Ahluwalia Contracts (India) Ltd Q1 FY2027 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/3x4k9jhwtqtbmlkxvdht68e0.pdf

Key Takeaways


The Quarter's Damage: What Went Wrong

Uppal: "It would be fair to say that this financial year, we are ruling out having a double-digit EBITDA margin."

Labour: The Structural Squeeze

Uppal: "No, no, whole quarter and going forward, the labour cost, once the labour price gets increased, it doesn't come back down."

Client Compensation: The Recovery Mechanism

Uppal: "It's not contractually -- strictly going by the contract, they may not."

Project Portfolio: The Ramp-Up Story


Order Book & Bidding Strategy

Uppal: "We are being conservative as far as the rest of this year is concerned in our approach towards picking up new orders."

Working Capital, Costs & Balance Sheet

Uppal: "We don't want to use our war shares to buy back our shares."

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue growth12–15% top-line growth for FY27; could cross 15% if NGT impact is similar to last yearFY27
EBITDA marginDouble-digit EBITDA margin ruled out for FY27FY27
Margin recoveryHoping to get back to Q1 FY26 margins over the next three quarters, with NGT impact as an unknown riderNext three quarters
Order inflowAt least ₹4,000–5,000 cr for FY27, revised down from ₹8,000 crFY27
Central Vista billingAbout ₹700 cr in FY27; about ₹1,000 cr next yearFY27 / FY28
CST billing₹40–45 cr/month over balance 9 months; roughly ₹400–450 cr in FY27FY27
Dahlias billingNearly ₹30–35 cr every month going forwardOngoing
DLF Downtown billing₹25–30 cr monthly; design issues resolvedOngoing
Gems and Jewellery ParkWork on ground likely to begin in Q3; billing of about ₹100 cr in FY27Q3 FY27 / FY27
Client labour compensationSome compensation expected to start flowing over the next two quartersNext two quarters
Working capitalExpected to return to previous quarter's level due to Assam paymentsCurrent quarter
FY28 marginsAspire to get to double-digit margins in FY28FY28

Key Metrics

MetricQ1 FY27
Revenue₹1,125.81 cr, +12.03% YoY vs ₹1,004.88 cr in Q1 FY26
PAT₹11.42 cr, -77.65% YoY vs ₹51.11 cr in Q1 FY26
EPS₹1.70, vs ₹7.63 in Q1 FY26
EBITDA margin4.29%, vs 8.59% in Q1 FY26
PAT margin1%, vs 5.01% in Q1 FY26
AIIMS Jammu bill reduction₹29 cr, adverse impact of 2.6% on EBITDA; dispute to go to arbitration
Net order book₹20,663.52 cr, to be executed over next 3 to 3.5 years as on 30 June
Order inflow FY27 to date₹512.81 cr, as on 30/06/2026 and up to date
Revenue growth guidance FY2712% to 15%, previous guidance was 15%; NGT impact uncertain
Order inflow guidance FY27₹4,000 cr to ₹5,000 cr, revised down from ₹8,000 cr
Fixed-price contracts share10.34% of total order book
Trade payable₹776 cr
Debtors₹632 cr
Retention money₹401 cr
Inventory including real estate₹391 cr
Mobilisation advance₹924 cr, 31% interest-bearing at average rate of around 8%
Unbilled revenue₹946 cr
Gross debt₹2.28 cr
Cash and bank balances₹920 cr
Working capital cycle119 days, expected to improve to previous quarter's level as Assam payments resume
Capex FY27₹220 cr to ₹250 cr, reduced from earlier ₹300 cr; Q1 capex being reduced to ₹60 cr
Central Vista billing FY27₹700 cr, ramping to about ₹1,000 cr in FY28
CST project billing FY27₹400 cr to ₹450 cr, about ₹70 cr done in Q1; hopeful to cross ₹500 cr vs earlier target of ₹600 cr
Gems and Jewellery Park billing FY27₹100 cr, about ₹450 cr next year; work on ground to begin in Q3
Dahlias monthly billing target₹30 cr to ₹35 cr per month
DLF Downtown monthly billing target₹25 cr to ₹30 cr per month
Labour force10,000 to 12,000 people, 70% skilled
Company-level labour cost impact1.5% of EBITDA this quarter; about 1% ongoing hit if no client escalation
NCR share of order book50% of total portfolio
Private sector share of order book62%
Material escalation clause coverage89% of order book has escalation clause for materials
Project staff costIn excess of 5%, up from 3.5% to 4.5% historically
Safety budgetNearly 3%, up from about 1 percentage point