Key Takeaways
- Recovery underway, but GRAP hits Q3: Q2 rebounded sharply after a weak Q1, but a 1–1.5 month NCR construction ban will cut Q3 revenue by up to 10% QoQ to ~₹1,300 cr.
- Margin recovery is structural, not one-off: Escalation clauses are kicking in, and half of clients without labour escalation have now agreed to pay it. Management expects H2 margins to hold at Q2’s 7.6% level.
- FY28 margin target set at 8.5%–9%: Double-digit margins are explicitly ruled out for the next 2–3 years, with management calling that talk “foolhardy” given persistent headwinds.
- Order inflow guidance intact at ₹4,000 cr: Only ~₹1,000 cr secured so far, implying a heavily back-end-loaded H2. A ₹350 cr Bennett University win and a ₹200 cr DLF scope increase help, but the Jewellery Park order remains stuck.
- What to watch next quarter: Whether the GRAP ban lifts on schedule or extends, the pace of Q4 order inflow to hit the ₹4,000 cr target, and any client pushback on the PF increase compensation ask.
Revenue & Margin Recovery
- Q1 was the trough: Big projects started slowly for reasons beyond the company’s control, and NCR labour costs were revised sharply upward by governments. Both effects reversed in Q2 as projects gained momentum and escalation clauses activated.
- H1 still trails last year: H1FY27 revenue and profit pale versus H1FY26 solely because of the Q1 weakness, not because Q2 was soft.
- GRAP disruption is priced into guidance: A blanket construction ban in Delhi and a halt in the rest of NCR until at least 20th November will pull Q3 turnover down ~10% QoQ. Central Vista and a Gurgaon hospital are exempt and will contribute ~₹200 cr combined. Management expects the ban deadline to be extended.
- Q4 is the seasonal peak: Q4 is guided to be the best quarter, with Q3 and Q4 margins both holding at Q2’s 7.6% EBITDA level. Going forward, Q2 and Q4 are expected to be the strongest quarters in any calendar year if pollution-driven shutdowns persist.
- Material cost mix is a temporary distortion: Material costs rose 4–5 pp YoY as a share of revenue because large EPC projects like Central Vista and CSMT bill materials differently than item-rate contracts. As these projects near structural completion and full billing on executed items occurs, the material percentage should decline over the next 6–9 months.
Uppal: “I think the worst is behind us. Going forward, we expect to maintain similar margins in this financial year, wherein we are also factoring in the impact of NGT shutdown.”
Labour & Input Cost Management
- Staff costs jumped on two fronts: Absolute employee cost rose ~₹12.5 cr in Q2 from increments, and PF outlays rose ~₹3 cr after the EPF wage ceiling increased from ₹15,000 to ₹25,000, bringing ~85% of the workforce under PF ambit.
- PF increase is a 50 bps margin headwind: Management has reached out to all clients seeking compensation, framing it as a government policy change. Whether clients agree within the next two quarters is uncertain.
- Escalation recovery is improving structurally: Built-in escalation clauses began playing their part in Q2. Critically, ~50% of clients whose contracts lacked a labour escalation clause have now agreed to pay escalation as per the minimum wage index going forward. Talks continue with the rest.
- Bidding discipline has tightened: The company now refuses to bid without both labour and material escalation clauses in new contracts. Government contracts carry WPI-based escalation; private contracts have basic-rate provisions for volatile materials like cement, RMC and steel.
- Employee cost leverage is a scale story: Absolute employee cost will not decline, but as a percentage of turnover it will fall as revenue scales toward the ₹5,500 cr year-end target.
Order Book & Project Pipeline
- ₹4,000 cr inflow target is back-end loaded: Only ~₹1,000 cr has been secured year-to-date. A post-September ₹350 cr Bennett University order from existing client Times of India and a ₹200 cr scope increase at DLF City Center Downtown provide recent momentum.
- Jewellery Park remains in limbo: The company has still not received notice to proceed; the client is sorting internal permission issues. No turnover is expected in Q3, and even after the notice, actual work will take ~3 months to begin because the client must first clean up the land. Management says there is no risk of cancellation and the contract carries an escalation clause, so no margin impact is expected despite the significant delay.
- Central Vista is on track and insulated: The project is exempt from the GRAP ban and running at full speed. FY27 target of ₹700 cr is intact, with Q3 guided at ₹150 cr and Q4 at ₹200 cr+. Completion is expected in 18–20 months, ahead of the original ~2-year timeline. FY28 target stands at ₹1,000 cr.
- CSMT designs are now mostly approved: Progress has picked up, with Q3 billing guided at ~₹150 cr and Q4 at close to ₹200 cr.
- Varanasi project is being fast-tracked: The government wants it inaugurated before U.P. elections; the company expects to complete it by end-January or before February, ahead of the stipulated June 2027 completion date. Workforce is largely from Bihar, Bengal and Jharkhand, so U.P. election disruption is expected to be minimal.
- Geographic diversification is underway: Mumbai now represents 24% of the order book, with growing presence in the East (15%), Assam, and Bangalore (₹2,000 cr order book). The company is also bidding in Hyderabad but remains cautious in cash-strapped Bihar and Bengal.
Capex, Capacity & Cyclicality
- Capex plan was deliberately cut: The original plan of ₹300 cr+ was toned down to ~₹220-odd cr for FY27, driven by a conservative view on business cyclicality. FY28 capex is guided at a similar ₹220–250 cr.
- Management is building for an inflection point: Higher overheads and IDC relative to smaller peers are intentional: the company is building capacity to support a turnover close to ₹5,500 cr by year-end. Inefficiencies from this build-up are expected to reduce in the next financial year.
- Cyclicality fears are shaping conservatism: Management’s “gut” says the business is cyclical, citing the 2008–2010 downturn. Supply chain disruptions from Middle East instability are reinforcing this caution.
- Supply chain planning has been recalibrated: The company now factors in lead times of 5–6 weeks (up to 8 weeks for electromechanical materials), versus the earlier 2–3 weeks, based on experience from Middle East war disruptions.
- War chest, not buyback: Management is preserving cash to strengthen supply chain control, squeeze timelines, and improve margins, explicitly prioritising this over a buyback.
Uppal: “Our thinking is slightly counterintuitive on this. ... our gut is telling us this business is cyclical. We went through a downturn around late 2008, 2009 and 2010. Given the disruptions happening in the supply chain because of what is happening in the West or the Middle East, we are being slightly conservative.”
Margin Trajectory & the 10% Question
- FY28 margin target is 8.5%–9%: This is described as conservative. Reaching 10% EBITDA is “difficult to say right now.”
- Double-digit margins are a 2–3 year story: Management believes the entire ecosystem must improve its efficiency first. Standardisation is the key enabler, and government action on the skills shortage is expected to show results in the next year or two years.
- Bangalore residential is a margin tailwind: As execution picks up, these projects are expected to be margin-accretive.
- Depreciation is rising with capex: Q2 depreciation was ₹35 cr, up ~₹2.5 cr QoQ. FY27 full-year average is guided at around ₹35 cr, rising to ₹37–38 cr per quarter in FY28.
Uppal: “Over the last two years, one thing or the other has cropped up every quarter, which tends to have an impact. That is why I think it would be foolhardy to talk about double-digit margins.”
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY27 revenue growth | 15%+ | FY27 full year |
| FY28 revenue growth | 15%–20% | FY28 full year |
| FY28 EBITDA margin | 8.5%–9% | FY28 full year |
| Q3 FY27 revenue | ~₹1,300 cr (down up to 10% QoQ) | Q3 FY27 |
| Q3 & Q4 margins | At least Q2 levels (7.6% EBITDA), possibly better | H2 FY27 |
| Central Vista FY27 turnover | ₹700 cr | FY27 full year |
| Central Vista FY28 turnover | ₹1,000 cr | FY28 full year |
| Central Vista completion | 18–20 months from now | ~6 months ahead of ~2-year timeline |
| CSMT Q3 billing | ~₹150 cr | Q3 FY27 |
| CSMT Q4 billing | ~₹200 cr | Q4 FY27 |
| Order inflow | ₹4,000 cr | FY27 full year |
| FY27 capex | ~₹225 cr (revised down from ₹300 cr+) | FY27 full year |
| FY28 capex | ₹220–250 cr | FY28 full year |
| FY27 depreciation | ~₹35 cr per quarter average | FY27 full year |
| FY28 depreciation | ₹37–38 cr per quarter | FY28 full year |
| Material cost % normalisation | Decline as EPC projects reach full billing | Next 6–9 months |
| Varanasi project completion | End-January / before February (ahead of June 2027 deadline) | Before U.P. elections |
Key Metrics
| Metric | Q2 FY27 |
|---|---|
| Revenue | ₹1,463.67 cr, +30.01% QoQ and +24.32% YoY |
| EBITDA margin | 7.58%, up from 4.29% in Q1 FY27; down from 10.92% in Q2 FY26 |
| PAT | ₹55.86 cr, +389.2% QoQ; -29.33% YoY |
| PAT margin | 3.78%, up from 1.0% in Q1 FY27; down from 6.63% in Q2 FY26 |
| EPS | ₹8.34, compared to ₹1.70 in Q1 FY27 and ₹11.80 in Q2 FY26 |
| 1HFY27 revenue | ₹2,589.48 cr, compared to ₹2,182.18 cr in 1HFY26 |
| 1HFY27 EBITDA margin | 6.15%, compared to 9.85% in 1HFY26 |
| 1HFY27 PAT | ₹67.28 cr, compared to ₹130.16 cr in 1HFY26 |
| FY27 revenue growth guidance | 15%+, maintained from prior guidance |
| FY28 revenue growth guidance | 15%–20% |
| FY28 EBITDA margin guidance | 8.5%–9%, up at least 1 ppt from FY27 |
| Net order book | ₹19,627.92 cr, to be executed over 3 to 3.5 years |
| Order inflow FY27 (till Sep 30) | ₹558.07 cr; post-September order of ₹350 cr from Bennett University brings total to ~₹1,000 cr |
| FY27 order inflow guidance | ~₹4,000 cr, revised down to focus on selective bidding with escalation clauses |
| Q3 FY27 revenue guidance | ~₹1,300 cr, factoring ~10% QoQ dip from GRAP shutdown in NCR |
| Central Vista Q3 FY27 expected revenue | ~₹150 cr, exempt from GRAP ban; full-year target of ₹700 cr intact |
| CSMT Q3 FY27 expected billing | ~₹150 cr, with Q4 expected at ~₹200 cr; October billing was ₹80 cr |
| Employee cost Q2 FY27 | ₹133 cr, up ~₹12.5 cr in absolute terms due to increments and PF law changes |
| Material cost increase YoY | 4–5 percentage points higher, driven by project mix of EPC contracts like Central Vista and CSMT |
| Mobilization advance | ₹939 cr, of which 32% is interest-bearing |
| Retention money | ₹437 cr |
| Unbilled revenue | ₹925 cr |
| Capex 1HFY27 | ₹142 cr; full-year FY27 guidance reduced to ~₹225 cr from earlier ₹300 cr+ |
| NCR revenue share Q2 FY27 | ~₹520 cr out of ₹1,463.67 cr total (approx. 36%), up from ~₹350 cr in Q1 |
| Fixed-price contracts share | 9.19% of unexecuted order book; EPC contracts at ~46% |