Key Takeaways
- Strong headline growth, but Q3 will be soft: Revenue rose 44.75% YoY to ₹901.55 Crores, yet the NCR construction ban and Chhath-related labor exodus will make QoQ growth difficult in Q3.
- The NCR ban is a material, near-term drag: ~18% of the order book sits in NCR and has been at a standstill since before Diwali, directly threatening the run rate and keeping full-year guidance unchanged despite a strong first half.
- A deliberate shift toward private sector is underway: Private orders now form ~30% of the book, with a stated ambition to reach 40% in the short term, driven by a cautious, due-diligence-led approach after past losses.
- Margin expansion is back-half loaded: EBITDA margin was flat YoY at 9.96%, but management expects the March-ending quarter to drive the traditional second-half uplift as large design-heavy projects enter their billing phase.
- What to watch next quarter: The duration of the NCR ban, the pace of labor return post-Chhath, and whether CSTM billing actually begins in Q4 as promised.
The NCR Ban & Q3 Disruption
- 18% of order book frozen: Projects in the National Capital Region have been at a standstill since before Diwali due to an NGT-imposed ban on construction, and the timeline for lifting remains unknown.
- Labor exodus compounds the hit: Even if the ban is lifted soon, 80-90% of the skilled workforce has already returned to Bihar and Jharkhand for Chhath Pooja and will not be back until late November or early December, creating a 30-40 day disruption.
- Q3 growth will be YoY, not QoQ: Management explicitly corrected an analyst's assumption, stating Q3 revenue will be better than the same quarter last year, but growing over Q2 is difficult given the disruption.
- Recovery bet is on a quick restart: Management hopes the situation improves within a couple of weeks post-Diwali, allowing the company to "hit the ground running" on NCR projects.
Management: "We have to factor in the NCR and the NGT ban almost 18% of our order book is from NCR and those projects as you know have been at a standstill now since before Diwali and we do not know for how many more days the ban will be there on construction so that is going to affect the run rate a little bit"
Order Book & Bidding Strategy
- Order book composition is shifting by design: The mix has moved from predominantly public sector to a healthier 70:30 split, with a short-term target of 60:40, as the company selectively pursues private clients with proven track records after past losses.
- Bidding has turned cautious: The company has not won any significant order in the last couple of months and is "not bidding aggressively," choosing to bide its time as elections approach and tender activity begins to slow.
- A large L1 position is pending: The company is the lowest bidder for a ₹2,840 Crore project, but the client is looking to redesign a portion to reduce the budget, delaying the Letter of Award by at least 1.5-2 months.
- No more station orders this fiscal year: Management will not pursue additional station redevelopment projects in FY24, prioritizing significant progress on the two large current ones (CSTM and Chandigarh) first.
- Election cycle will cool order inflows: With elections likely to be announced in December/January, the number of tenders is already reducing, and management expects the rapid order book growth of recent quarters to pause over the next couple of quarters.
Management: "As far as private sector clients are concerned having burnt our fingers during the last few sessions. Residential and private sector project is something that we only do with a few developers with proven track records."
Project Execution & Billing Milestones
- Large projects are nearing billing inflection points: CSTM station redevelopment is expected to start billing in Q4 FY24 at a monthly run rate of ₹75-100 Crores, while Chandigarh station billing has already commenced.
- Jammu project is winding down: Most of the work will be completed by December end or January, at which point the company should be in a position to start handing over.
- Aerocity projects await ban lift to scale: Post the NGT ban being uplifted, the Bharti project is expected to cross ₹20 Crores per month and the retail development to exceed ₹15 Crores per month.
- Nepal project delayed but margin-insulated: The Police Academy project is running about two months behind schedule due to coordination issues between CPWD and the local client, but the contract structure links inflows to advances, insulating margins from the delay.
- Bihar Animal Husbandry project is unlocking: The slow-moving 400-acre campus modernization has now received 60% of the area for demolition of old heritage buildings, suggesting a potential pickup in execution.
Margins
- Margins are flat but poised for a second-half lift: Q2 EBITDA margin was 9.96%, nearly identical to 9.93% a year ago, while H1 margin improved to 10.36% from 9.94%, with management promising further improvement in the last two quarters.
- The margin story is a lifecycle story: Margins are lower in the first half of a project's lifecycle and rise in the second half; large jobs like CSTM, Chandigarh Railway Station, and Aerocity are still in their initial, lower-margin phases.
- Design completion is the margin unlock: With design work substantially complete on CSTM and progressing on other large jobs, the resulting increase in execution run rate is expected to drive margin expansion, particularly in the March-ending quarter.
- Employee costs are rising by design: The company continued recruiting and training through the downturn, viewing upskilling as integral, and has embarked on a digital transformation exercise to minimize inefficiencies through an in-house design cell using Autodesk and BIM.
Management: "The company has embarked on a digital transformation exercise which is being spearheaded by our director Mr. Vikas Ahluwalia and that is something which we feel now that the scale at which we have begun to operate that is something which is now mandatory."
Balance Sheet & Working Capital
- Working capital can swing with EPC contracts: In item rate contracts, billing is monthly for work executed, but in EPC contracts, payments follow milestones that may not reflect actual work done in the first half of a project, creating potential for temporary working capital buildup.
- Fund-based limits have been expanded: An additional ₹100 Crores has been sanctioned, taking the total limit to ₹2,040 Crores, with documentation for the new tranche still to be completed.
- Bihar receivables remain a sticky point: Most of the ₹175 Crores in receivables are tied to the Bihar Medical two hospitals project (Chapra and Nalanda), where state government payments have been slow.
- Other state payments are recovering: Bengal exposure is almost negligible with payments mostly recovered; a significant chunk of Haryana government dues was recovered in the last quarter; Himachal payments are coming through.
- West Bengal land monetization is a post-FY25 event: The company wants to monetize its land parcel in West Bengal, but this will not happen until after FY2025.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 20% or upward of 20% | FY2024 and FY2025 |
| Margin improvement | Margins and run rate will improve | Last two quarters of FY24 |
| CSTM billing start | Begin billing; ₹75-100 Crores monthly run rate | Q4 FY24 |
| CSTM monthly run rate | Cross ₹100 Crores per month | FY2025 |
| Chandigarh station billing | ~₹100 Crores | FY2024 |
| CSTM and Chandigarh capex | Remain within ₹120 Crores (₹54 Crores done in H1) | FY2024 |
| Order book mix target | 60:40 (public:private) | Short term |
| Station orders | Will not look at any more station orders | Rest of FY24 |
| Jammu project | Most of job completed, start handing over | December end / January |
| West Bengal land monetization | Monetize land parcel | Post FY2025 |
Key Metrics
| Metric | Q2 FY24 |
|---|---|
| Revenue | ₹901.55 cr, +44.75% YoY |
| PAT | ₹55.30 cr, +41.21% YoY |
| EBITDA margin | 9.96%, vs 9.93% in Q2 FY23 |
| PAT margin | 6.13%, vs 6.29% in Q2 FY23 |
| EPS | ₹8.26, vs ₹5.85 in Q2 FY23 |
| Revenue (H1 FY24) | ₹1,665.16 cr, vs ₹1,232.09 cr in H1 FY23 |
| PAT (H1 FY24) | ₹105.03 cr, vs ₹76.94 cr in H1 FY23 |
| EBITDA margin (H1 FY24) | 10.36%, vs 9.94% in H1 FY23 |
| FY24 revenue growth guidance | 20% or upward of 20%, maintained |
| Net order book | ₹12,622.20 cr, to be executed in 24 to 30 months |
| Order inflow FY24 to date | ₹5,259.50 cr |
| L1 project value | ₹2,840 cr, one project |
| Private sector share of order book | ~30%, targeting 40% in the short term |
| Gross debt | ₹32 cr |
| Unbilled revenue | ₹430 cr |
| Bihar receivables | ~₹175 cr |
| Capex (H1 FY24) | ~₹54 cr, full-year guidance ~₹120 cr |
| Fixed-price share of order book | 24% |