Key Takeaways
- Flat revenue, margin expansion: Turnover was flat YoY at ₹622.84 cr as excessive rainfall and NCR pollution curbs wiped out working days, yet EBITDA margin still improved to 10.99% from 10.04% a year ago.
- Order inflow running hot: The company may surpass its ₹3,000 cr inflow guidance by ~₹1,000 cr, with a healthy order book set to convert into substantially higher turnover in the last two quarters.
- Margin push is the priority: Management is being conservative in bidding and has a concerted push to exit the year at ~12% EBITDA margin, a level it expects to maintain into next year.
- Private-sector discipline is a tailwind: Large private clients are consciously choosing proven contractors, which management believes will improve private-sector margins, even as public-sector competitive intensity stays high.
- What to watch next quarter: Whether the promised second-half turnover surge materializes, whether Bihar payment flows improve after political intervention, and whether the Emaar MGF arbitration restarts with a new presiding arbitrator.
Revenue Headwinds & Recovery Path
- Rain and pollution stole working days: Excessive rainfall across the country and 15–20 days lost to NCR pollution-related curbs compressed Q2 turnover. Management believes the pollution disruption is behind them.
- Second-half surge expected: The last two quarters traditionally carry a higher run rate, and the company is geared up to increase turnover substantially over the next 4.5–5 months of FY23.
- Large NCR wins ready to convert: A couple of large marquee projects won in NCR this financial year will begin contributing to turnover in the next two quarters.
- South India entry underway: Operations have started or restarted in Bangalore with projects aggregating about ₹450 cr, and the first Hyderabad project has begun. The company is bidding commercial work in the South but is very cautious on residential.
Management: "11%, Ashish. And sorry to pre-empt you, but I have a peer comparison in front of me. I think we've beaten the margins of some of my closest peers, smaller and bigger than us."
Order Book & Pipeline
- Inflow guidance comfortably exceeded: Order inflow guidance was ₹3,000 cr; management now expects to surpass it by about ₹1,000 cr. Another ₹1,000 cr of inflows is targeted for the second half.
- Pipeline is robust and diverse: The ₹5,000 cr bid pipeline spans railway station development, airports, hospitals, institutional buildings, campuses, and commercial projects.
- Design-build EPC projects nearing construction: Many projects in the healthy order book are design-build EPC contracts where actual ground-level construction will begin in the next month or so, with site mobilization expenses already absorbed. This supports the margin expansion thesis.
- Key project timelines: Jammu project (biggest), Adani data center, Bennett University, Muthoot Hospital, and Sant Nirankari Hospital all to be completed in the next 12 months. Hamirpur and Chamba hospitals to finish in 9–10 months.
Margins: The Concerted Push
- EBITDA margin improved despite flat revenue: Margin rose to 10.99% in Q2 FY23 from 10.04% in Q2 FY22, absorbing the overhead impact of lost working days from excessive rainfall.
- Conservative bidding to protect margins: Competitive intensity remains high on public-sector contracts, so the company is being selective and conservative in bidding, with a stated concerted push to push up margins.
- Exit-rate target of ~12%: Management is striving to exit FY23 at around 12% EBITDA margin and expects to maintain that run rate next year. The logic rests on design-build projects where mobilization costs are already done and construction revenue is about to begin.
- Private-sector margins expected to improve: Greater discipline among large private clients, who are consciously choosing proven contractors with proven track records, should support better margins on the private-sector side, especially for non-residential projects.
- Competitive intensity to persist: Management expects competitive intensity to remain high over the next six months to one year, particularly on public-sector contracts. On larger contracts above ₹700 cr, prequalifying conditions thin out the bidder pool.
Management: "Look, just to give you an idea, pipeline is very robust... we have been very conservative because the competitive intensity remains high. So there is a concerted push to try and push up our margins, which I had given the guidance during my last two con calls that we'll get into double digits, we touch about 12%. So that is what we are pushing on."
Working Capital & Balance Sheet
- Working capital days improved sharply: Working capital days fell from 87 days last quarter to 71 days, which management states is at par with 31st March 2022 levels.
- Further reduction expected: Management guided that there will be no increase in working capital and that there should be a reduction by year-end.
- Capex plans: About ₹33 cr of capex already done in FY23, with another ₹20 cr planned for the next two quarters. FY24 capex is expected in the range of ₹50–60 cr.
- Kota bus terminal monetization: Management expects approximately 80% of the entire area to be covered, i.e., leased out, by the middle of next year. Efforts are underway to lease out the entire property.
Bihar & Legal Overhangs
- Bihar payment issues persist: Cash flow problems continue on Bihar projects, especially medical and hospital projects, linked to a change in government composition. Active push from political leadership is expected to improve the situation in the last quarter.
- ₹900 cr claims and ₹1,800 cr counterclaims disclosed: The disclosure was newly added in FY21 and FY22 because auditors insisted, following new Government of India transparency guidelines. Management states the risk of these counterclaims materializing is highly unlikely.
- Emaar MGF arbitration stalled: The major claim and counterclaim relate to a 10-year-old arbitration for the Commonwealth Games Village project. The process was nearing culmination after seven years, but the 85-year-old presiding arbitrator resigned during COVID. The process is set to start again with a new presiding arbitrator.
- Details on other claims deferred: When asked for the nature, age, and provisioning against the legal claims and counterclaims beyond the Emaar MGF case, management deferred, stating investors could reach out to the IR department or CFO for those details.
Management: "No, it's as per the new guidelines that have been given by the government of India, we have to mention this because of transparency, but the risk of this materializing is highly unlikely."
Sector Strategy: Public vs Private
- Public-sector competitive intensity rising: More bidders are chasing public-sector contracts, especially in the ₹300–700 cr building segment. Beyond ₹700 cr, prequalifying conditions reduce the bidder pool.
- Private-sector discipline improving: Large private clients are making a conscious effort to go with proven contractors with proven track records, which management sees as a structural positive for margins.
- Residential avoided after past losses: The company will not do any private residential contracts in the rest of this financial year. Residential is not a priority because inflow targets have already been met and the company wants to tread cautiously after burning fingers with private developers.
- Long-term 50-50 split targeted: In the long term, the company would like a 50-50 breakup between public and private sector, and will look at residential again once discipline on the developer side increases.
- Private-sector exposure ramping up: The company will increase private-sector share of the total portfolio, focusing on education, institutional, and hospital projects, while staying away from residential for now.
Management: "So I'm not saying that we will never do residential even in the rest of this financial year, we will not do any private residential contracts. It's just that we burnt our finger."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | Maintain 15% growth guidance; order book healthy | FY23 |
| Order inflow | Surpass ₹3,000 cr guidance by ~₹1,000 cr; target another ₹1,000 cr in H2 | FY23 |
| EBITDA margin | Exit at ~12% run rate and maintain next year | FY23 exit / FY24 |
| Working capital | No increase; reduction expected by year-end | FY23 year-end |
| Bihar payments | Improvement expected from active political push | Last quarter FY23 |
| Capex | ~₹20 cr remaining in FY23; ₹50–60 cr in FY24 | FY23 / FY24 |
| Kota bus terminal | ~80% of area leased out | Middle of next year (CY24) |
| Residential contracts | No private residential contracts | Rest of FY23 |
| Earnings presentation | Upload before conference call | From next quarter |
Key Metrics
| Metric | Q2 FY23 |
|---|---|
| Revenue | ₹622.84 cr, vs ₹698 cr in Q2 FY22 |
| PAT | ₹39.17 cr, vs ₹35.78 cr in Q2 FY22 |
| EPS | ₹5.85, vs ₹5.34 in Q2 FY22 |
| EBITDA margin | 10.99%, vs 10.04% in Q2 FY22 |
| PAT margin | 6.29%, vs 5.13% in Q2 FY22 |
| H1 FY23 revenue | ₹1,232.09 cr, vs ₹1,278.11 cr in H1 FY22 |
| H1 FY23 PAT | ₹76.94 cr, vs ₹70.60 cr in H1 FY22 |
| H1 FY23 EBITDA margin | 11.06%, vs 10.67% in H1 FY22 |
| Net order book | ₹7,587.73 cr, to be executed in 24–30 months |
| Order inflow, FY23 to date | ₹3,182.77 cr |
| L1 projects, aggregate value | ₹1,098.35 cr across three projects |
| Order inflow guidance | ₹3,000 cr for FY23, may surpass by about ₹1,000 cr |
| Private sector share of portfolio | 20% |
| Working capital days | 71 days, down from 87 days in the prior quarter |
| Capex, FY23 to date | ₹33 cr, with another ₹20 cr expected in H2 FY23 |
| Capex guidance, FY24 | ₹50–60 cr |