Key Takeaways
- Guidance cut, but FY27 rebound promised: FY26 revenue growth was trimmed to 10%-15% from 15%-20% after NGT/GRAP pollution bans shut Delhi NCR sites, where 44% of the order book sits. Management expects to recover the lost 3-4 percentage points in FY27, guiding 15%-20% growth.
- Order book is full, execution is the bottleneck: Order inflow crossed ₹9,500 crores against a ₹8,000 crore projection, and the company is L1 in another ₹2,485 crores of work. The constraint is not demand but the ability to build, with labor scarcity now a "full-blown issue."
- Margins held the line, just: PAT margin stayed nearly flat YoY (6.85% vs 6.90%) despite pollution shutdowns, steel inflation and rising labor rates, because material and subcontract costs are largely passed through. Management calls 10% EBITDA doable in Q4.
- The NGT/GRAP pollution ban is now a structural Q3 risk: Management concedes it has become an annual event and is working with clients and governments on mitigation, but the short-term profitability hit from idle overheads is real.
- What to watch next quarter: Whether the four L1 projects convert to letters of award, the pace of CSMT and DLF Dahlias execution after design resets, and any sign that labor availability is improving.
The NGT/GRAP Disruption
- What happened: Pollution-related construction bans in Delhi NCR hit project execution in December and January, directly compressing Q3 revenue. The impact was amplified because NCR now accounts for more than 40% of the order book, up from prior years.
- Profitability side-effect: While sites were idle, overhead costs tied to large recently-won orders kept running, so the ban hit both the top line and short-term margins.
- Now a recurring risk: Management acknowledged GRAP has "pretty much become a part of the annual calendar, especially the third quarter," and is working with clients, governments and the broader ecosystem to mitigate future impact. The hope is that disruptions lessen as awareness grows and on-site pollution-reduction measures take hold.
- FY27 assumption: The 15%-20% FY27 growth guide bakes in recovery of the 3-4 percentage points lost in FY26, implying management expects a cleaner winter next year or has built compensating execution capacity.
Shobhit Uppal: "It's not only impacted the top line. It's also impacted our profitability because while we bagged a lot of large orders and to execute those large orders, our overhead costs had also gone up. So in the short term, our profitability has been hit. But the silver lining is that now going forward, not only are we well stocked on our order book, but we are also well equipped every which way to ramp up our execution speed."
Order Book & Pipeline
- Inflow overshot the target: FY26 order inflow reached ~₹9,500 crores against a ₹8,000 crore projection, driven by large government and institutional wins.
- L1 pipeline: The company is the lowest bidder on four projects worth ₹2,485 crores (including GST): RML Hospital, Odisha University, Assam Judicial Complex, and Kota Airport. Conversion to letters of award is uncertain, especially on state-government projects where timelines can stretch.
- FY27 inflow to step down deliberately: Management guided ₹5,000-₹6,000 crores of order inflow for FY27, down from FY26, as the focus shifts from bagging work to executing the swollen backlog and improving margins.
- Mix target: The private/government order book split is targeted at roughly 50:50 going forward, though it could swing 55:45 or 60:40 either way.
| Project | Status & Timeline |
|---|---|
| Gem & Jewellery Park (EPC) | Engineering underway; work on ground starts Q1 FY27; ~3.5-year completion; 20%-25% of project value targeted in FY27 |
| CSMT station redevelopment | Design reset complete after original tender design proved unworkable; work now moving fast; ₹300-350 crores targeted in FY26, ~₹700 crores in FY27 |
| DLF Dahlias (residential) | FY26 revenue target cut to ~40% of original (>₹100 crores) after earthquake-code redesign by client; FY27 estimate held at ₹300-350 crores |
| Central Vista | Fast-moving, insulated from GRAP; designing started, awaiting authority clearance; at least 30% of ₹2,600 crores to be billed in FY27 |
| Chandigarh station redevelopment | Panchkula and Chandigarh stations completed; platform work underway; targeting May completion (Q1 FY27) |
| Bihar Animal Husbandry | Run rate slowed as old-building vacation lagged; CM announced completion date; confident of FY27 finish |
Project-Level Execution Risks
- CSMT delays and cost recovery: The entire design had to be redone because the tender's conceptual design was not tenable on the ground, causing a "huge delay." Costs have been impacted; management hopes to recover some through extra work or claims. A hindrance register jointly signed with the client documents delays not attributable to the contractor, but quantification typically happens only at project-end.
- CSMT future uncertainty: Greenfield buildings face no further delay, but platform and concourse work depends on railway shutdowns being granted, which is hard to predict. Based on Chandigarh experience, some delays are possible and have been budgeted to an extent.
- DLF Dahlias redesign: New earthquake codes forced DLF to redo structural design at its own cost. Designs are now coming in and work picks up post-Holi, but the FY26 revenue contribution was materially reset.
- Residential exposure being dialed back: Management has slowed bidding for further residential projects, pivoting toward institutional projects, airports, hotels and commercial work. RERA is cited as a positive: it ring-fences project cash flows and pressures developers to deliver on time.
Shobhit Uppal: "What happens in all government contracts is that there is a hindrance register, which is maintained and which is jointly signed off, which helps establish the delays, which are not attributable to the contractor. Generally, these are finally quantified towards the end or the last stage of the project."
Labor & Input Costs
- Labor scarcity is structural: Management called it a "full-blown issue," not a lurking one, but noted a silver lining: clients and governments now widely recognize the problem, which may drive systemic solutions.
- Unit rates climbing fast: Labor unit rates are increasing every 3-4 months, at a pace "far more than what the governments are recognizing." The company now extrapolates 1-2 years of past data to inflate its bids accordingly.
- Steel and cement pass-through: Base-price escalation clauses cover cement and steel in contracts. The indirect exposure is through other material and equipment (tower cranes, mixers, transit mixers, scaffolding, aluminium shuttering) where steel-price inflation leaks through.
- Subcontract cost optics: A ~30% YoY rise in subcontract and other expenses drew a question. Management responded that when material, construction expenses and subcontract are taken together, PAT margin is nearly flat YoY (6.90% vs 6.85%), implying the mix shift is cost-neutral at the net level.
- Labour Code provision: ₹1.31 crores was factored in over nine months for the new Labour Code, covering outsourced labor as well.
Shobhit Uppal: "When we bid for a job, we see -- we are seeing that the unit rates are on the increase every 3 months or 4 months, and they are far more than what the governments are recognizing. So we are putting -- we are sort of accounting for this increase based on the past data, past 1 year or past 2 years. We are extrapolating that data and using it to sort of hike our bids also."
Margins & Profitability
- PAT margin held nearly flat: At 6.85% vs 6.90% YoY, despite the GRAP shutdown, steel inflation and rising labor rates. The pass-through structure of contracts and the mix of material-plus-subcontract costs explain the resilience.
- Q4 margin target: 10% EBITDA is "doable," per management.
- FY27 margin ambition: A "possibility towards 10.5%," though this is framed as aspirational rather than a firm commitment.
- Overhead drag from growth: Bagging large orders raised overhead costs in anticipation of execution; when GRAP shut sites, those costs went unmatched by revenue, compressing short-term profitability. The offset is that the company is now fully resourced to ramp execution speed when conditions allow.
- Capex to ease: FY27 capex is expected to be similar to or less than FY26 (~₹300 crores), because by March-end the company will have already catered to capex for current projects.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY26 revenue growth | 10%-15% (revised from 15%-20%) | FY26 full year |
| FY26 EBITDA margin | Double-digit | FY26 full year |
| Q4 FY26 revenue | ~₹1,400 crores | Q4 FY26 |
| Q4 FY26 EBITDA margin | 10% doable | Q4 FY26 |
| FY27 revenue growth | 15%-20% (conservative estimate) | FY27 full year |
| FY27 order inflow | ₹5,000-₹6,000 crores | FY27 full year |
| FY27 capex | Similar to or less than ~₹300 crores | FY27 full year |
| CSMT execution | ₹300-350 crores in FY26; ~₹700 crores in FY27 | FY26 and FY27 |
| DLF Dahlias execution | ~₹300-350 crores | FY27 |
| Central Vista billing | At least 30% of ₹2,600 crores | FY27 |
| Gem & Jewellery Park start | Work on ground begins; 20%-25% of project value billed | Q1 FY27; FY27 full year |
| Chandigarh station completion | May | Q1 FY27 |
| Bihar Animal Husbandry completion | Project completion | FY27 |
| Himachal university completion | Hoping to complete | Q1 FY27 |
Key Metrics
| Metric | Q3 FY26 |
|---|---|
| Revenue | ₹1,060.72 cr, +11.43% YoY |
| PAT | ₹54.02 cr, +9.38% YoY |
| EPS | ₹8.06, vs ₹7.37 in Q3 FY25 |
| EBITDA margin | 9.05%, up from 8.86% in Q3 FY25 |
| PAT margin | 5.02%, down from 5.11% in Q3 FY25 |
| 9M FY26 revenue | ₹3,242.90 cr, vs ₹2,882.79 cr in 9M FY25 |
| 9M FY26 PAT | ₹184.18 cr, vs ₹118.35 cr in 9M FY25 |
| 9M FY26 EBITDA margin | 9.59%, vs 7.57% in 9M FY25 |
| FY26 revenue growth guidance | 10% to 15%, revised from 15% to 20% due to NGT-related disruptions in Delhi-NCR |
| FY27 revenue growth guidance | 15% to 20%, conservative estimate; potential to recoup lost growth |
| Net order book | ₹18,679.50 cr, to be executed over 2.5 to 3 years |
| Order inflow, FY26 YTD | ₹9,562 cr (including GST of ₹603 cr) |
| L1 projects | ₹2,485 cr across 4 projects (including GST) |
| FY27 order inflow guidance | ₹5,000–₹6,000 cr, including L1 conversion; focus shifting from residential to institutional |
| Gross borrowings | ₹22 cr |
| Cash and bank balance | ₹840 cr (cash ₹253 cr, bank ₹587 cr) |
| Capex, 9M FY26 | ₹193 cr; full-year FY26 target ~₹300 cr |
| Labour Code impact, 9M FY26 | ₹1.31 cr |
| Bid pipeline | ~₹7,000 cr |