Advait Energy Transitions Limited Guidance Report - SOIC x StockScans Report

as of Nov 2026

  1. 150 MW/300 MWh Junagadh BESS - COD due Nov 2027 On track - At the Q1 FY27 PPT, the GUVNL BESS project (150 MW/300 MWh, Junagadh) carried a Scheduled Commercial Operation Date of Nov 2027, with BESPA executed and commencement expected in Q3 FY27. The Q2 FY27 PPT shows the project ongoing.
  2. PTS margin - EBITDA between 14% to 16% Delivered - At the Q2 FY26 call, management hoped to continue the same PTS margin year-on-year, "basically EBITDA between 14% to 16%". PTS PBIT margin was 16.65% in FY25 and 17.21% in FY26; standalone EBITDA margin was 15.78% in FY26, 16.2% in Q1 FY27 and 16.50% in Q2 FY27.
  3. No fresh capex in FY27 Missed - At the Q2 FY26 call, management said that apart from capex already tied up for the current year, AETL will not incur any fresh capex in the coming financial year. At Q4 FY26 this was replaced by capex guidance of \~₹300-350 crores for FY27, and H1 FY27 saw ₹101 crore of incremental capex.
  4. No equity raising for existing operations Partial - At the Q2 FY26 call, management stated no equity raising is foreseen for existing operations, which would sustain on bank limits. Through H1 FY27 no equity was raised and \~₹100 crore of capex was debt-funded with D/E at 0.86x, but by Q2 FY27 management was "in process to raise some fund maybe in Q3 or Q4" including equity.
  5. Private placement - 5.9 lakh shares at ₹1,388/share Delivered - At the Q4 FY24 PPT, the board approved issuing 5.9 lakh shares at ₹1,388/share aggregating ₹82.3 Cr via private placement to Ashish Kacholia, RBA Finance & Investment and others. By the Q3 FY25 call, total preferential allotment including convertible warrants of ₹107.44 Cr was secured in FY25, with ₹88.58 Cr received.
  6. Debt-to-equity - about 0.5 to 0.7 for manufacturing and solution business Partial - At the Q2 FY27 call, management guided the debt-to-equity ratio for the manufacturing and solution business at "about 0.5 to 0.7", noting it may shift during the transition. Consolidated D/E stood at 0.86x as of H1 FY27 versus 0.42x in March 2026.
  7. Group EBITDA margin - 15% by FY28-29 On track - At the Q2 FY27 call, management targeted a 15% group EBITDA margin once the manufacturing setup is established in the FY28-29 timeframe, with margins progressing 1 to 1.5% every year. H1 FY27 consolidated EBITDA margin was 14.17% and Q2 FY27 14.46%, against FY26's 11.73%.
  8. ₹5,000 crore top-line target - roughly 5 years (\~7x FY26 revenue) On track - At the Q2 FY27 call, management reiterated the \~₹5,000 crore top-line target over roughly 5 years, stating "it is feasible to make this revenue target by the specific timeline" and citing historical 50-60% CAGR, while confirming ₹5,000 crore stays the base number. FY26 revenue was ₹715 Cr, TTM ₹839 Cr, and H1 FY27 revenue ₹400 Cr, up 45.4% YoY.
  9. Dividend - ₹2 per share for FY26 Pending - At the Q4 FY26 call, the board recommended a dividend of ₹2 per equity share for FY26, subject to shareholders' approval. No record of shareholder approval or payment appears in our notes.
  10. Solar EPC - secure pure-play orders in FY27 Delivered - At the Q4 FY26 call, management said the company will bid and expects to secure a few pure-play solar EPC orders this year itself, with \~100 MW of ground-mounted solar EPC in final stages of award. In Q2 FY27 the NRE segment won a ₹116 crore solar EPC order for a 200 MW project from KPI Green Energy.
  11. SPV electricity revenue in consolidated statements once BESS projects achieve COD - possibly by FY27 end Pending - At the Q4 FY26 call (June 2026), management said electricity generation revenue would be reported separately in an SPV within consolidated statements once projects achieve COD, possibly by that financial year end. The Radhanpur 50 MW/100 MWh BESS project is completed, but no separate SPV electricity revenue disclosure appears in the record through Q2 FY27, with the horizon still open until March 2027.
  12. 1 GW BESS build-and-operate plan - by FY30 On track - At the Q4 FY26 call, management set out a 1 GW BESS build-and-operate plan by FY30, with electricity revenue to be reported in an SPV, later framing an initial 1 GW renewable asset platform with a roadmap to 5 GW. Two IPP BESS projects totalling 200 MW/400 MWh are secured - Radhanpur 50 MW/100 MWh completed and Junagadh 150 MW/300 MWh ongoing - under the AURA IPP platform.
  13. PTS division growth - 40-50% for next 5 years On track - At the Q4 FY26 call, management set a PTS vision of 40-50% growth for the next 5 years after capex completion, later targeting "more than 2,500 crore" of manufacturing sales at full capacity and 55-60% growth with 65-75% manufacturing by 2028-29. PTS revenue grew from ₹302 Cr in FY25 to ₹459 Cr in FY26, reached ₹127.22 Cr in Q1 FY27, and \~₹462 crore of PTS orders were secured in Q2 FY27.
  14. Fuel cell manufacturing - Ahmedabad plant, \~1.5 years for manual plant On track - At the Q4 FY26 call, management expected fuel cell delivery/demand from '27-'28, citing a JV MoU with AVL and TECO for an Ahmedabad plant, \~1.5 years to a manual plant and \~2-3 years to an automatic one, and by Q2 FY27 promised a "very important information announcement" on the fuel cell segment by next quarter. A technology transfer agreement is done, ₹22 crore is invested in TECO 2030 technology with the license intact despite TECO's December 2024 bankruptcy, and the fuel cell facility sits in Unit 3 Phase 1 - but no plant is yet operational.
  15. Capex - \~₹300-350 crores in FY27 On track - At the Q4 FY26 call, management guided total capex of about ₹300-350 crores for FY27, comprising \~₹137 crores excluding IPP plus \~₹75 crores for subsidiary facilities, later planning ₹140 crore of further investment in H2 FY27. H1 FY27 incremental capex was ₹101 crore against ₹59 crore in FY26, with CWIP at ₹159.71 Cr.
  16. Margin improvement - \~1 point in FY27 On track - At the Q4 FY26 call, management guided margin improvement of about 1 point in FY27, driven by the manufacturing facility opening, later restating a 15% FY28-29 target with 1 to 1.5% yearly progress. H1 FY27 consolidated EBITDA margin was 14.17% against FY26's 11.73%, with Q2 FY27 at 14.46% versus Q2 FY26's 11.04% - about 2.4 points of improvement.
  17. Order book - ₹1,600-1,650 crores by end of FY27 On track - At the Q4 FY26 call, management expected the order book to reach ₹1,600-1,650 crores by end of FY27, working on \~₹2,000 crores of opportunities for the year, later saying it "will be at least 1.6 to 1.8 times" last year's revenue. The order book stood at ₹1,574.8 Cr as of 30 Sep 2026, up 47% YoY, from ₹1,330.1 Cr in Q1 FY27 and ₹1,303.6 Cr in FY26.
  18. Revenue growth - 40%+ sustained in FY27 On track - At the Q4 FY26 call, management expected sustained revenue growth of 40%+ supported by the strong order book and tender pipeline, later saying the \~₹1,100 crore FY27 track is in line, with growth "about 55 to 60%" crossing ₹1,000 crores. H1 FY27 revenue was ₹400.21 Cr, up 45.4% YoY, with Q2 FY27 at ₹220.94 Cr, up 40.8%, and TTM growth of 48.04%.
  19. Revenue growth - 40-45% in FY26 Delivered - At the Q3 FY26 call, the CFO guided to approximately 40% to 45% revenue growth in 2026, supported by an order book over ₹1,000 crores. FY26 consolidated revenue came in at ₹714.52 Cr, up 80% from ₹397.66 Cr, as management noted at the Q4 FY26 call.
  20. OPGW capacity expansion - 7,000 km to 10,000 km Pending - At the Q1 FY27 PPT, Unit 1 OPGW capacity of 7,000 kms was slated for expansion to 10,000 kms, restated at Q2 FY27. No completion disclosure appears in the record; current capacity is stated as 8,000+ km annual OPGW manufacturing capacity.
  21. HTLS conductor manufacturing - greenfield project by Q4 FY27 On track - At the Q4 FY26 PPT, the new PTS manufacturing facility including the greenfield HTLS conductor project was expected to be commissioned by Q4 FY27. HTLS Conductors remain listed as "Planned" in the PTS portfolio, with High Ampacity Conductors 12,000 km included in Unit 3 Phase 1, not yet operational.
  22. PTS manufacturing expansion - ready by Q3 FY27 On track - At the Q2 FY26 call, management planned to complete the PTS manufacturing expansion by Q3 of FY2026-27, with the ERS facility "going to be ready by next month", later revised to Q4 FY27 commissioning. The ERS plant offers \~350 towers per year, stringing tools capacity is rising from ₹30-40 crores to ₹80-100 crores, \~₹100 crores of PTS capex was done in FY26, NABL approval came at Kadi, and the Gangad facility targets Q4 FY27.
  23. Multi-integrated manufacturing facility at Gangad - fully operational by Q4 FY27 On track - At the Q2 FY26 call, the grand integrated facility at Gangad was to be ready by July 2026, then targeted for full commercialisation by mid-2028, with Phase 1 expected operational by Q4 FY27. CWIP reached ₹159.71 Cr in H1 FY27 versus ₹59.3 Cr in FY26, Unit 3 (4,00,000 sq. ft.) is under construction with Phase 1 capacities of BESS 2.5 GWh, PEM Fuel Cell, HAC 12,000 km and more, but the facility is not yet operational.
  24. BESS revenue potential - ₹1,000 crores+ from FY28 onwards Pending - At the Q4 FY26 call, management expected only \~2 months of BESS manufacturing in FY27 yielding maybe ₹100-200 crores, and ₹1,000 crores+ from that plant from the next year onwards, later sizing the potential at "1,000 to 1,100 crores of revenue per gigawatt-hour" at 100% utilization. The plant is not yet operational; FY26 BESS revenue of ₹46 crore and Q1 FY27's ₹46.58 Cr are from the BOO project, not manufacturing.
  25. BESS plant utilization - 80-85% within 18 months of launch Pending - At the Q4 FY26 call, management expected 80-85% utilization of the 2.5 GWh BESS plant within maybe a year and a half from start, later guiding "about 40 to 60% capacity utilization for the first year". The plant is not yet commissioned, so no utilization data exists.
  26. BESS manufacturing facility - 2.5 GWh operational by Q4 FY27 Partial - At the Q2 FY26 call, management hoped a BESS DC-block facility would be ready by year '26, then targeted commissioning the 2.5 GWh factory by October 2026, revised to Q4 FY27 with machinery orders placed. Final plant and machinery orders are placed with HG Tech, China, an MSA with HiTHIUM covers up to 1 GWh of 314 Ah LFP cells, a MoU with Cospower covers localized containers, and CWIP stands at ₹159.71 Cr - but the facility is not yet operational.
  27. BESS annuity revenue - \~₹16 crores per year for 12 years Pending - At the Q3 FY25 call, management described the BESS business as an annuity distributed over the next 12 years with revenue of \~₹16 crores per year. The \~₹46 crores of Q4 FY26 BESS revenue was EPC revenue from the BOO project, not electricity-selling revenue, the Radhanpur project is completed, and no annuity revenue has been recognized yet.
  28. BESS first project - 50 MW/100 MWh GUVNL annuity, supplies by June 2026 Delivered - At the Q2 FY26 call, management expected the first ₹50-60 crores of BESS supplies in March 2026 and the entire order completed by June 2026, with the GUVNL Phase-IV Radhanpur project (50 MW/100 MWh, 12-year concession) scheduled for Nov 2026 completion, later revised to Q3 FY27 commissioning. \~₹46 crores of EPC revenue was booked in Q4 FY26 and the 50 MW/100 MWh Radhanpur project is completed per the Q2 FY27 PPT.
  29. PTS division capex - ₹100 crores from internal cash flow Delivered - At the Q3 FY26 call, management stated the PTS division capex of ₹100 crores would be managed from internal cash flow and existing funds. At Q4 FY26, \~₹100 crores of capex had been done in the PTS division during FY26, funded from internal funds.
  30. Electrolyzer capex - \~₹200 crores over current and next two FYs On track - At the Q3 FY26 call, management stated the electrolyzer factory capex plan for the current and next two financial years would be close to approx ₹200 crores, clarifying the electrolyzer-plus-BESS ₹200 crores is for FY2027. H1 FY27 incremental capex was ₹101 crore with CWIP at ₹159.71 Cr, though no electrolyzer-vs-BESS split is disclosed.
  31. 100 MW electrolyser manufacturing plant - by end of FY26 Missed - At the Q3 FY26 call, management said the first phase of the 100 MW Electrolyser Manufacturing Plant, within the next phase of 300 MW, would be completed end of FY26, later revised to 100 MW operational by Q4 FY27 and then to a 150 MW Phase 1 in 2027. Only a 30 MW assembly line was commissioned in March 2026; no 100 MW plant is operational.
  32. 30 MW electrolyzer assembly unit - ready by 15 March 2026 Delivered - At the Q3 FY26 call, management committed to putting up the first 30 MW electrolyzer assembly and manufacturing unit in Ahmedabad, ready by 15th of March 2026. The 30 MW electrolyser assembly line at Kadi was commissioned in March 2026 with FAT completed.
  33. Electrolyzer orders - expected Q4 FY26 and Q1 FY27 Partial - At the Q3 FY26 call, management said electrolyzer orders, similar to PTS flows, were expected in Q4 of that year and Q1 of the next. By Q2 FY27, only small projects are disclosed - a completed 300 kW THDC unit and a 1 MW Gujarat EPC-plus-supply project commissioning that quarter - while larger order booking is targeted for FY28 against 1 GW+ of active inquiry.
  34. Electrolyser margins - 8-10% net margin, ₹250-300 crores revenue in FY27-28 Pending - At the Q3 FY26 call, management expected net margin for electrolyzer manufacturing around 8% to 10%, with a ₹200 crores capex expected to generate revenue of ₹250-300 crores within one-two years post-completion, revised at Q4 FY26 to margins of \~5-10% to start, rising to around 20% in FY28. No meaningful electrolyzer revenue is recognized yet - the 30 MW line has minimal revenue, with the 150 MW phase expected operational in FY27-28 and potential of ₹600-1,000 crores.
  35. Electrolyzer revenue - ₹250-300 crores in FY28 On track - At the Q3 FY26 call, management estimated full-fledged revenue from the new electrolyzer facility in FY28 at anything between ₹250 crores to ₹300 crores, later saying the 150 MW phase "should add the value anywhere between 600 to 1,000 crores". The 30 MW line has minimal revenue with utilization intended in FY27-28, against 1 GW+ of active inquiry and a 150-200 MW pipeline.
  36. PLI scheme benefit - commencing FY2026-27, \~₹440 crores over 5 years On track - At the Q3 FY25 call, management said the first PLI benefit would likely commence from FY2026-27 over 5 years for 300 MW per year, totalling approx. ₹440 crores with the major portion in 3-4 years, later moved to production and supplies from 2027 to 2031. PLI of ₹450 crores is confirmed with the 300 MW allocation secured, but with only the 30 MW line operating and 150 MW targeted Q4 FY27, no PLI benefit is yet recognized in reported financials.
  37. NRE share of mix - grow \~5% per year toward \~65:35 Partial - At the Q3 FY25 call, management said the 8-10% NRE revenue mix would grow \~5% per year, later 5-7% or maybe 10%, with a \~65:35 mix next year and order-book parity in 1.5-2 years. FY26 order book reached 64% NRE but slipped to 32% by Q2 FY27, while NRE segment revenue was ₹268 Cr vs PTS's ₹459 Cr (\~37%), short of the guided mix.
  38. No capital deployment for carbon business Delivered - At the Q3 FY25 call, management said it will not deploy balance-sheet capital for the carbon business nor buy carbon credits from the open market. No disclosure contradicting this appears in the record, and the carbon business remains active with I-REC issuance.
  39. Carbon business revenue - ₹13 crores over 3-5 years Pending - At the Q3 FY25 call, management expected carbon revenue from the next year onwards - \~₹2 crores from consultancy and ₹2.5 crores from carbon credit selling - totalling ₹13 crores over 3-5 years. Sustained carbon credit revenue commenced by Q2 FY26 and 63,000 I-RECs were issued in a single month in Q1 FY27, but no specific revenue figures are disclosed.
  40. Carbon credit inventory - \~10x increase by end of next year, 8+ million credits by 2030 Partial - At the Q3 FY25 call, management expected carbon credit inventory to increase \~10x "by end of the next year" from ₹0.14 crore, with an 8+ million credits under management target by 2030 and a tenfold rise anticipated within three years. The Q4 FY25 PPT shows 0.14 crore credits managed with 0.8 crore+ and 0.4 crore verified credits referenced, and sustained revenue plus 63,000 I-RECs issued in Q1 FY27 - but no confirmation of the \~1.4 crore level by end-2025 and no material progress toward 8+ million.
  41. RDSS order book - ₹200-300 crores "very soon" Delivered - At the Q3 FY25 call, management hoped to build an RDSS order book of \~₹200-300 crores "very soon", choosing projects selectively. RDSS order booking reached ₹270 crores by September 2025, alongside ₹167 Cr of SIS scheme orders won in Q1 FY26 and \~₹52 crores of DGVCL distribution orders plus multiple PGVCL orders in Q2 FY27.
  42. 67.5 MW Khavda solar EPC - commissioning by Q2 FY27 Delivered - At the Q1 FY27 PPT, the 67.5 MW Solar EPC project at Khavda was completed with commissioning of the entire project scheduled for Q2 FY27, after earlier timelines of June 2026, March 2026 and Q1 FY27. The 67.5 MW project was completed during Q1 FY27 and is listed as completed in the Q2 FY27 PPT.
  43. 100 MW Adani project - completed by 15 March 2026 Partial - At the Q3 FY26 call, management committed to completing the first 100 MW project with Adani by 15th of March 2026, with the remaining 25 MW of the 100 MW award expected by May 31, 2026. 75 MW was commissioned by Q4 FY26, 67.5 MW completed in Q1 FY27, and the full 100 MWp Khavda Adani project only shows completed in Q2 FY27.
  44. 30 MWp Solar EPC Project at Khavda - commissioned by Jan 2025 Delivered - At the Q2 FY25 PPT, Advait secured a 30 MWp Solar EPC Project at Khavda worth INR 59 Cr, expected to be commissioned by Jan 2025. The Q3 FY25 call placed the KPI Green order under execution with completion in February 2025, and the Q4 FY25 PPT recorded the 30 MWp (DC) subcontract executed for KP Green.
  45. Solar EPC credentials - 100 MW by end of FY25, 250 MW by FY26, 250+ MW per year Partial - At the Q3 FY25 call, management said it was developing at least 100 MW of solar EPC credentials with \~30 MW done within the month, targeting 250 MW for 2025-26 and 250+ MW per year thereafter. Only 30 MW was executed in FY25 and 75 MW commissioned in FY26, though cumulative execution reached \~197.5 MW by Q2 FY27 with the 30 MWp, 100 MWp and 67.5 MWp Khavda projects completed and a 200 MW KPI Green order won.
  46. 300 kW green hydrogen microgrid - THDC Rishikesh Delivered - At the Q4 FY25 PPT, the company showcased a 300 kW microgrid-based green hydrogen plant in Rishikesh, described as India's one-of-a-kind. The Q1 FY27 PPT records India's first operational green hydrogen microgrid (300 kW electrolyser + 70 kW PEM fuel cell) commissioned for THDC India, with the Q2 FY27 PPT noting the THDCIL Rishikesh commissioning.
  47. 1 MW green hydrogen project - completed June 2025 Delivered - At the Q3 FY25 call, management expected the 1 MW green hydrogen project to be completed in June 2025. India's first green hydrogen EPC project was completed by September 2025 with a further 1 MW project in Bharuch delivered that quarter, and the 1 MW KPI Green Hydrogen plant at Matar was completed and commissioned for trials in December 2025.
  48. 300 MW electrolyser manufacturing facility - by 2026-27, expandable to 1 GW Partial - At the Q3 FY25 call, management said the 300 MW electrolyser manufacturing phase should be completed by 2026 with supplies by end-2026 and first year of 2027, expanding to 1 GW in 2-3 years, after earlier Kadi plans of 120 MW expanding to 200 MW/year by 2025 and stated 300 MW/year capacity in Sep 2024, with repeated revisions to 100 MW by end-FY26, Q4 FY27, and a 150 MW Phase 1 in 2027 with 1 GW site capability by 2028-29. Only the 30 MW assembly line at Kadi was commissioned, in March 2026, with minimal revenue and its first 1 MW electrolyzer in-house, while the 300 MW PLI allocation and ₹450 crores are secured and the 5 MW electrolyser testing is demonstrated - no 100/150 MW phase yet operational, Phase 1 at Gangad targeted Q4 FY27.