Adani Power Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://www.stockscans.in/document/mddxnh19s2h4zf9gn011d9nb.pdf

Key Takeaways


Quarterly Performance: Heatwave-Fueled Records

Khyalia: "We have earlier said that going forward, we would like to tie up almost everything through medium term or long term PPAs to reduce volatility inherent in merchant prices."

Capacity Expansion: The March to 45 GW

Jha: "Net debt-to-EBITDA as on date, is slightly higher than 2 timex. We are expecting that net debt-to-EBITDA will not cross 3 times at any point. So this net debt to EBITDA level of between 2 to 3 will persist over this period of time."

Nuclear & Diversification: Ambition Without a Clock

Khyalia: "As I explained earlier, for nuclear, we have only stated our intention. So until the Government of India notifies the rules, we cannot decide exactly in which year, how much we will invest and when we can commission the projects, because we are waiting from last 6 months or so for the rules to come, but the rules have yet not come."

Acquisitions & Strategic Moves


Bangladesh & Receivables


Guidance & Commitments

CommitmentSpecificsTimeline
Korba Phase-II commissioning1,320 MW commissionedBefore December end, current year
Mahan Phase-II first unit800 MW (of 1,600 MW) commissionedQ1 next financial year
Mahan Phase-II second unit800 MW commissionedQ3 next financial year, trying to pull to Q2
Portfolio target45 GWFY2031 or beyond
Net debt-to-EBITDA ceilingWill not cross 3x at any pointThroughout the capex period
180 MW Jaiprakash plant revivalPlant operational and contributing~6 months to revive; good contribution next year
Nuclear investment decisionCannot decide until government notifies rulesNo timeline; waiting for 6 months already
QIP executionEnabling provision only; timeline to be communicatedNo timeline given

Key Metrics

MetricQ1 FY27
Continuing revenue from operations₹17,550 cr, +28% YoY
Total continuing revenue (incl. other income)₹17,936 cr, +27% YoY
Total reported revenue (incl. prior period)₹19,322 cr, +33% YoY
Continuing EBITDA (excl. prior period items)₹6,983 cr, +22% YoY
Reported EBITDA₹8,369 cr, +36% YoY
Profit after tax₹4,867 cr, +47% YoY (up from ₹3,305 cr in Q1 FY26)
Profit before tax (continuing basis)₹4,914 cr, +29% YoY
Fuel cost₹9,513 cr, +30% YoY, driven by higher dispatch volumes and imported coal indices
One-time prior period revenue recognition₹1,386 cr, primarily from revision in historic energy charges under certain PPAs
Consolidated plant load factor78%, vs 67% in Q1 FY26
Consolidated power sales volume~2,900 cr units, +17% YoY (vs 2,500 cr units in Q1 FY26)
Power sales under PPAs2,500 cr units, +30% YoY
Merchant sales volume400 cr units, vs 600 cr units in Q1 FY26 (one-third reduction)
PPA tariff realization₹5.93 per unit, +8% YoY
Merchant and short-term realization₹7.04 per unit, +13% YoY
Total debt outstanding (as of Jun 30, 2026)₹58,381 cr
Net debt (as of Jun 30, 2026)₹47,643 cr
Net debt-to-EBITDASlightly above 2x, expected to remain between 2x and 3x during expansion period
Expansion capex (FY27)~₹25,000 cr
Expansion capex (FY28)~₹33,000 cr
Expansion capex (thereafter)>₹35,000 cr
Total capex program>₹2 lakh cr over next few years
Annual funds from operations₹20,000 cr
Upcoming capacity tied under long-term PPAs56%
Capacity under PPAs (operational)95% tied up; ~5% open capacity
Bangladesh receivables (end of Jun 2026)~USD 40 cr, with average monthly collection of ~USD 10 cr
Godda generation251.9 cr units, vs 236.2 cr units in Q1 FY26
Godda total revenue₹2,473 cr, vs ₹2,135 cr in Q1 FY26
Korba Phase-II (1,320 MW) commissioningExpected before December end 2026
Mahan Phase-II (1,600 MW) commissioningFirst unit expected Q1 FY28, second unit Q3 FY28 (targeting Q2)
Raipur Phase-II execution progressOver 62%
Raigarh Phase-II execution progressOver 54%
Target capacity45 GW, revised from 42 GW, same timeline (FY31 or beyond)