Adani Power Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/bj5jq3lmhhrsetcx0f8p5g77.pdf

Key Takeaways


Demand & Operating Environment

Nishit Dave: "the power plants will now act more as increasingly as we go along, they will start to act more as balancing power plants. And therefore, the focus would be on keeping the plant uptime as high as possible rather than actually trying to maximize the PLF out of them."

PPA Strategy & Merchant Exposure

Dilip Jha: "You might be witnessing our strategy. So, if you see that 2 years ago, our open capacity and the PPA was 80-20, which got reduced to 84-16. Now this is 90 and 10. So we are very much mindful about the merchant tariffs and rate."

Capacity Expansion & Commissioning Pipeline

Nishit Dave: "Yes. And for the other plants, you can expect commissioning 6 months after Mahan, one unit after the other. So, by the middle of FY '29, all these 3 projects would be completed."

Financial Performance


Godda Plant & Bangladesh Exposure

Dilip Jha: "We are supplying around 10% of Bangladesh total effective capacity... We continued our supply when there was a huge turmoil. There was a lot of hardship over there, but we never ever stopped."

Capex & Funding

Dilip Jha: "we are very much confident that in the planned way, we will add our capacity"

Guidance & Commitments

CommitmentSpecificsTimeline
Capacity commissioning~2.9 GW (Mahan Phase-II, Korba Phase-II units)FY27 (next year)
Capacity commissioning2.4 GWFY28
Capacity commissioning2.4 GW (Mahan, Raipur, Raigarh all complete)By mid-FY29
Capacity commissioning8 GWFY30
Capacity commissioning5.6 GWFY31
Capacity commissioning2.4 GWAfter FY31
Plant availabilityFull-year availability above 90%FY26
Merchant exposure reductionReduce from current 10% to 3-4%Over 6-7 years
New capacity PPA tie-upEntire 24 GW pipeline tied up in long-term PPAsNo date (intent stated)
Q4 demand and PLFHigher than Q3Q4 FY26
Long-term EBITDA and FFOAverage EBITDA INR 22,000 cr, FFO INR 20,000 crBy FY31-32
Rajasthan tenderDISCOM to re-present case with supporting information to regulatorNo date (process ongoing)

Key Metrics

MetricQ3 FY26
Continuing total revenue₹12,717 cr, vs ₹13,434 cr in Q3 FY25
Continuing EBITDA₹4,636 cr, vs ₹4,786 cr in Q3 FY25
Continuing PBT₹2,800 cr, vs ₹2,659 cr in Q3 FY25
PAT₹2,488 cr, vs ₹2,940 cr in Q3 FY25
Prior period income₹278 cr, vs ₹1,400 cr in Q3 FY25
Fuel cost₹6,800 cr, 9.7% lower YoY
Continuing operating expenses₹1,280 cr, up 14.8% YoY
Total debt₹45,331 cr as of 31 Dec 2025
Net debt₹38,679 cr as of 31 Dec 2025
Power sales volume2,360 crore units, vs 2,330 crore units in Q3 FY25
Plant load factor62.6%, vs 63.9% in Q3 FY25
Installed capacity18.15 GW as of 31 Dec 2025
Capacity tied up under PPAsMore than 90% of operating fleet
Merchant sales volume430 crore units
Merchant realization₹4.37/kWh, vs ₹4.56/kWh in Q3 FY25
Godda plant PLF68%, vs 50% in Q3 FY25
Godda plant continuing EBITDA₹1,092 cr, vs ₹1,222 cr in Q3 FY25
Weighted average cost of borrowingLess than 9%
Employee cost₹216 cr, includes ₹56 cr one-time provision for New Labour Codes