Adani Green Energy Ltd Q4 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/wlkgvwlriacyjpg4duwkovdv.pdf

Key Takeaways


Capacity Addition & Execution

Sagar Adani: "If you ask me, my personal view would be that we are significantly underbuilding the wind capacity. So, in fact, across the board, all developers from a country perspective as well, we need to ensure a significantly higher development of wind capacity versus solar capacity."

Merchant & C&I Strategy

Sagar Adani: "We don't have to compete where 20 other people are already."

Pumped Hydro & Storage


Module Supply & ALMM


Strategic Boundaries

Sagar Adani: "India is a very, very different animal and a very different set of considerations compared to many other places in the world. So it would be very wrong to kind of borrow off from specific commercial experiences in other places in the world versus what the situation in India is."

Financial Strength & ESG


Guidance & Commitments

CommitmentSpecificsTimeline
Greenfield capacity additionAt least 6,000 MWFY25
Greenfield capacity additionSimilar or slightly higher than FY25, in a similar rangeFY26
Annual greenfield run rate6,000 to 8,000 MW per yearOngoing
Khavda project completionFull project completedBy 2029
2030 renewable capacity target50 GW, fully funded from debt and equityBy 2030
Pumped hydro storage targetAt least 5 GWBy 2030
First pumped hydro commissioning500 MW project in Andhra PradeshFY27
Merchant and C&I portfolio mixApproximately 10% of portfolioOngoing guidance

Key Metrics

MetricQ4 FY24
Revenue from power supply₹7,735 cr, +33% YoY
EBITDA₹7,222 cr, +30% YoY
EBITDA margin92%, industry-leading
Run-rate EBITDA₹10,462 cr
Cash profit₹3,986 cr, +25% YoY
Net debt to run-rate EBITDA4x, improved from 5.4x a year ago
Operating capacity10,934 MW
Greenfield capacity addition in FY242,848 MW, +35% YoY, over 15% of India's total renewable capacity addition
Greenfield capacity addition guidance for FY256,000 MW, more than double FY24
Greenfield capacity addition guidance for FY26Similar or slightly higher than 6,000 MW
Annual greenfield capacity execution range6,000 to 8,000 MW
Locked-in PPAs20 GW
Revised 2030 renewable energy capacity target50 GW, up from 45 GW, 100% fully funded from debt and equity
Pumped hydro storage target by 2030At least 5 GW, first 500 MW project in Andhra Pradesh under construction, commissioning by FY27
Pumped hydro capital cost₹4.5 cr to ₹5 cr per MW
Solar capital cost~₹5 cr per MW, at ~1.35 AC-DC ratio, inclusive of BCD and domestic modules
Wind capital cost~₹6.5 cr per MW
Merchant capacity (PPA not yet signed)~550 MW, about 5% of portfolio capacity
Future merchant and C&I mix guidance~10% of portfolio
Refinanced Restricted Group 1 bondUS $409 million, 18-year issuance, oversubscribed 6.5x