Uppal: "Shravan, I am sticking my neck out and saying that we will maintain what I had projected last time. And we have done that. For this quarter, we have crossed 10%, we are nearly at 11%, and we are nearly at 10% for H1. So, I think overall, it will be more than double-digit. Let me just say that for the entire year."

Order Book & Revenue Visibility

Uppal: "At the moment, actually, to sort of give you the correct picture on the private sector side, we are actually refusing work every month because we don't want the ratio to be skewed too much."

Project Execution & Key Assets


Labor & Capacity Constraints

Uppal: "Yes, labor is a continuous challenge. It is the biggest challenge that we are facing. In addition to the labor, there being a skills shortage, there is also an impact on account of events such as, or festivals such as Diwali, Chhath, and then elections now, which just got over in Bihar. En masse, a lot of skilled workforce has gone to Bihar, especially this year, because of the implementation of the FIR."

Capex & Balance Sheet


Strategy & Diversification

Uppal: "What I am trying to say is that we have negotiated the contract in such a fashion that our financial liabilities are considerably reduced, we have de-risked ourselves, so to speak."

Guidance & Commitments

CommitmentSpecificsTimeline
Revenue growth15% to 20% top-line growthFY26
Revenue growth15%+ growth, similar ~₹8,000 cr order inflowFY27 onwards
EBITDA marginMore than double-digit for the full yearFY26
Order inflow~₹8,000 cr new ordersFY26
Capex~₹400 cr (revised from ₹500 cr)FY26
Capex~₹300 cr (20% less than FY26)FY27
Dahlias project revenue₹100–125 crFY26
Dahlias project revenue₹300–350 crFY27
CSMT station revenue~₹400 cr (balance ~₹250 cr in H2)FY26
CSMT station revenue~40% of order valueFY27
Gems & jewelry project revenue30–35% of order valueFY27
Airport projects revenueCross 30% of order value at both Varanasi and DarbhangaFY26
Darbhanga Airport completionProject completionOctober 2026
Varanasi Airport completionStipulated completion (client pressing for March 2027)June/July 2027
Smaller-value legacy projectsCompletionFY27 to mid-FY28
Structural steel fabrication capacityDoubling capacityNext 2–3 months

Key Metrics

MetricQ2 FY26
Revenue₹1,177.30 cr, +16.39% YoY
PAT₹79.45 cr, +106.07% YoY
EBITDA margin9.85% in 1HFY26, vs 6.93% in 1HFY25
PAT margin5.88% in 1HFY26, vs 3.53% in 1HFY25
Net order book₹18,057.60 cr as on 30 Sep 2025
Order inflow (H1 FY26)₹4,374 cr
FY26 revenue growth guidance15% to 20%, maintained
FY26 EBITDA margin guidanceDouble-digit, maintained; Q2 crossed 10%, nearly 11%
FY26 new order inflow target~₹8,000 cr
L1 orders outstanding~₹1,620 cr (OUTR Bhubaneswar ~₹1,000 cr, RML Hospital Delhi ~₹570 cr)
Bid pipeline~₹6,500 cr
Working capital days87 days as on 30 Sep 2025, improved from 95 days as on 30 Jun 2025
Mobilization advances₹708 cr as on 30 Sep 2025, 33% interest-bearing
Retention money₹418 cr (including non-current) as on 30 Sep 2025
Unbilled revenue₹552 cr as on 30 Sep 2025
Cash and equivalents~₹1,000 cr, of which restricted cash ~₹419 cr and free cash ₹615 cr
FY26 CAPEX target~₹400 cr, revised from earlier guidance of ₹500 cr; H1 CAPEX ₹137 cr
FY27 CAPEX target~₹300 cr, about 20% less than FY26
Employee cost₹121 cr in Q2, vs ₹91 cr in Q1; includes arrears for increments effective 1 Jan
GST stuck (Maharashtra & Assam)~₹70 cr
CST station redevelopment FY26 revenue~₹400 cr for full year, ~₹250 cr balance in H2
Dahlias project FY26 revenue₹100 cr to ₹125 cr
Dahlias project FY27 revenue₹300 cr to ₹350 cr
Gems & jewelry project FY27 revenue30% to 35% of order value
Interest rate on mobilization advances7% to 8%