Key Takeaways
- Record Q1, broad-based strength: Both liquid and LPG logistics delivered their highest-ever Q1 volumes, EBITDA, PBT and PAT, with liquid margins sustained north of 70%.
- Distribution hit by gas-price war, not demand: Volumes dipped as Gujarat Gas slashed prices in what management called a "suicidal attempt"; that has since reversed in July, and EBITDA held up on stronger realizations.
- Capex engine is accelerating, not slowing: The INR4,500 crores plan may finish 6–12 months early, and management sees the pace of spending persisting beyond FY27 as new opportunities surface.
- Mangalore cryogenic LPG is the next structural unlock: A one-of-its-kind terminal in Asia that can evacuate a VLGC in 24–36 hours versus several days for pressurized terminals, saving customers hundreds of crores in logistics cost.
- What to watch next quarter: Whether the July gas-price reversal translates into the guided 150–280 QoQ volume jump in distribution, progress on ammonia-terminal permits, and any clarity on the JV IPO speculation that management declined to address.
Liquid Logistics: Margins, Capacity & the Next Leg
- Margins firmly above 70%: Liquid division margins are significantly north of 70% and expected to sustain on a full-year basis, with no take-or-pay revenues inflating the Q1 print.
- Kandla nearing a milestone: Current capacity reached 970,000 kiloliters, just shy of 0.1 crore metric tons, with another 25,000 kiloliters expected operational next year.
- JNPT on time, on budget: A 110,000 kilolitre terminal will be commissioned later this year, and management hinted at more to come at the same port.
- Mumbai gets a new build: The port has allocated land for a 150,000 kilolitre storage terminal at an estimated cost of INR250 crores, approved by the board and housed under the listed entity, not the JV.
- Mangalore liquid capacity: 71,000 kiloliters set to be operational within the next 12 to 15 months, adding to the liquid pipeline.
- Haldia and Kochi infill: Haldia's 50,000 kiloliters completed last year will reflect in revenue and profitability this fiscal year; Kochi is adding 25,000 kiloliters of liquids.
LPG Logistics: Throughput, Competitive Moats & the Cryogenic Shift
- Mumbai is a throughput machine: The terminal turns its static 20,000-tonne capacity over 80 times a year, berthing more than 7 ships per month, with evacuation via rail, road and the Mumbai-Chakan pipeline into a saturated but captive consumption zone.
- New capacity will not dent Mumbai: Management sees no expected difference in throughput volumes even as new terminals come online, because the market is already saturated and the terminal is embedded in refinery and consumption infrastructure.
- Mangalore cryogenic terminal is the structural differentiator: Existing pressurized spheres (8,000 metric tons) force a VLGC to berth 5–6 times to unload, creating huge inefficiency. The new cryogenic terminal will evacuate a full VLGC in 24–36 hours, with rail and pipeline connections, and is described as one of its kind in Asia.
- Mangalore throughput ambition: At peak with all evacuation modes operational, management expects the terminal to achieve a similar 80x turnaround, serving a 300–500 km radius by road and potentially connecting into the Mangalore LPG pipeline grid.
Murad Moledina: "The pressurized terminal would have a rate under 400 tons, probably if I am not wrong. And that means that you can then calculate — several days. And it's a cost which would run into hundreds — probably INR100 crores on account of inefficiency at Mangalore port on NOC's account."
Distribution Business: The Gas-Price Shock & Recovery
- Q1 volume dip was price-driven, not structural: Distribution volumes fell to 129,000 metric tons from 160,000, but management attributed this entirely to Gujarat Gas cutting natural gas prices to unsustainably low levels, a move that has already reversed in July.
- EBITDA held up on better realizations: Despite the volume drop, distribution EBITDA was only slightly lower at ~INR42 crores versus ~INR45 crores, implying stronger per-tonne realizations that management believes are sustainable going forward.
- Propane comparison flatters last year: Q1 last year saw propane making inroads into the Morbi sector, which drove unusually high volumes and makes the year-on-year comparison look worse than the underlying trend.
- Growth guidance intact: Management reiterated expectations of 25–30% year-on-year volume growth, with a step-up next year when two new cryogenic terminals are commissioned.
- Q2 jump signaled: Based on July trends, management indicated a possible QoQ volume jump of 150 to 280 in Q2.
Murad Moledina: "It was a very kind of suicidal attempt by Gujarat Gas to lower down natural gas prices so low."
Ammonia: The Next Vertical
- First ammonia terminal in Gujarat: Plans have been announced and construction is expected to commence during this fiscal year after receiving all necessary permits, marking the company's entry into a new molecule.
- Vertical integration ambition: Management intends to build more ammonia terminals as the business matures and to become vertically integrated, mirroring the playbook executed in LPG.
- Odisha still exploratory: An analyst flagged a November 2023 news item about a JV receiving approval for an ammonia terminal in Gopalpur, Odisha. Management said it remains in the exploratory stage with nothing finalized, and will disclose only when land and permits are secured.
Capex Trajectory & the Pipeline Beyond FY27
- INR4,500 crores plan running ahead of schedule: The five-year capex plan is now expected to complete in 4 to 4.5 years, a little before FY27.
- Spending will not stop at FY27: Management was explicit that the pace of capital spending is expected to persist beyond FY27 as the company explores further opportunities, citing political stability and robust economic growth as tailwinds.
- Pipavav LPG terminal: Expected to be commissioned in Q1 FY26, with revenue starting in the same quarter.
- Mangalore cryogenic LPG: Commissioning targeted for March 2025, operational in Q1 FY26.
- KGPL pipeline: 95% of welding is done; completion expected December 2024 per guidelines, possibly slipping to March; volumes from the Pipavav terminal expected in FY26.
- Capacity disclosure gap: An analyst requested a capacity chart with projected additions in presentations. Management noted the request but said they cannot go beyond a one-year time frame or projects only actually underway, and will look into incorporating it.
Raj Chandaria: "The opportunities, as we see the clarity about Indian economic growth, of course, with now political stability and robust economy and so on, we see the opportunities coming rapidly and frequently, more — we can't obviously talk about everything — of every opportunity materialize into an actual project."
JV IPO Speculation & Unanswered Questions
- JV IPO news surfaced but got no answer: An analyst asked about a news item regarding an IPO of the joint venture. Management declined to discuss it, calling it premature, and said they will come out with reasoning only when a decision is made. The answer was partially cut off by audio issues.
- Holdco-JV relationship off-limits: When asked about the nature of the relationship between the holding company and the JV, management again declined, citing many considerations to take into account and the prematurity of any disclosure.
- No competing capacity at other ports: Asked about capacity expansions at other ports such as Dahej, management said at least not to their knowledge is anything under construction.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue/EBITDA CAGR | Achieve 25% CAGR over next 3 years, supported by Greenfield and Brownfield expansion | FY25–FY27 |
| Capex plan completion | INR4,500 crores plan completed ahead of original 5-year schedule | 4–4.5 years (before FY27) |
| Pipavav LPG terminal | Commissioned and revenue-generating | Q1 FY26 |
| Mangalore cryogenic LPG | Commissioned by March 2025, operational | Q1 FY26 |
| Mangalore liquid capacity | 71,000 kiloliters operational | Within 12–15 months |
| JNPT liquid terminal | 110,000 kilolitres commissioned on time and on budget | Later this year |
| Mumbai new liquid terminal | 150,000 kilolitres built at INR250 crores | No date (land allocated, board approved) |
| Ammonia terminal Gujarat | Construction commences after permits received | During this fiscal year |
| Distribution volume growth | 25–30% year-on-year growth | FY25 |
| Q2 LPG volume jump | 150–280 QoQ increase based on July trends | Q2 FY25 |
| KGPL pipeline | Construction complete; volumes from Pipavav | December 2024 (possibly March 2025) |
Key Metrics
| Metric | Q1 FY25 |
|---|---|
| Group EBITDA | ₹250 cr, +18% YoY |
| Profit after tax | ₹158 cr, +19% YoY |
| Earnings per share | ₹3.75, +14% YoY from ₹3.30 |
| Liquid segment revenue | ₹143 cr, +24% YoY |
| Liquid segment EBITDA | ₹108 cr, +38% YoY |
| LPG segment EBITDA | ₹142 cr, +7% YoY |
| LPG throughput volumes | 10.12 lakh metric tons, +15% YoY across 4 terminals |
| Distribution volumes | 1.29 lakh metric tons, vs 1.59 lakh metric tons in Q1 FY24 |
| Sourcing business sales volume | 124,000 metric tons, vs 226,000 metric tons in Q1 FY24 |
| Distribution EBITDA | ~₹42 cr on 129,000 metric tons, vs ~₹45 cr on 160,000 metric tons in Q1 FY24 |
| Kandla terminal liquid capacity | 970,000 kiloliters, with 25,000 kiloliters addition expected next year |
| Capex program | ₹4,500 cr by FY27, nearly 50% completed or in progress |
| Mumbai new terminal approved capacity | ~150,000 kiloliters, estimated cost ₹250 cr |
| Mangalore cryogenic LPG project capacity | 85,000 tons, expected operational Q1 FY26 |
| Pipavav LPG expansion capacity | 45,000 metric tons via two cryogenic tanks, expected Q1 FY26 |