H1 as a result.
- The Phase 3 gate: The 7 GW transmission corridor, which gives full GNA capacity and removes existing curtailments plus enables more execution, is now expected in Q4 (next quarter), previously expected by year-end. AGEL has completed all infrastructure and balance of system, ready to deploy modules and commission quickly when the corridor is available.
- A second 7 GW line also looks delayed, though management is currently more focused on the first corridor. For Phase 6 and Phase 7, battery storage is positioned as the mitigation tool if transmission delays persist, and the company is also looking at other states including Rajasthan for capacity.
- Curtailment payment mechanics: All PPAs are take-or-pay; when the grid orders curtailment or backdown, AGEL is paid for deemed generation. Power that was never scheduled, however, is not paid for.
Ashish Khanna: "In our 25-year profit through business or a project business, 3 to 6 months here and there on curtailment will not have a very major impact on the return on asset on an asset."
BESS: Scale, Tie-ups & Strategic Role
- 10 GWh target to be surpassed: Management is firmly on track to exceed 10 GWh during the year and committed to not only commission 10 GWh by year-end but surpass it. Capex focus has shifted more toward battery given transmission delays, and the largest plants in the world are being built in 8–10 months.
- Tie-up status: 3.5 GWh of BESS already tied up as of September 30; the balance 3.1 GWh is in the process of being tied up. Input solar and wind power is already available for these assets. Management declined to specify the split between AESL and other hybrid or FDI obligations, stating parameters are clear and details will be shared when tying up is complete.
- "Virtual transmission" framing: BESS provides flexibility that can be deployed very fast without much land, deconstraining solar and wind execution from transmission delays. This is a capability management says it did not have last year.
- Tie-up parameters: 100% of BESS capacity will be tied up; critical parameters are counterparty rating and return expectations. Currently tying up with AESL, an AA+ partner, and will also look for other organizations meeting return and credit requirements.
Rajat Seksaria: "We now have an added tool in our arsenal to respond to that, so that executing more solar and possibly wind is kind of deconstrained by any delays that may happen on transmission. So, versus last year, if you compare this year, we certainly have a very, very strong arsenal in our hand as a group, as Adani Green to take care of that."
Financial Performance & Interest Cost
- H1 growth drivers: Energy sales rose 32% YoY to 2,570 crore units, supported by 24% YoY greenfield capacity additions. Revenue from power supply grew 36% YoY and EBITDA grew 41% YoY, with EBITDA margin at 93%.
- Q2 standalone: Revenue from power supply +45% YoY, EBITDA from power supply +51% YoY, EBITDA margin 92%.
- EBITDA outpacing generation: Driven by better realizations, battery numbers now getting added, solar-wind combination where untied capacity goes to merchant, better wind speed due to lower rains, and operational efficiencies keeping operating costs relatively flat. Merchant rates improved from ~₹2.1 last year to ₹2.4 this year due to better listing and pricing.
- Interest cost structural improvement: AGEL-level interest rate fell from 11.1% in 2019 to 8.9% now, a ~220 bps reduction driven by rating upgrades as projects become operational. 72% of project loans are fixed-rate for 3–5 years, insulating a substantial portion from rate-cycle impact.
- AGE23L upgrade: The SPV converted from AA+ to AAA, giving a 20–25 bps reduction on that asset, which represents ~15% of AGEL overall EBITDA. The asset has 7–8 years of operation, loans are amortizing, and PAT-level profitability is rising.
- Rate outlook: As the portfolio transitions to more operating capacity with 25-year PPAs, no major impact is expected on the interest rate profile even if the rate cycle goes up; the under-construction phase has a larger impact, which tapers off as the operating share grows.
Returns, PPA Strategy & Counterparty Discipline
- ROE/ROA threshold: Management is committed to maintaining 13%–14% ROE (or ROA, used interchangeably in the call) by tying up capacities with AA+ counterparties on 25-year contracts. The strategy is counterparty-neutral: the firm will pursue opportunities delivering high returns with long-term visibility and desired credit quality.
- PPA strategy removes merchant risk: The company wants to carry only execution risk, not merchant price risk. 25-year fixed PPAs eliminate worry about annual merchant price fluctuations.
- C&I strategy: AESL is one AA+ partner; the firm will also look for other organizations meeting return and credit requirements. Management declined to provide specific C&I capacity figures or differentiate between C&I and other demand, stating AGEL is a developer with long-term tie-ups regardless of end-use.
- Curtailment and returns: 3–6 month blips in curtailment over a 25-year project life will not have a major impact on asset-level returns; many assets were commissioned before time, preserving returns.
Saurabh Shah: "For us, we are removing that kind of risk that we were carrying on merchant. We want to carry only one major risk, which is execution. So we are good at that. We want to execute better."
Capex, Leverage & Hedging
- Capex program firm at ₹2.4 lakh crores: Battery storage acceleration adds on top of the existing plan; no challenge is foreseen in achieving it. Solar, wind, battery storage, and pump storage all have roles in the next 3–5 years.
- Leverage trajectory: Will remain in the 5.6x range till FY28–FY29. As operating assets increase post FY29–FY30, leverage moves to 4.5–5x, then toward 4x and below as debt amortizes. Curtailment of 3–6 months does not materially change the leverage profile, because leverage is based on project assets, not short-term EBITDA fluctuations.
- Hedging policy: The firm will continue fully hedging principal plus interest on dollar borrowings. RG1 hedging is to be rolled over for another 3–5 years during a good window.
Saurabh Shah: "It does not have a larger impact due to curtailment, which will change the leverage profile in that big way, because our leverage is based on project assets and not based on a change of 3 to 6 months here and there on any EBITDA profile."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| BESS capacity | Surpass 10 GWh commissioned | By FY27 year-end |
| Chitravathi pump storage | 500 MW project completion | By year-end |
| FY27 greenfield commissioning | 4.5–5 GW, conditional on Phase 3 transmission corridor arrival | If corridor comes by Q4 |
| Phase 3 transmission corridor (7 GW) | Corridor availability, enabling full GNA capacity and curtailment removal | Q4 (next quarter) |
| ROE/ROA on new tie-ups | 13%–14% with AA+ counterparties on 25-year contracts | Ongoing |
| Capex program | ₹2.4 lakh crores, with battery storage added on top | Over next 3–5 years |
| Leverage | Remain in 5.6x range, then move to 4.5–5x post FY29–FY30, then toward 4x and below as debt amortizes | FY28–FY29 and beyond |
| Dollar borrowing hedging | Fully hedge principal + interest; roll over RG1 hedging for another 3–5 years | During a good window |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue from power supply | ₹4,019 cr, +45% YoY |
| EBITDA from power supply | ₹3,835 cr, +51% YoY |
| EBITDA margin | 92% |
| H1 FY27 revenue from power supply | ₹8,299 cr, +36% YoY |
| H1 FY27 EBITDA from power supply | ₹7,957 cr, +41% YoY |
| H1 FY27 EBITDA margin | 93% |
| H1 FY27 total EBITDA | ₹8,276 cr; would have been close to ₹9,000 cr without curtailment |
| H1 FY27 energy sales | 2,570 crore units, +32% YoY |
| Operational capacity | 20.8 GW, crossing 20 GW milestone |
| Installed battery storage capacity | 6.6 GWh, after commissioning 3 GWh at Khavda in Q2; accounts for >50% of India's operational BESS |
| Khavda commissioned capacity | 10.8 GW of solar, wind and hybrid |
| Solar CUF H1 FY27 | ~23%, vs 24.8% in H1 FY26; dip primarily due to curtailment |
| Average interest cost | 8.9%, flat over last 6 months; down from 11.1% in 2019 |
| Leverage | 5.6x; expected in 4.5–5x range till FY28–FY29, then moving toward 4x and below |
| FY27 commissioning target | 4.5–5 GW, contingent on Phase 3 transmission line now expected in Q4 |
| BESS target by year-end | 10 GWh, confident of surpassing |
| BESS tied up in long-term contracts | 3.5 GWh; balance 3.1 GWh of 6.6 GWh as of Sep 30 in process |
| Capex program through FY30 | ₹2.4 lakh cr |
| Target ROA | 13%–14% (EBITDA divided by cost of project) |
| Fixed-rate project loans | 72% of portfolio, medium-term range of 3–5 years |
| AGE23L SPV interest cost | 8.4%, down from ~10%–11% after upgrade to AAA rating |
| Solar PPA tariff with AESL (25-year) | ₹2.7/unit |
| Wind PPA tariff (25-year) | ₹3.93/unit |
| Merchant realization | ₹2.4/unit, vs ~₹2.1/unit last year |