Key Takeaways
- NGT bans crushed the quarter: Revenue fell 7.26% YoY and PAT dropped 30% as Delhi/NCR construction stoppages hit 33% of the order book, far worse than management had anticipated.
- FY25 growth guide cut, FY26 stays bold: Full-year revenue growth revised down to ~8.5%-9% from ~10%, but management guides 15%+ growth for FY26, betting on stalled projects restarting and new ones breaking ground.
- Margins are troughing, not breaking: EBITDA margin fell to 8.86% from 10.90% YoY, but grew 15% QoQ; management expects ~10% in Q4 and >10% in FY26 as idle labor costs unwind and slow-moving projects finish.
- The order book is now balanced at 50:50 public-private, a three-year strategic target achieved; a ₹25,000 crore bid pipeline across residential, healthcare and commercial segments supports the FY26 inflow target of ~₹7,800 crores.
- What to watch next quarter: Whether CSMT design issues actually resolve by March-end and billing begins in April, whether the Gem & Jewellery Park notice to proceed arrives, and whether Q4 margin hits the promised ~10% after a January still badly hit by NGT stoppages.
NGT Ban: The Quarter's Central Shock
- Timeline and severity: The ban began end-October around Diwali, continued in fits and starts till February's first week due to Supreme Court involvement. This year had far more stoppages and restarts than last year, making supply chain disruption much worse.
- Mechanics of the stoppage: When AQI crosses 300, construction machinery and truck supply chains come to a standstill; after revocation, a logjam at borders delays the pace of recovery. The impact cascaded through labor deployment, material movement and billing cycles.
- Labor cost blowout: Idle labor during the bans inflated staff expenses to nearly 9% of revenue, up from normal levels. Labor continues to be in structural short supply, a problem management says requires government intervention for upskilling and making the profession more attractive.
- DLF Arbour as counter-example: DLF compensated labor to stay on site during the ban, so work resumed immediately on February 3; the project already poured close to 4,000 cubic meters of concrete in February. This shows what is possible when clients absorb the holding cost.
- Next year's NGT risk: Management expects the October-January period next year to be handled better by all stakeholders, including the government, with BJP ruling both center and NCR states and concrete measures expected. The industry is making representations, but no policy change is guaranteed.
Uppal: "When the AQI say, crosses a certain level, one level of restrictions come in. It crosses, it jumps up further, another level, more stringent restrictions kicking. So, when it crosses 300, the entire construction machinery comes to a standstill. The supply chain comes to a standstill because the trucks cannot enter the NCR region."
Margin Mechanics: Compression Now, Recovery Promised
- The YoY damage: EBITDA margin fell to 8.86% in Q3 FY25 from 10.90% in Q3 FY24; the 9-month margin stands at 7.57% versus 10.56% last year. PAT declined 30.10% YoY.
- Sequential improvement underway: Despite the YoY decline, EBITDA margin grew 15% QoQ and net profit grew 28% QoQ. Management claims this trajectory is better than most peers, excluding L&T.
- Finance cost pressure: Finance cost as a percentage of sales rose, driven by interest-bearing mobilization advances on the CSMT project where work was slow and mobilization recoveries consequently lower. Company policy is to avoid interest-bearing advances where possible; two airport projects were funded from internal accruals without availing advances.
- Cost escalation protection: Government contracts, except one NBCC fixed-price contract nearing completion, carry escalation clauses based on WPI and labor/minimum wage indices. For private contracts, volatile materials like cement, steel and aggregates are pass-through; labor escalation is paid in roughly 50% of private contracts.
- Subcontracting cost volatility: The subcontracting line item fluctuates between 28% and 32% depending on the mix of outsourced works with material, like lift, escalator or AC installation, versus pure labor supply. Management says the figure must be read alongside labor supply and material costs, not in isolation.
- Slow-moving project unwind: Most slow-moving projects should be completed by end of Q4 FY25, removing a drag on margins as idle labor and overhead get absorbed by active sites.
Uppal: "You know me, we are always conservative. Yes. Otherwise you hold us. That is why I am confident that our margins will also go up and we will be having double-digit margins next year."
The Big Projects: CSMT and Gem & Jewellery Park
- CSMT: the complexity tax: The project is a live railway station hemmed by a newer nodal agency, unlike established PMCs such as NBCC or CPWD. Designs took five months due to the complexity of integrating a new building with 100-year-old infrastructure. The 15% completion figure reported by the railway includes off-site fabrication of 5,000-6,000 metric tons of structural steel, which is not yet billed.
- CSMT: the path to billing: Design issues should be resolved by end of Q4 FY25; from April FY26, steady turnover should begin with work on multiple buildings proceeding in parallel. Management expects work to be "in real earnest from April."
- Gem & Jewellery Park: fewer headaches expected: The notice to proceed is expected in the next 1-2 months, with actual ground work beginning towards the end of Q1 FY26 after the design phase. The project is less complex than CSMT since it involves large sites and offices, not a live station.
- Larger projects, thinner near-term margins: Projects above ₹1,000 crores are more complex, with shorter timelines and higher mechanization and staffing costs, making them more working-capital intensive. In the short term, margins are not higher; long-term margins should improve as entry barriers rise for smaller players.
Uppal: "Conventional logic says that the larger projects should come with better margins. But in the short term, the projects because they are becoming larger, they are also becoming more complex."
Order Book, Pipeline and Sector Mix
- 50:50 public-private balance achieved: The order book is now equally divided between public and private sectors, a strategic target management has been mentioning for three years. The plan is to maintain this equitable distribution going forward.
- FY26 order inflow target: Expected to be similar to FY25 at roughly ₹7,800 crores, supported by a total bid pipeline of about ₹25,000 crores across residential, healthcare and commercial segments.
- Private sector momentum intact: Management sees no slowdown in private sector activity. Government focus on infrastructure in Bihar, where elections are due end of this year, and continued activity in Assam are expected to support order inflow.
- Airport projects underway: Varanasi airport has clocked about ₹40 crores and Darbhanga airport about ₹20 crores in execution.
- Slow starters: The Signature Global Business Park has barely 10% of site handed over by the client; DXP and Signature Global projects have work fronts at only 5%-10% handed over. Composite steel structural works and DXP are expected to take off in the next financial year.
- MR installment received: The last installment of roughly ₹56 crores has been collected.
Digital Transformation and Structural Shifts
- SAP going live: The SAP implementation is going live in about a month, part of a digital transformation drive started 3-4 years ago. The company is becoming more data-driven and will use AI for operations.
- Labor shortage is structural, not cyclical: Management is explicit that labor scarcity is not a short-term problem and requires government intervention for upskilling and making the profession more attractive. This is a persistent cost and execution risk across the industry.
- Revenue recognition mechanics: Revenue is booked when the client passes a bill; there is no minimum threshold, and even 1% completion can be booked if the client approves. Work-in-progress and unbilled revenue are also included, so reported revenue lags physical progress when client approvals are slow.
- Mobilization advance discipline: Going forward, management is working to reduce finance costs from interest-bearing mobilization advances. The advance level is expected to remain in a similar range next year.
Uppal: "It is not a problem that is going to go away in the short term. This is something which the government will have to look at."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY25 full-year revenue growth | ~8.5%-9% (revised down from ~10%) | FY25 |
| Q4 FY25 EBITDA margin | ~10% (double-digit) | Q4 FY25 |
| FY26 revenue growth | 15%+ | FY26 |
| FY26 EBITDA margin | Exceed 10% (double-digit) | FY26 |
| FY26 order inflow | Similar to FY25 (~₹7,800 crores) | FY26 |
| CSMT design resolution and billing start | Design issues resolved; steady turnover from April | End Q4 FY25 / April FY26 |
| Gem & Jewellery Park ground break | Notice to proceed in 1-2 months; ground work end of Q1 FY26 | Q1 FY26 |
| Slow-moving project completion | Most completed by end of Q4 FY25 | Q4 FY25 |
| Order book mix | Maintain 50:50 public-private | Ongoing |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Revenue | ₹951.95 cr, -7.26% YoY |
| 9M FY25 revenue | ₹2,882.79 cr, +7.1% YoY |
| PAT | ₹49.39 cr, -30.10% YoY |
| 9M FY25 PAT | ₹118.35 cr, vs ₹175.69 cr in 9M FY24 |
| EPS | ₹7.37, vs ₹10.55 in Q3 FY24 |
| EBITDA margin | 8.86%, vs 10.90% in Q3 FY24 |
| 9M FY25 EBITDA margin | 7.57%, vs 10.56% in 9M FY24 |
| PAT margin | 5.11%, vs 6.82% in Q3 FY24 |
| FY25 revenue growth guidance | 8.5%-9% (full year) |
| FY26 revenue growth guidance | 15% plus |
| FY26 EBITDA margin guidance | double-digit, should exceed 10% |
| Net order book | ₹16,258.44 cr, to be executed in next 3 years |
| Order inflow FY25 (YTD) | ₹7,794.37 cr |
| FY26 order inflow expectation | similar to FY25, around ₹7,800 cr |
| Order book from NCR region | 33% |
| Fixed price contracts in order book | 13%; variable price 87% |
| Cash and bank balance | ₹735 cr (cash ₹246 cr, bank ₹489 cr) |
| Gross debt | ₹11 cr (long-term, including term loan) |
| Trade receivables | ₹882 cr |
| Unbilled revenue | ₹572 cr |
| Mobilization advance | ₹621 cr, 43% interest-bearing |
| Retention money | ₹351 cr |
| Inventory | ₹324 cr, including ₹36 cr real estate inventory |
| 9M FY25 CAPEX | ₹154 cr |
| Full year FY25 CAPEX expectation | ₹175 cr (Q4) |
| FY26 CAPEX expectation | ~₹125 cr |
| CSMT project FY25 revenue expectation | ₹80-₹100 cr (Q4), earlier target of ~₹300 cr not met |
| CSMT project FY26 revenue expectation | ~₹750 cr |
| Gem & Jewellery Park FY26 revenue expectation | ~₹500 cr |
| Total bid pipeline | ~₹25,000 cr |
| Projects bid, awaiting decision | ~₹5,500 cr |
| Additional bids expected by March | at least ₹3,000 cr |