Key Takeaways
- Strong headline growth, margin reset: Revenue rose 25.34% YoY and PAT 31.63% YoY, but EBITDA margin compressed 200 bps QoQ to 10.8% as the company front-loaded wage increments and staff additions for its large order book.
- Order book provides election-year insulation: With tendering activity beginning to slow ahead of general elections, management is leaning on a healthy unexecuted order book and its L1 position in a ₹2,840 crore jewellery park project to sustain momentum.
- The ramp-up story is back-end loaded: Multiple large projects (CSTM station, Tata Memorial, Dharavi) are just beginning to bill; the steepest revenue curves are guided for the Jan-Mar quarter and the first half of next financial year.
- Margins are a deliberate trade-off, not a problem: The Q1 employee cost jump to ₹66 crores is the new absolute run rate; management expects the percentage to fall as execution scales, targeting 11.5-12% EBITDA next year.
- What to watch next quarter: Whether the guided billing ramp-ups at CSTM and Tata Memorial materialise on schedule, any update on the jewellery park LOA, and the pace of employee cost absorption as a percentage of revenue.
The Quarter: What Drove the Numbers
- Top-line strength: Turnover grew 25.34% YoY and PAT grew 31.63% YoY, driven by execution across the existing order book.
- Margin compression mechanics: EBITDA margin fell from 12.8% to 10.8% QoQ because employee cost rose to ₹66 crores, absorbing both announced increments and staff strength built up for recently awarded large orders.
- The new cost baseline: Management stated this ₹66 crore employee cost is the new absolute run rate; as a percentage of revenue, it will decline as execution on new projects scales over subsequent quarters.
- Workforce availability: Q1 was slow for all construction companies; the major factor was two Eid holidays affecting the Muslim community, which constitutes roughly 60% of the workforce, not just the monsoon.
- Monsoon drag: July was impacted by heavy monsoon across the country, but Q2 is still expected to be better than Q1.
Uppal: "Yes, we can. I had mentioned that last time, we can."
Order Book & The Election-Year Bet
- Inflow guidance maintained: Management expects another ₹2,000-2,500 crores of order inflow this year, even as tendering activity begins to slow with the approach of general elections.
- L1 in a landmark project: The company is L1 in the ₹2,840 crore International Jewellery Park project in Mumbai; the LOA is expected in 2-3 months, and the execution period is three years.
- Selective bidding: Competitive intensity remains high, but with an election-year slowdown in fresh tenders and a healthy order book, the company is in a position to pick and choose which projects to pursue.
- Unexecuted order book lifespan: The current unexecuted order book is likely to be executed over the next 2-3 years.
- Election-year logic: Management acknowledged a slowdown in fresh tenders but argued that state and central governments will look to showcase ongoing projects, which supports meeting guidance from the existing book.
- Jewellery park details withheld: Management declined to share details on the payment mechanism, security of timely payments, or BGs required, stating it is not yet awarded and is a private project.
Uppal: "Because we have a healthy order book, we are in a position to pick and choose."
Project Ramp-Up: The Back-End Loaded Pipeline
- AIIMS Jammu: Slated for completion towards the end of this calendar year (November/December), on track.
- Bihar Animal Science: Construction has picked up pace; management expects a run rate of ₹10-15 crores per month.
- Station redevelopment: Revenue earnings started from the July quarter for Chandigarh; CSTM revenue booking will begin in about two months.
- CSTM billing trajectory: Management guided a steep ramp: ₹10-15 crores/month in the Oct-Dec quarter, ₹30-40 crores/month in Jan-Mar, and ₹60-70 crores/month in the first half of the next financial year.
- Tata Memorial: Execution has begun and ground is broken; substantial revenue generation starts this quarter (Q2), with a run rate of ₹10 crores+ per month guided for Q3.
- Other projects now billing: The Arbour Project in Gurgaon and Puri (The Aravallis) have started Q2 revenue generation; Dharavi Wastewater Treatment will also start generating revenue in Q2.
- Sion Hospital: Moving at projected pace, billing about ₹4-5 crores per month.
Margin Outlook & Cost Structure
- Current margin and target: EBITDA margin stands at 11% currently; management sees a path to 11.5-12% next year as execution scales up and the elevated employee cost base is absorbed over a larger revenue base.
- Capex run rate: Will remain similar to Q1 at roughly ₹24 crores per quarter as the company adds machinery and shuttering for recently awarded projects; FY24 total capex is guided at approximately ₹100 crores.
- Limit enhancement in process: The company is working to increase its limits from ₹1,940 crores to approximately ₹2,100-2,200 crores.
Bihar & West Bengal: State-Level Exposures
- Bihar payment situation: Some payment issues exist, but two medical hospital projects in the Chief Minister/Deputy Chief Minister's constituency are being fast-tracked for completion this financial year, so payments are expected; other projects (animal husbandry, university) are receiving payments on time.
- West Bengal land monetisation: Nothing will happen this year; any steps will be taken in the next financial year. Management will wait for the general elections to conclude before deciding. The company is not averse to selling if it gets a good price, but is in no hurry.
Uppal: "I can't really say. I mentioned last time around that, if we get a good price which we should, we are not averse to disposing it off also. But whatever we do, we'll let the general elections get over and after that, we'll take a step on that. But we are in no hurry to sell it also."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 20% YoY growth; guidance described as conservative | FY24 |
| Order inflow | Additional ₹2,000-2,500 crores | FY24 |
| EBITDA margin | 11% currently; 11.5-12% targeted | Next year (FY25) |
| AIIMS Jammu completion | Project completion | Nov-Dec this calendar year |
| CSTM station billing ramp | ₹10-15 cr/month → ₹30-40 cr/month → ₹60-70 cr/month | Oct-Dec → Jan-Mar → H1 next FY |
| Tata Memorial run rate | ₹10 crores+ per month | Q3 FY24 |
| Capex | ~₹24 crores/quarter; ~₹100 crores total | FY24 |
| West Bengal land monetisation | No action; decision after general elections | Next financial year |
| Bihar Animal Science run rate | ₹10-15 crores per month | Ongoing |
Key Metrics
| Metric | Q1 FY24 |
|---|---|
| Revenue | ₹763.61 cr, +25.34% YoY |
| PAT | ₹49.73 cr, +31.63% YoY |
| EPS | ₹7.42, vs ₹5.64 in Q1 FY23 |
| EBITDA margin | 10.8%, vs 12.8% in Q4 FY23; employee cost at ₹66 cr on higher staff and increments |
| EBITDA margin guidance | 11% plus, maintained |
| Revenue growth guidance | 20% for FY24, maintained |
| Order inflow (YTD, incl. L1) | ₹7,217 cr, with additional ₹2,000–2,500 cr expected in FY24 |
| L1 position | ₹2,840 cr, International Jewellery Park, Mumbai; 3-year execution |
| Order book – central government | 45% of order book |
| Order book – state government | 32% of order book |
| Order book – private sector | 25.35% of order book |
| Gross debt | ₹7.42 cr |
| Cash and bank position | ₹266 cr cash, ₹280 cr bank |
| Unbilled revenue | ₹379 cr |
| Trade receivables | ₹552 cr |
| Capex (Q1) | ₹24 cr, FY24 target ~₹100 cr |
| Bid pipeline | ~₹2,500 cr |