Ahluwalia Contracts (India) Ltd Q3 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/k3td1v6za800jxtm1lf6vi2w.pdf

Key Takeaways


The NGT/GRAP Disruption

Shobhit Uppal: "It's not only impacted the top line. It's also impacted our profitability because while we bagged a lot of large orders and to execute those large orders, our overhead costs had also gone up. So in the short term, our profitability has been hit. But the silver lining is that now going forward, not only are we well stocked on our order book, but we are also well equipped every which way to ramp up our execution speed."

Order Book & Pipeline

ProjectStatus & Timeline
Gem & Jewellery Park (EPC)Engineering underway; work on ground starts Q1 FY27; ~3.5-year completion; 20%-25% of project value targeted in FY27
CSMT station redevelopmentDesign reset complete after original tender design proved unworkable; work now moving fast; ₹300-350 crores targeted in FY26, ~₹700 crores in FY27
DLF Dahlias (residential)FY26 revenue target cut to ~40% of original (>₹100 crores) after earthquake-code redesign by client; FY27 estimate held at ₹300-350 crores
Central VistaFast-moving, insulated from GRAP; designing started, awaiting authority clearance; at least 30% of ₹2,600 crores to be billed in FY27
Chandigarh station redevelopmentPanchkula and Chandigarh stations completed; platform work underway; targeting May completion (Q1 FY27)
Bihar Animal HusbandryRun rate slowed as old-building vacation lagged; CM announced completion date; confident of FY27 finish

Project-Level Execution Risks

Shobhit Uppal: "What happens in all government contracts is that there is a hindrance register, which is maintained and which is jointly signed off, which helps establish the delays, which are not attributable to the contractor. Generally, these are finally quantified towards the end or the last stage of the project."

Labor & Input Costs

Shobhit Uppal: "When we bid for a job, we see -- we are seeing that the unit rates are on the increase every 3 months or 4 months, and they are far more than what the governments are recognizing. So we are putting -- we are sort of accounting for this increase based on the past data, past 1 year or past 2 years. We are extrapolating that data and using it to sort of hike our bids also."

Margins & Profitability


Guidance & Commitments

CommitmentSpecificsTimeline
FY26 revenue growth10%-15% (revised from 15%-20%)FY26 full year
FY26 EBITDA marginDouble-digitFY26 full year
Q4 FY26 revenue~₹1,400 croresQ4 FY26
Q4 FY26 EBITDA margin10% doableQ4 FY26
FY27 revenue growth15%-20% (conservative estimate)FY27 full year
FY27 order inflow₹5,000-₹6,000 croresFY27 full year
FY27 capexSimilar to or less than ~₹300 croresFY27 full year
CSMT execution₹300-350 crores in FY26; ~₹700 crores in FY27FY26 and FY27
DLF Dahlias execution~₹300-350 croresFY27
Central Vista billingAt least 30% of ₹2,600 croresFY27
Gem & Jewellery Park startWork on ground begins; 20%-25% of project value billedQ1 FY27; FY27 full year
Chandigarh station completionMayQ1 FY27
Bihar Animal Husbandry completionProject completionFY27
Himachal university completionHoping to completeQ1 FY27

Key Metrics

MetricQ3 FY26
Revenue₹1,060.72 cr, +11.43% YoY
PAT₹54.02 cr, +9.38% YoY
EPS₹8.06, vs ₹7.37 in Q3 FY25
EBITDA margin9.05%, up from 8.86% in Q3 FY25
PAT margin5.02%, down from 5.11% in Q3 FY25
9M FY26 revenue₹3,242.90 cr, vs ₹2,882.79 cr in 9M FY25
9M FY26 PAT₹184.18 cr, vs ₹118.35 cr in 9M FY25
9M FY26 EBITDA margin9.59%, vs 7.57% in 9M FY25
FY26 revenue growth guidance10% to 15%, revised from 15% to 20% due to NGT-related disruptions in Delhi-NCR
FY27 revenue growth guidance15% to 20%, conservative estimate; potential to recoup lost growth
Net order book₹18,679.50 cr, to be executed over 2.5 to 3 years
Order inflow, FY26 YTD₹9,562 cr (including GST of ₹603 cr)
L1 projects₹2,485 cr across 4 projects (including GST)
FY27 order inflow guidance₹5,000–₹6,000 cr, including L1 conversion; focus shifting from residential to institutional
Gross borrowings₹22 cr
Cash and bank balance₹840 cr (cash ₹253 cr, bank ₹587 cr)
Capex, 9M FY26₹193 cr; full-year FY26 target ~₹300 cr
Labour Code impact, 9M FY26₹1.31 cr
Bid pipeline~₹7,000 cr