Key Takeaways
- A brutal quarter, honestly owned: EBITDA margin collapsed to single digits on a threefold hit: a ₹29 cr AIIMS Jammu final-bill reduction, surging NCR labour costs, and elevated staff costs from mobilising for large projects. Management has ruled out double-digit margins for FY27.
- Labour is the structural problem: A 35–40% minimum-wage hike in NCR, skilled labour in extreme short supply, and projects running at 40–50% labour strength for 2–2.5 months. Management says labour prices never come back down.
- Growth guidance survives, order inflow guidance cut: Revenue guidance trimmed only modestly to 12–15% for FY27, but order inflow guidance was slashed from ₹8,000 cr to ₹4,000–5,000 cr as management turns deliberately conservative on bidding.
- The order book is the cushion: ₹20,000 cr+ of backlog, with Central Vista, Dahlias and DLF Downtown all ramping billing meaningfully over the next three quarters.
- What to watch next quarter: Whether client compensation for labour costs actually starts flowing, whether NGT-related disruption materialises in Q3, and whether large-project billing ramps as guided.
The Quarter's Damage: What Went Wrong
- AIIMS Jammu finalisation: The final bill was reduced by ₹29 cr during Q1 after being frozen; costs were already incurred but bill value and receivables came down. The project is now closed, with no potential for further hit, and the reduction becomes an arbitration dispute.
- Threefold EBITDA impact: Management confirmed ~₹30 cr from AIIMS, plus increased staff costs and increased labour costs, broadly split across the remaining impact.
- Margin arithmetic: AIIMS Jammu alone cost 2.6% of EBITDA margin; the rest came from raw materials, increased labour costs and increased staffing costs.
- Finance cost step-up: Interest cost rose sharply on the mobilisation advance for the new Central Vista project; management expects a similar ₹15–16 cr every quarter going forward.
- Depreciation is recurring: Higher depreciation in Q1 is not one-time; it reflects the higher capital expenditure of the last 2–3 years.
Uppal: "It would be fair to say that this financial year, we are ruling out having a double-digit EBITDA margin."
Labour: The Structural Squeeze
- NCR wage shock: Minimum wages in NCR rose 35–40% across unskilled and skilled categories; NCR is nearly 50% of the portfolio, so the impact was immediate and material.
- Demand-supply reality: April–June is traditionally a period of extreme labour shortage; this year was exacerbated by a slew of festivals. 50–60% of labour, or 80% of skilled labour, is Muslim, so festival absences hit harder than predicted, especially in NCR, Haryana and UP.
- Actual wages exceed mandates: Over the past two months, actual payments to bar binders, carpenters and masons have been more than government-mandated rates, driven purely by demand and supply.
- Projects understaffed: All projects, especially in NCR, have been operating at 40–50% labour strength over the last 2 to 2.5 months.
- Skilled labour is the bottleneck: 70% of labour is skilled; skilled labour is in extreme short supply and paid above government-declared skilled wages, while unskilled labour sits at the minimum wage threshold.
- Productivity drag: Skilled manpower shortage is compounded by lower skill levels; buildings are becoming more complex, leading to low productivity and rising costs.
- Quantified impact: Company-level labour cost impact was ~1.5% this quarter; if no escalation materialises, the hit is ~1% because some contracts have pass-through and some have escalation after 6 months to a year.
- No rollback expected: Labour pricing increases never reverse; management sees no rollback coming, calling it a very sensitive political issue.
Uppal: "No, no, whole quarter and going forward, the labour cost, once the labour price gets increased, it doesn't come back down."
Client Compensation: The Recovery Mechanism
- Contractual reality: Strictly going by contract, many large developers are not obligated to compensate for labour cost increases; only a few contracts carry labour escalation clauses.
- Negotiation underway: Management is in talks with NCR clients where the impact is sizable, showing actual costs and telling clients it will be difficult to continue on old pricing.
- Two options offered: Clients can either compensate the impact till now, or supply labour going forward; management says clients are looking at proposals favourably because labour can make or mar a project.
- Timing is uncertain: Management expects some compensation to start flowing over the next two quarters but cannot put a date on whether it will be in Q2.
- Client incentives emerging: Godrej, DLF and Signature Global have started announcing incentives linked to progress or stage-wise timely completion, such as casting a certain number of slabs per month.
- Bidding incorporates new reality: Empirical data from the last 1.5 years is now being incorporated into costing for future tenders; shuttering and steel prices have virtually doubled in bids, and staff costs are now taken in excess of 5%.
Uppal: "It's not contractually -- strictly going by the contract, they may not."
Project Portfolio: The Ramp-Up Story
- Central Vista: Nirman Bhawan completely demolished, foundation casting begun; Udyog Bhawan handed over ~3 weeks ago and 90% demolished. Billing of about ₹700 cr expected in FY27, about ₹1,000 cr next year; the building where Nirman Bhawan existed (~50% of the job) to be commissioned by end of next year, entire project completed in FY29.
- CST project: Average billing of ₹40–45 cr/month over the balance 9 months, roughly ₹400–450 cr in FY27; ramping to about ₹700 cr next year; management hopeful to cross ₹500 cr this year.
- Dahlias: Design changes contributed to less work this quarter; targeting nearly ₹30–35 cr every month going forward.
- DLF Downtown: The ₹1,600–1,700 cr project was delayed by design changes; client is looking to compress the timeline, and the company has further ramped up mobilisation and staffing. Design issues seem to be a thing of the past; targeting ₹25–30 cr monthly billing.
- Gems and Jewellery Park: Client-side design change means work on ground will not begin this quarter; likely to begin in Q3, with billing of about ₹100 cr in FY27 and about ₹450 cr next year; completion timeframe 3.5 years.
- Odisha Government University lapsed: Client asked to increase bid validity; the company refused because it was a fixed-price contract given volatility and cost increases at ground level. The project has fallen through.
- RML Hospital Delhi: Still L1; has not translated into a work order yet.
- NGT overhang: Work on Central Vista has not stopped; impact limited to raw material coming from other parts of the country, with special permissions being sought. Management cannot quantify the EBITDA impact; Q3 is likely to be impacted but magnitude unknown.
Order Book & Bidding Strategy
- Deliberate conservatism: Management is no longer aggressive on order inflows, being conservative for the rest of the year due to material and labour price volatility.
- Guidance cut: Full-year order inflow guidance reduced from ₹8,000 cr to at least ₹4,000–5,000 cr; order book is already ₹20,000 cr plus.
- Bid pipeline: Visibility of ₹5,000–6,000 cr remains.
- Bidding discipline: The company will bid only after factoring in ground realities and fluctuations; it will not bid very aggressively.
- Margin recovery via pricing: Quoting and getting higher rates on newer jobs will help get back to historical high margins.
Uppal: "We are being conservative as far as the rest of this year is concerned in our approach towards picking up new orders."
Working Capital, Costs & Balance Sheet
- Working capital: Currently at 119 days; expected to improve because Assam region payments are now coming through after election-related delays.
- Assam payments: Bills were not getting signed off during elections; the process was streamlined about 15 days ago, and major chunks of outstanding dues are now being received.
- Central government payments: Central Vista, Varanasi and Darbhanga (Airports Authority of India projects) payments are not an issue; one Central University project in Himachal has been unpaid for 5 months because the project went over budget, with bills certified but payments not coming.
- Capex cut: Full-year capex being reduced from ₹300 cr to ₹220–250 cr; Q1 capex reduced to ₹60 cr.
- Staff cost rationalisation: Staff costs should rationalise over the next three quarters as turnover from large projects increases and their contribution to top-line rises.
- Safety cost step-up: Project staff cost used to be 3.5–4.5%, now in excess of 5% due to increased focus on safety measures; safety budget increased from ~1 percentage point to ~3 percentage points.
- Material pass-through: Cement and steel are pass-throughs; the major impact is from labour, not materials.
- Supply chain friction: Switchgear delivery times extended from 4–6 weeks to 3–4 months, impacting ground-level performance.
- Haryana RMC shutdowns: 90% of RMC plants in Haryana have shut down over the past month due to a government crackdown; developer lobbies are talking to the government and some plants may reopen.
- Share buyback: Not on the agenda; focus is on growing the business, digitisation, efficiency and investing in machinery to offset labour shortages.
Uppal: "We don't want to use our war shares to buy back our shares."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 12–15% top-line growth for FY27; could cross 15% if NGT impact is similar to last year | FY27 |
| EBITDA margin | Double-digit EBITDA margin ruled out for FY27 | FY27 |
| Margin recovery | Hoping to get back to Q1 FY26 margins over the next three quarters, with NGT impact as an unknown rider | Next three quarters |
| Order inflow | At least ₹4,000–5,000 cr for FY27, revised down from ₹8,000 cr | FY27 |
| Central Vista billing | About ₹700 cr in FY27; about ₹1,000 cr next year | FY27 / FY28 |
| CST billing | ₹40–45 cr/month over balance 9 months; roughly ₹400–450 cr in FY27 | FY27 |
| Dahlias billing | Nearly ₹30–35 cr every month going forward | Ongoing |
| DLF Downtown billing | ₹25–30 cr monthly; design issues resolved | Ongoing |
| Gems and Jewellery Park | Work on ground likely to begin in Q3; billing of about ₹100 cr in FY27 | Q3 FY27 / FY27 |
| Client labour compensation | Some compensation expected to start flowing over the next two quarters | Next two quarters |
| Working capital | Expected to return to previous quarter's level due to Assam payments | Current quarter |
| FY28 margins | Aspire to get to double-digit margins in FY28 | FY28 |
Key Metrics
| Metric | Q1 FY27 |
|---|---|
| Revenue | ₹1,125.81 cr, +12.03% YoY vs ₹1,004.88 cr in Q1 FY26 |
| PAT | ₹11.42 cr, -77.65% YoY vs ₹51.11 cr in Q1 FY26 |
| EPS | ₹1.70, vs ₹7.63 in Q1 FY26 |
| EBITDA margin | 4.29%, vs 8.59% in Q1 FY26 |
| PAT margin | 1%, vs 5.01% in Q1 FY26 |
| AIIMS Jammu bill reduction | ₹29 cr, adverse impact of 2.6% on EBITDA; dispute to go to arbitration |
| Net order book | ₹20,663.52 cr, to be executed over next 3 to 3.5 years as on 30 June |
| Order inflow FY27 to date | ₹512.81 cr, as on 30/06/2026 and up to date |
| Revenue growth guidance FY27 | 12% to 15%, previous guidance was 15%; NGT impact uncertain |
| Order inflow guidance FY27 | ₹4,000 cr to ₹5,000 cr, revised down from ₹8,000 cr |
| Fixed-price contracts share | 10.34% of total order book |
| Trade payable | ₹776 cr |
| Debtors | ₹632 cr |
| Retention money | ₹401 cr |
| Inventory including real estate | ₹391 cr |
| Mobilisation advance | ₹924 cr, 31% interest-bearing at average rate of around 8% |
| Unbilled revenue | ₹946 cr |
| Gross debt | ₹2.28 cr |
| Cash and bank balances | ₹920 cr |
| Working capital cycle | 119 days, expected to improve to previous quarter's level as Assam payments resume |
| Capex FY27 | ₹220 cr to ₹250 cr, reduced from earlier ₹300 cr; Q1 capex being reduced to ₹60 cr |
| Central Vista billing FY27 | ₹700 cr, ramping to about ₹1,000 cr in FY28 |
| CST project billing FY27 | ₹400 cr to ₹450 cr, about ₹70 cr done in Q1; hopeful to cross ₹500 cr vs earlier target of ₹600 cr |
| Gems and Jewellery Park billing FY27 | ₹100 cr, about ₹450 cr next year; work on ground to begin in Q3 |
| Dahlias monthly billing target | ₹30 cr to ₹35 cr per month |
| DLF Downtown monthly billing target | ₹25 cr to ₹30 cr per month |
| Labour force | 10,000 to 12,000 people, 70% skilled |
| Company-level labour cost impact | 1.5% of EBITDA this quarter; about 1% ongoing hit if no client escalation |
| NCR share of order book | 50% of total portfolio |
| Private sector share of order book | 62% |
| Material escalation clause coverage | 89% of order book has escalation clause for materials |
| Project staff cost | In excess of 5%, up from 3.5% to 4.5% historically |
| Safety budget | Nearly 3%, up from about 1 percentage point |