Key Takeaways
- Strong volume-led quarter, one-time items inflate PAT: Continuing revenue grew 29.8% YoY on 11.5% volume growth, while reported PAT surged 141.5% to ₹7,019 Cr, boosted by a ₹2,422 Cr onetime prior period revenue recognition and a net tax credit.
- Strategic shift from merchant to contracted sales: Merchant volumes fell 43% YoY as the company locked previously open capacity into medium-term PPAs, improving revenue visibility and capturing a 33% surge in short-term tariffs on the remaining merchant book.
- Fuel cost lag temporarily pressures margins: A ~50% rise in imported coal cost hit Q2, but the index-linked pass-through for Gujarat PPAs takes over six months, meaning the benefit will not appear for two more quarters and margins would have been higher otherwise.
- Execution pipeline is deep and broadening: Korba Phase-II Unit 1 synchronized, Raipur Phase-III (1,600 MW) announced, and the company entered hydro via the GVK Energy acquisition and a Bhutan JV, diversifying beyond thermal.
- What to watch next quarter: The pace of commissioning for Korba Units 2 and 3, the outcome of UP, West Bengal, and Rajasthan PPA bids, and whether the imported coal tariff pass-through begins to lift margins in H2.
Volume & Realization: The Shift to Contracted Sales
- Volume growth driven by availability and demand: Sales volume rose 11.5% YoY to 2,640 crore units, supported by high plant availability and intense power demand from economic momentum and a weak monsoon.
- PLF jumped on lower hydro generation: Operating PLF reached 70.1% versus 62.8% a year ago, well above the normal expectation of 65%, because hydro generation availability was lower during the quarter.
- PPA sales expanded sharply: Sales under long-term and medium-term PPAs grew 29.7% to 2,340 crore units, reflecting increasing offtake by DISCOMs and a larger capacity base operating under PPAs compared to last year.
- PPA realization improved: Realization rose 12.7% on a continuing basis, supported by pass-through of import coal indices and recently signed medium-term PPAs.
- Merchant volumes deliberately shrunk: Merchant and short-term volumes were 43% lower YoY because the company strategically tied up previously open capacities under medium-term contracts, sacrificing volume for revenue stability.
- Merchant tariffs surged on residual book: Short-term merchant tariffs jumped 33% per unit, capturing strong demand momentum on the capacity that remained uncontracted.
One-Time Items & Accounting Choices
- Prior period revenue recognized: ₹2,422 Cr in onetime net prior period revenue was booked, primarily from revision of initial energy charges for Gujarat PPAs where indexation has been applied in subsequent years; the past period recovery was completed across three installments over the last two quarters and no further recovery remains.
- Haryana claim derecognized despite cash received: ₹1,970 Cr in revenue was reversed for Haryana DISCOM alternate coal compensation claims because discussions are ongoing and the issue is not fully settled; management adopted a conservative accounting approach on auditors' advice even though 50% of the claim amount has already been collected.
- Finance costs declined on disciplined management: Finance costs fell 9.7% YoY to ₹760 Cr, and dropped QoQ from ₹900 Cr, driven by disciplined debt and liquidity management; net debt remained flat at ~₹45,000 Cr despite gross debt rising to ₹61,860 Cr, aided by a ~₹6,000 Cr receipt from GUVNL.
- Other expenses and income moved on reversals and lower interest: Other expenses declined QoQ due to reversal of provisions made in the prior year, while other income fell because interest income from fixed deposits was comparatively lower than Q2 of last year.
Khyalia: "Though we have received the money, we want to have a conservative approach unless it is completely settled and both parties are on the same page. So we decided that we should reverse it, though we have received the money."
Fuel Costs & the Margin Lag
- Imported coal cost surged: Total fuel cost rose 41.8% YoY to ₹10,229 Cr, driven by increased volumes and an approximate 50% increase in the landed cost of imported coal.
- Domestic coal cost edged up on seasonal quality: Effective cost of domestic coal rose slightly due to lower quality of coal received during the monsoon, a normal seasonal phenomenon; Coal India did not increase notified prices.
- Index pass-through delayed by over six months: For Gujarat PPAs with index-linked tariffs, the increase in imported fuel cost from Q2 will not be reflected in the next two quarters and will probably appear only in the third quarter, meaning the Q2 fuel cost increase did not immediately pass through and slightly depressed margins.
- Bangladesh PPA benefits immediately from higher coal prices: The tariff is determined based on international prices and gets reflected immediately in billing with no time lag, providing a positive offset.
Khyalia: "This increase of imported fuel cost will get reflected almost after more than 6 months. Therefore, it will not get reflected even in next quarter because the indexing mechanism is such that whatever fuel prices has remained in this quarter will not get reflected in next two quarters."
Capacity Expansion & Project Pipeline
- Korba Phase-II progressing: The first 660 MW unit achieved grid synchronization and commercial commissioning is expected shortly, in Q3 FY27; the second unit is planned for Q4 FY27.
- Raipur Phase-III announced: A third phase of expansion adding 1,600 MW of ultra-supercritical capacity will expand the Raipur site to 4,570 MW, supplying a second long-term PPA to Maharashtra DISCOM.
- Mahan Phase-II targeted for early FY28: The 1,600 MW project is at an advanced stage with commercial operations targeted for early FY28.
- Hydro entry via two routes: The company was declared the successful resolution applicant for GVK Energy Limited under CIRP, marking entry into hydro generation through the operational 330 MW Alaknanda plant in Uttarakhand; separately, a shareholders' agreement was signed with Druk Green Power for a 770 MW hydropower project in Bhutan through a 49:51 JV, the second joint development in Bhutan after the 570 MW Wangchhu project.
- Uttarakhand PPA secured for Korba: A letter of award was received for a 25-year PPA of 1,320 MW from Uttarakhand Power Corporation Limited, to be supplied from the upcoming Korba 2 power project; power will start after 4 years, and during the interim the capacity will be placed in the medium-term or merchant market.
- Multiple PPA bids in play: Bids have already been submitted for UP and are likely to be opened this month or early next month; a 1,600 MW bid for West Bengal and a Rajasthan bid are both to be submitted in the first week of next month; a Gujarat PPA is in preparation but slightly behind in progress.
- Nuclear power entry awaits rule notification: Draft rules and regulations have been circulated for comments and the stakeholder process is complete; capacity expansion will proceed once rules are notified.
Demand Thesis & Strategic Positioning
- Thermal demand underpinned by data centers: Management expects data centers to be significant power guzzlers requiring baseload thermal power, noting that data center load has not yet started being seen and demand is likely to increase further.
- Government thermal target provides comfort: A government statement on thermal capacity addition potentially extending beyond the 97 GW target for 2035 was welcomed; management indicated it may revisit its own capacity addition strategy going forward.
- India needs over 100 GW of new thermal by 2032: Management cited this figure as the structural demand driver behind its expansion plans.
- Power market expected to strengthen in FY28: Given demand growth patterns, the power market is expected to be quite strong next year, and capacity expansion plans are aligned with expected demand growth.
- Capacity target set at 45 GW by 2032: This comprises 42 GW from new capacity additions plus 3 GW through inorganic acquisitions in the pipeline, as noted in the presentation.
Khyalia: "When a data center says that it wants to consume the green power, they are only taking green certificates. Ultimately, reliable 24/7 power, not missing even a second, can be supplied only by the thermal power projects."
Balance Sheet & Credit Profile
- Credit rating upgraded to AA+: The upgrade from AA by CARE Ratings and India Ratings reflects the operating track record, strong cash flows, market leadership, revenue visibility, and balance sheet flexibility.
- Capex funded primarily through internal accruals: Debt is relied upon only to the extent of any gap between accruals and capex funding requirements.
- Peak debt expected around ₹1 lakh crore by FY30 or FY31: Management provided this estimate as the outer bound of leverage during the expansion cycle.
- Finance costs expected to remain largely flat: Despite increasing market-linked interest rates, improving credit ratings are expected to offset pressure and keep interest and financing costs stable.
- Management pushing for further rating improvement: In discussions with rating agencies, management is arguing that the entire borrowing can be easily serviced from existing operations and hopes the rating will improve further.
Khyalia: "In my recent discussion with the rating agency, I made the same argument that our entire borrowing can be easily serviced from my existing operations."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Korba Phase-II Unit 1 commissioning | First 660 MW unit commercial operations | Q3 FY27 (shortly) |
| Korba Phase-II Unit 2 commissioning | Second 660 MW unit commercial operations | Q4 FY27 |
| Mahan Phase-II commissioning | 1,600 MW commercial operations | Early FY28 |
| Imported coal tariff pass-through | Gujarat index-linked PPA fuel cost increase reflected in tariffs | After ~6+ months (not in next two quarters) |
| Peak debt | ~₹1 lakh crore | FY30 or FY31 |
| Capacity target | 45 GW (42 GW new + 3 GW inorganic) | By 2032 |
| Uttarakhand PPA power supply start | 1,320 MW from Korba 2 | After 4 years |
| Nuclear power capacity expansion | Proceed once rules are notified | After rule notification (date unspecified) |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Continuing revenue from operations | ₹17,014 cr, up 29.8% YoY from ₹13,106 cr |
| Total continuing revenue (incl. other income) | ₹17,528 cr, up 28.5% YoY |
| Total reported revenue (incl. onetime items) | ₹19,951 cr |
| Continuing EBITDA | ₹6,321 cr, up from ₹5,333 cr in Q2 FY26 |
| Reported EBITDA | ₹8,743 cr, up 45.7% YoY |
| Consolidated profit after tax | ₹7,019 cr, up 141.5% YoY from ₹2,906 cr |
| Finance costs | ₹760 cr, down 9.7% YoY from ₹842 cr |
| Sales volume | 2,640 crore units, up 11.5% YoY |
| Plant load factor | 70.1%, vs 62.8% in Q2 FY26 |
| PPA realization | Improved by 12.7% on a continuing basis |
| Short-term merchant tariffs | Surged by 33% per unit |
| Merchant and short-term volume | 43% lower YoY |
| Long-term and medium-term PPA sales volume | 2,340 crore units, expanded by 29.7% YoY |
| Total fuel cost | ₹10,229 cr, up 41.8% YoY |
| Imported coal landed cost | Increased ~50% YoY |
| Total debt (as of Sep 30, 2026) | ₹61,860 cr, vs ₹53,556 cr as of Mar 31, 2026 |
| Net debt (as of Sep 30, 2026) | ₹45,846 cr, vs ₹45,022 cr as of Mar 31, 2026 |
| Onetime net prior period revenue | ₹2,422 cr, from revision of Gujarat PPA energy charges |
| Net tax credit | ₹231 cr, due to reversal of provisions from subsidiary amalgamation |
| Credit rating | Upgraded to AA+ from AA |
| Secured long-term PPAs for upcoming thermal pipeline | 62% of 24 GW pipeline |
| Uttarakhand PPA fixed charge | ₹4.30 per unit |
| Derecognition of revenue (Haryana DISCOM coal compensation) | ₹1,970 cr reversed, 50% of claim amount received |