Key Takeaways
- Record 5.1 GW greenfield addition, but curtailment cost INR 1,500 crores: The world's largest annual renewable build-out outside China was partly offset by grid curtailment and lower merchant realizations, a trade-off management calls a short-term price for locking in 25-year ISTS benefits.
- Battery storage is the hedge, not an afterthought: 3 GWh installed in months, targeting 10 GWh+ in the coming year, with economics that turn curtailed zero-value power into high-margin evening supply.
- Capacity addition disciplined to 4.5–5 GW for FY27: Management is deliberately slowing from a 7–8 GW capability to match transmission build-out, calling last year's mismatch a mistake it will not repeat.
- 9.5 GW of operating capacity still selling as merchant or infirm: The entire INR 1,500 crore under-recovery hit this unprotected book; 5.3 GW converts to PPAs by December 2026, while 4.2 GW of pure merchant must find long-term contracts.
- What to watch next quarter: Whether the 5.3 GW infirm-to-PPA conversion stays on track for December 2026, the pace of battery commissioning against the 10 GWh target, and any improvement in curtailment as Khavda evacuation expands by 7 GW.
The Curtailment Problem: Scale, Cost and the Battery Answer
- INR 1,500 crores lost in FY26: INR 500 crores from outright curtailment where power went to waste, plus INR 800–1,000 crores from lower merchant realizations versus the prior year, all hitting the 9.5 GW of capacity not under take-or-pay PPAs.
- Solar bore the brunt: Khavda solar CUF would have been ~30% without curtailment, actual was upwards of 27%; wind CUF held at ~29–30% because wind generates in the evening when transmission capacity frees up after solar declines.
- Battery turns waste into margin: Curtailed power carries zero economic value as input, so battery storage charged from it earns significantly higher margin for limited discharge windows, making the economics similar to or slightly better than the core solar/wind portfolio.
- Capital intensity and returns: Battery capex runs INR 1.5 crores per MWh, with an EBITDA thumb rule of INR 25 lakhs per MWh; total battery capex of about INR 15,000 crores is planned over coming years.
- Curtailment is not permanently behind us: Management declined to call a peak, citing India's complex regulatory framework and the sheer volume of capacity being added nationally; the strategy is to insulate Adani Green specifically by adding enough battery storage that country-level curtailment stops being an Adani Green problem.
Sagar Adani: "I don't think that one or anyone can say that this issue is permanently behind us. All we can do is what is in our hand, which is what we are doing, which is making sure that we have enough and more battery capacities being added up that even from a country perspective, if this matter becomes an issue, it does not remain an issue for Adani Green."
Capacity Addition: Record Scale, Then Discipline
- 5.1 GW added in FY26: The highest greenfield annual capacity expansion globally by any company outside China, driven by a rush to commission before ISTS benefits expired so those capacities enjoy the waiver for 25 years.
- Execution capability exceeds what the grid can absorb: The organization can deliver 7–8 GW per year but is deliberately capping FY27 at 4.5–5 GW because transmission and evacuation constraints are the binding limit, not construction speed.
- The ISTS trade-off was deliberate: Management acknowledges a short-term price was paid via curtailment and lower merchant realizations, but frames it as a rational choice to lock in a structural 25-year cost advantage on the capacities added.
- FY27 addition is 100% PPA-backed: Unlike the merchant-heavy FY26, the coming year's 4.5–5 GW will be fully tied to long-term contracts, reflecting the return to a contracted model after the ISTS anomaly.
- FY28 and beyond unguided but gated by transmission: Management will only guide FY28 capacity toward the end of this year, once visibility on evacuation build-out firms up; Khavda alone expects 14–15 GW of additional transmission capacity over the next 12–15 months, with a 3–4 month margin of error.
Sagar Adani: "We are stopping our execution at a number of about between 4.5 to 5 gigawatts, looking at the transmission and evacuation constraints that we expect to happen going forward because unlike the past year, what the mistake that we do not want to repeat going forward is to have capacities coming up and then evacuation not being sufficiently available."
The PPA Overhang: 9.5 GW Seeking a Home
- Two distinct buckets: 5.3 GW is currently selling as infirm power and will automatically convert to PPAs once all elements are in place, with conversion expected incrementally by December 2026 and some residual stretching to March 2027. The remaining 4.2 GW is pure merchant capacity that must be tied up in long-term contracts as soon as possible.
- Infirm selling is not value-destructive: Revenue and EBITDA from infirm sales come over and above PPA economics, so the interim period generates incremental cash rather than a shortfall versus contracted rates.
- The entire INR 1,500 crore under-recovery hit only the unprotected 9.5 GW: PPAs are take-or-pay with no curtailment exposure, so contracted capacity was fully insulated from both curtailment and merchant price weakness.
- Long-term commitment to contracting: Management states more than 90% of capacities added going forward will be tied up in long-term PPAs and contracts; last year's merchant-heavy mix was an anomaly driven by the ISTS deadline.
- C&I demand flows through a sister company: Adani Green does not directly participate in commercial and industrial opportunities; Adani Energy Solutions interfaces with C&I customers including upcoming data centers, and contracts capacity from AGEL at arm's length, market-tested rates currently at INR 2.60–2.80 for solar and INR 3.70–3.80 for wind.
Khavda: The World's Largest Renewable Site
- 9.4 GW operational, 9 GW of transmission active: The site is now the world's largest renewable energy installation, with evacuation capacity recently expanded by additional line commissioning that opened a significant bottleneck and drove the quarter's performance improvement.
- Transmission build-out is the growth gate: An additional 7 GW of evacuation capacity is expected by December 2026, and another 7 GW by March 2027, taking total transmission to 23–24 GW over the next 12–15 months.
- Battery storage at gigawatt scale: 1.4 GWh added in the last year, with 3 GWh installed capacity expected within the next week, representing roughly 50% of India's total operating battery storage capacity.
- Performance metrics with and without curtailment: Solar CUF upwards of 27% actual versus ~30% potential; wind CUF ~29–30% with significantly less curtailment impact because evening generation faces less transmission congestion.
- Group company capacity is separate: 742 MW at Khavda was built for group companies; EBITDA does not accrue to Adani Green, which only earns a project management charge on those assets.
Battery Storage: The Second Engine
- 3 GWh added in 3–4 months, quarterly run rate of ~3 GWh: Management is comfortable maintaining and increasing that pace, targeting north of 10 GWh commissioned in the coming year.
- Economics stack up against core renewables: Capital intensity of INR 1.5 crores per MWh and EBITDA of INR 25 lakhs per MWh produce returns similar to or slightly better than solar and wind, with the added benefit of using otherwise curtailed zero-cost power as input.
- Flexible configuration for evolving markets: Plants may be designed with 2-hour or 3-hour configurations depending on how market structures and demand patterns evolve, giving operational optionality.
- Deployment across three use cases: The 10 GWh capacity will be available for pure merchant storage, stand-alone storage contracts, and FDRE (firm and dispatchable renewable energy) projects; the focus is on locking in and commissioning capacity first, then deploying where economic opportunity is highest.
- Pumped hydro enters the mix: A maiden 500 MW pumped storage project at Chitravathi, Andhra Pradesh aims to complete in the coming year, adding a longer-duration storage option alongside the battery fleet.
Sagar Adani: "The power that is curtailed today goes completely to waste. So when you put a battery storage capacity, you use otherwise wasted power, which has today 0 economic value into the BESS, making the cost of input very, very low."
The 50 GW Target and the Path to FY30
- 50 GW by 2030 remains the stated goal: Management says it is firmly on course and currently gearing up to find a way to deliver, though it declined to give a direct yes/no on whether the target needs review given the increased battery storage focus.
- Composition is 5 GW of solar/wind per year for five years, plus 5–6 GW of pumped storage: Batteries and pumped hydro are energy storage system capacities that sit on top of the generation base, not substitutes for it.
- Execution ramp depends on transmission: If Khavda evacuation capacities open up as expected through FY27, management will look to ramp solar and wind execution in FY28, with exact numbers guided toward the end of this year.
- Interest rate tailwind: The blended rate currently stands at 8.9%, and management expects downward pressure going forward, which would improve project-level returns across the portfolio.
- No FY28/FY29 guidance yet: Management will only commit to capacity on a 12-month forward basis and will guide FY28 toward the end of this year, keeping near-term visibility tight while the transmission picture firms up.
Sagar Adani: "Currently, we are gearing up to find a way to deliver on the target that we've announced."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Capacity addition | 4.5–5 GW, 100% PPA-backed | FY27 |
| Battery storage commissioning | North of 10 GWh | Coming year (FY27) |
| Infirm-to-PPA conversion | 5.3 GW incrementally converted | By December 2026, residual by March 2027 |
| Khavda transmission expansion | Additional 7 GW | By December 2026 |
| Khavda transmission expansion | Further 7 GW (total 14–15 GW added) | By March 2027, with 3–4 month margin of error |
| Pumped hydro | Maiden 500 MW at Chitravathi, Andhra Pradesh | Complete in coming year |
| Long-term PPA share | More than 90% of future capacity additions | Going forward |
| FY28 capacity guidance | Exact numbers to be provided | Toward end of this year |
| 50 GW target | On course, composition: 5 GW solar/wind per year + 5–6 GW PSP | By 2030 |
| Battery capex | About INR 15,000 crores total | Coming years |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue from power supply | ₹11,602 cr, +22% YoY |
| EBITDA | ₹10,865 cr, +23% YoY |
| EBITDA margin | 91.2% |
| EBITDA loss from curtailment in FY26 | ₹500 cr |
| Total EBITDA loss from curtailment and lower merchant realizations in FY26 | ₹1,300 cr to ₹1,500 cr |
| Energy sales | 3,760 crore units, +34% YoY |
| Capacity added in FY26 | 5.1 GW, +35% YoY |
| Cumulative operating portfolio | 19.3 GW |
| Khavda operational capacity | 9.4 GW of wind, solar and hybrid assets |
| Battery capacity added in Khavda in FY26 | 1.4 GWh |
| BESS capacity installed in Khavda (as of call date) | 3 GWh expected within the next week, 50% of India's total operating battery storage capacity |
| Average blended PPA rate | ₹3.10 |
| Solar contracting range | ₹2.60 to ₹2.80 |
| Wind contracting range | ₹3.70 to ₹3.80 |
| Total PPA signed-up capacity | 28 GW |
| Operating capacity under PPAs | 9.7 GW |
| Operating capacity as infirm (PPA-bound) | 5.3 GW |
| Operating capacity as pure merchant | 4.2 GW |
| Planned capacity addition for FY27 | 4.5 to 5 GW |
| Battery commissioning target for FY27 | north of 10 GWh (about 3.3 GW dispatch capacity in 3-hour configuration) |
| Battery capex per MWh | ₹1.5 cr |
| Total battery capex for FY27 | ~₹15,000 cr |
| Total capex guidance for FY27 | ₹40,000 to ₹42,000 cr |
| Blended interest rate | 8.9% |
| Khavda solar CUF | upwards of 27% (without curtailment) |
| Khavda wind CUF | upward of 29–30% |
| CUF impact from curtailment | 2.5% to 3% |
| Additional evacuation capacity expected at Khavda by March 2027 | 14 to 15 GW over the next 12 to 15 months |
| Maiden pumped hydro project | 500 MW at Chitravathi, Andhra Pradesh, expected completion in FY27 |