Ahluwalia Contracts (India) Ltd Q1 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/eog2l52a5wgy9jmz1wt2l7p4.pdf

Key Takeaways


Margin Walk: What Broke and What Fixes It

Uppal: "What the contractors have been saying for the last couple of years that this is an epidemic waiting to happen now while we struggle with labor on the ground... labor shortage is here to stay. Let me qualify that."

Order Book & Bidding Strategy

Uppal: "We want to consolidate. We want the average ticket size to go up. And this has been a conscious decision and we have been kind of building towards it over the last 4-5 years."

Project Pipeline: The Big Swings

ProjectStatus & TimelineRevenue Target
CSMT redevelopmentEntire design revamped because client's international agency concept did not account for local bylaws; client accepted redesign, work started on ground. Rains impacted June-July.FY25: ₹450-₹500 Cr; FY26: ~₹1,000 Cr. H2 monthly run rate >₹50 Cr; FY26 monthly ~₹100 Cr.
Gems & Jewellery ParkAutonomous body under Ministry of Economic Affairs; funded by jewelers plus government equity. Work to start in ~3 months.FY25: ₹125-₹150 Cr; material number in FY26.
Darbhanga & Varanasi airportsDesign interaction with Airports Authority has started; ground-breaking expected in ~2 months.Not quantified.
Sion Hospital Phase-2Company is doing Phase-1 and has bid for Phase-2; described as a large contract.Not quantified.
Animal husbandry project~95% of land handed over; progress softer in Q1 but expected to pick up substantially.Not quantified.
Bihar medical collegesOnly ~10% of jobs (Chakra and Nalanda) left; stuck payments expected to start flowing within a month to month-and-a-half.Completion this financial year.

Balance Sheet & Capital Allocation

Uppal: "I had mentioned in my last call also that there should not be any more surprises, but this is a surprise if there are certain clients who we feel are going to pay off, but if one or the other of their creditors takes them to court or takes them to NCLT, then we have to put this in our, make a provision in our balance sheet."

Revenue Growth & Mix Shift

Uppal: "It takes up a lot of bandwidth. We feel that the margins are not commensurate that we focus or develop this segment especially."

Guidance & Commitments

CommitmentSpecificsTimeline
Full-year EBITDA marginCross double-digit margins for FY25FY25 full year
H2 EBITDA margin~11%H2 FY25
FY26 EBITDA marginH2 FY25 run rate to continue into FY26FY26
FY25 revenue growth15% to 20%FY25 full year
FY26 revenue growthSimilar run rate as FY25FY26
Remaining FY25 order inflow₹2,500-₹3,500 crores moreFY25
CSMT revenue₹450-₹500 croresFY25
CSMT revenue~₹1,000 croresFY26
Gems & Jewellery revenue₹125-₹150 croresFY25
Gems & Jewellery revenueMaterial numberFY26
Emaar settlement receiptMoney expectedBy 31st August
Bihar medical college projectsCompletion of remaining ~10%This financial year
FY25 CAPEX~₹175 croresFY25
FY26 CAPEX~₹125 crore annual ballparkFY26
Long-term public-private mix50-50Long-term (no date)
Residential shareCross 20% (from 13.7%)No date
Darbhanga & Varanasi airportsGround-breaking~2 months
Gems & Jewellery project startWork to begin~3 months
FY26-27 EBITDA marginDouble-digitFY26 and FY27

Key Metrics

MetricQ1 FY25
Revenue₹919.35 cr, +20.39% YoY
EBITDA margin6.58%, vs 10.83% in Q1 FY24
PAT₹30.60 cr, vs ₹49.73 cr in Q1 FY24
PAT margin3.33%, vs 6.51% in Q1 FY24
EPS₹4.57, vs ₹7.42 in Q1 FY24
Revenue growth guidance FY2515% to 20%
H2 FY25 EBITDA margin target11%
Order inflow FY25 to date~₹4,950 cr
Remaining order inflow expected FY25~₹2,500–₹3,500 cr
Order book as of June 30~₹13,000 cr
Order book including post-June wins~₹15,500 cr
Fixed-price contracts in order book24%
Gross debt₹100 cr
Cash and bank balance₹704 cr, cash ₹248 cr plus bank ₹456 cr
CAPEX FY25~₹175 cr, ₹54 cr spent in Q1, ~₹120 cr additional planned
Labor availability in May–June~40% across pan-India sites
Private sector share target~50% of total pie, long-term
Residential market share13.7% currently, expected to cross 20%