Key Takeaways
- Execution engine hits its stride at Khavda: Over 4 GW operationalized in two years, with solar CUF exceeding 32% in the last quarter, proving the site's world-class resource potential.
- Capital recycling milestone de-risks growth: A $1.06 bn construction facility was refinanced with AA+ rated, 19-year door-to-door debt, matching asset cash flow lifecycles and validating the project finance model.
- FY25 capacity addition fell short on weather, not demand: ~3.2 GW commissioned against a 5 GW target, as extended rains and soil conditions at Khavda delayed execution; management has baked those learnings into a 150% step-up target for FY26.
- PPA strategy is paying off in tariff premiums: By waiting to contract capacity as hybrid projects, the company locked in significantly better tariffs on the 10 GW of PPAs signed last year, with two-thirds already executed.
- What to watch next quarter: Whether the 4 GW of new evacuation capacity due by June arrives on time, the pace of commissioning against the ~4.8 GW FY26 target, and any policy movement on the ISTS waiver that could reshape the merchant strategy.
Khavda: The Engine Becomes Visible
- Scale and speed: Over 4 GW operationalized in two years at a single site, with the company on track to complete the full 30 GW by 2029.
- Technology driving CUF: Bifacial N-type modules, single-axis trackers and robotic cleaning systems pushed solar CUF above 32% in the last quarter, a run rate management expects to sustain on an annualized basis going forward.
- Wind performance bifurcated: Portfolio wind CUF of 27% reflects the age of older assets; newer 5.2 MW turbines at Khavda are delivering over 35% CUF, though last year's wind resource was below assumptions across all developers.
- Evacuation is the next gate: An additional 4 GW of transmission capacity is expected by June and 7 GW by December, which management says should be sufficient for its commissioning plans.
- Stabilization is now routine: Last year's capacities are fully integrated and performing at their best; capacities commissioned in the most recent quarter are in a 1-2 month stabilization phase.
Khanna: "Not able to get it across. But on a decent, that's why I exemplify the last quarter, and that will be the quarter in front too. So in monsoon it will change across as such. But on a good sunny day as we have, like we had the last quarter and we do expect it in this quarter itself, it will be definitely on this range, if not above it."
FY25 Miss: Weather, Not Structural
- The shortfall: ~3.2 GW commissioned against a 5 GW target, a gap management attributed entirely to environmental factors at Khavda: soil conditions and extended rains that stretched beyond normal monsoon months.
- Slippages were site-specific: The Rajasthan (1 GW) and Kadapa (250 MW) projects are on track and performing well; only Khavda saw delays.
- Learnings are now embedded: Management says new initiatives have been taken based on last year's experience, and it is confident about adding 150% of last year's capacity addition in FY26, implying roughly 4.8 GW.
- Debt tie-up already secured: Approximately 95% of the 5 GW FY26 target capacity is under various sanctions, with debt coming from domestic sources (REC, PFC), removing financing risk from the execution equation.
PPA Strategy: Patience Paid Off
- The hybrid premium: The company deliberately stayed away from bidding for a period, choosing to hybridize projects before tying up revenue streams. The result: the 10 GW of PPAs won last year carry significantly better tariffs.
- Contracting progress: Two-thirds of last year's wins are already signed; the balance are very recent and management does not see much challenge in executing them.
- Maharashtra 5 GW timeline: The PPA starts in two years, with an additional 1 GW every six months thereafter; the company intends to follow the contracted timelines.
- Portfolio split target intact: The company aims for 75% contracted with DISCOMs and 25% merchant, C&I or CFDs, a framework that leaves limited uncontracted pipeline beyond the 33 GW already disclosed.
Jain: "Earlier, we were not bidding for good time because we thought it is good that we hybrid our projects for whatever revenue stream we tie up. And that's where you see whatever we have won in the last one year has that tariff numbers being reflecting significantly better premiums."
Merchant: Dynamic, Not Doctrinaire
- FY25 merchant volumes explained: The large volume sold on merchant last year came from projects commissioned ahead of their scheduled COD dates; distribution companies granted NOCs to sell that interim power in the merchant market.
- No guidance on repeat: Management declined to guide for a similar quantum of pre-COD merchant sales in FY26, though some capacities finished this year may seek NOCs for pre-COD power before entering PPAs.
- Realization outlook stable: Merchant realizations are expected to remain around last year's levels: solar at ₹3.6–3.7 per unit, wind at roughly ₹6 including RECs.
- Wind share rising in merchant mix: The company is increasing wind's share in its merchant portfolio, while solar merchant capacity is targeted to capture value around the ISTS waiver until June 2025; post-June capacities can serve the C&I market or become input for pumped storage.
- Battery storage on the radar: The company is working on battery storage and keeping a close watch, but offered no timeline: "in the times to come you will be one of the first ones to hear from us."
Jain: "we play this strategy dynamically to ensure that there is a maximum value which is realized for the capacities which we are putting up."
Pumped Storage & the Optionality Play
- Chitravathi PSP on track: Execution is proceeding on time, with a 72-month (6-year) timeline for the Uttar Pradesh project.
- Revenue strategy deliberately open: Management says a good amount of time remains before deciding whether to sell into the commercial market or tie up a PPA later; the priority is to be among the earliest PSPs to commission.
- The merchant balancing act: Management pushed back against taking a "myopic view on a short-term basis," arguing that merchant remains an important and balanced part of the approach.
Khanna: "our focus is to make sure that the Chitravathi project should be the project which is from the earliest among all the PSPs which anyone else is doing."
Policy & Regulatory Posture
- ISTS waiver strategy is conservative: The company's current planning assumes existing policies remain in place; it will not take risk on assumptions about an ISTS waiver extension, though it will re-strategize if policy changes.
- Management declined to generalize on PPA delays: When asked whether PPA signings are being delayed and bidding is slowing down, management said it is not right to generalize and that Adani Green specifically does not see much challenge.
- Quarterly merchant detail withheld: Management declined to provide quarterly merchant sales and utilization figures on the call, offering to share them separately.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Khavda completion | 30 GW fully built out | By 2029 |
| Total portfolio | 50 GW operational | By 2030 |
| FY26 capacity addition | ~4.8 GW (150% of FY25's ~3.2 GW) | FY26 |
| Khavda evacuation capacity | Additional 4 GW | By June 2025 |
| Khavda evacuation capacity | Additional 7 GW (cumulative) | By December 2025 |
| Maharashtra 5 GW PPA | First capacity delivery | Two years from now |
| Maharashtra 5 GW PPA | Subsequent 1 GW tranches every six months | Per contract agreement |
| Chitravathi PSP (UP) | Project completion | 72 months from start |
| Annual growth rate | ~25% year-on-year capacity increase | Ongoing |
| Portfolio split | 75% contracted / 25% merchant, C&I, CFDs | Target framework |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Revenue from power supply | ₹9,495 cr, +23% YoY |
| EBITDA | ₹8,818 cr, +22% YoY |
| EBITDA | Surpassed $1 bn in FY25 |
| Energy sales | 2,800 crore units, +28% YoY |
| Operational capacity | 14.2 GW |
| Capacity added in Q4 | 2.6 GW |
| FY25 capacity addition | ~3.2 GW, against a target of 5 GW |
| FY26 capacity addition target | 5 GW |
| Target capacity by 2030 | 50 GW |
| Khavda operational capacity | 4.1 GW |
| Khavda solar CUF | >32% in Q4 |
| Wind portfolio CUF | 27% |
| Merchant share of operational capacity | 14% |
| Solar merchant realization (incl. REC) | ₹3.6–3.7 per unit |
| Wind merchant realization (incl. REC) | ~₹6 per unit |
| Merchant units sold (pure) | 220 crore units |
| Merchant units sold (under PPA, pre-COD) | 530 crore units |
| Contracted portfolio (PPA + merchant) | 33 GW (roughly 30 GW PPA, 3 GW merchant) |
| PPAs won in last year | 9.6 GW, of which ~6.25 GW signed |
| Khavda evacuation capacity expected by Dec 2025 | 7 GW |
| Refinanced construction facility | $1.06 bn, 19-year door-to-door tenure, AA+ rated |