Key Takeaways
- Double-digit margins return in Q4: EBITDA margin recovered to 10.17% from 8.96% YoY as slow-moving and NGT-hit projects cleared, though FY25 full-year margin still fell to 8.34%.
- FY26 guided for 15% revenue growth: Management targets ~15% top-line growth on a ~₹15,500 crore order book, with double-digit margins sustained, while cautioning that labour shortages could cap upside.
- Order inflow steady, not accelerating: FY26 inflow target of ₹7,000–8,000 crores matches FY25’s ₹8,400 crores; the company is L1 in another ~₹1,800 crores and sees a healthy bid pipeline, especially in private residential high-rises.
- CSMT is the swing factor: India’s largest running railway station redevelopment is finally moving on the greenfield portion, targeting ₹400–500 crores revenue in FY26, but design-approval delays on the brownfield side keep the full timeline at 2–2.5 years.
- What to watch next quarter: Whether CSMT billing actually hits the ₹15–20 crores/month run-rate, the pace of private-sector order conversion from the L1 pipeline, and any labour disruption from Bihar elections in October.
Margin Recovery: Q4 Bounce, FY25 Drag, FY26 Promise
- Q4 lift driven by project mix: Slow-moving legacy projects and NGT-related stoppages are now largely behind the company, letting fresh orders signed at decent margins flow through to the P&L.
- Full-year decline reflects H1 pain: FY25 EBITDA margin fell to 8.34% from 10.08% in FY24 because the first half carried the weight of those stalled projects; the Q4 exit rate is what management asks investors to extrapolate.
- Staff-cost leverage kicking in: Staff costs as a percentage of revenue fell in Q4 as revenue rose, and management expects this ratio to keep declining as the ₹15,500 crore backlog converts, directly pushing up profits.
- Employee inflation a headwind: Employee expenses rose ~15% last year and management expects that to accelerate by another couple of percentage points given a shortage of skilled engineers and managers, though it insists cost increases are being passed on to clients.
- Supply-chain strategy to protect margins: The company plans to deploy its cash reserves to better control procurement pricing and delivery timelines, a lever it believes will support the double-digit margin commitment.
- 12–13% margins not coming back soon: Management was explicit that pre-COVID margin levels are structurally out of reach until the industry adopts greater standardization and industrial techniques on-site.
Uppal: "I do not think we are going to reach 12%, 13% margins till such time that there is greater standardization and greater dependence or greater use of industrial techniques in what we do on our project side."
CSMT: The Megaproject Moving in Phases
- Greenfield portion now moving: Approvals for the greenfield side are in place and billing of ₹15–20 crores per month is expected to begin immediately, supporting the ₹400–500 crores FY26 revenue target for the project.
- Brownfield side still gated by design: The station remains one of India’s busiest and permissions come one platform at a time; finishing-item design issues with the nodal agency RLDA persist even though structural issues are largely resolved.
- Full completion pushed to FY28: Management now guides two to two and a half years to complete the entire project, a timeline that reflects the phased-permission reality rather than a single delay event.
- Margin slightly below company average: The job was bid with a margin assumption a touch lower than the company’s double-digit target, so as CSMT scales it will mix down the blended margin modestly.
- Delay compensation uncertain: On whether additional costs from design-driven delays will be recovered, management said it is too early to say and noted such claims are typically resolved only at the project’s tail end.
Ahluwalia: "It's a very complicated project, given the nature of it that it's one of the largest running railway stations of the country and the footfall is immense here. So, frankly speaking, my friend, it would be wrong to expect that it is going to get some huge monthly turnovers because it has taken us a while also to understand this that the permissions will come in phases."
Order Book & Inflow: Quality Over Quantity
- FY25 inflow of ₹8,400 crores: The company booked healthy orders through the year, and management says it is being aggressively wooed by clients, particularly in the private sector where few contractors meet quality and safety standards.
- FY26 target flat at ₹7,000–8,000 crores: The guidance implies no acceleration in new wins, though ₹2,000–2,100 crores is already in hand and another ~₹5,000 crores is expected over the balance of the year.
- L1 pipeline adds ~₹1,800 crores: The company is lowest bidder on a ~₹1,000 crore university project in Bhubaneshwar and a ~₹700 crore MIDC project in Mumbai, both awaiting final award.
- Private-sector mix staying at 60:40: Management intends to keep the private-government split at roughly 60:40 in the near term, favouring private clients where competitive intensity is lower and margin profiles are better.
- Bid pipeline broadening beyond metros: Substantial growth is visible in residential high-rises in Tier-2 cities like Bhubaneshwar and Patna, plus airports, government housing, and educational projects.
- Gems and Jewellery Park still waiting: The project awaits departmental clearances to break ground; management’s best guess is a Q3 FY26 start, with ~₹150 crores of revenue possible in the year.
- Scope increases adding to backlog: The medical college at Chapra saw extra government-approved works lift the order size from ~₹450–470 crores to ₹600-plus crores, a reminder that in-situ scope creep is a material top-up to reported inflows.
Uppal: "There is a paucity of good construction companies, especially on the private sector side where the focus on quality and safety is very, very high... there are only a handful of contractors who are equipped to do that."
Balance Sheet & Working Capital
- Mobilization advances shifting to interest-free: Total mobilization advances grew 21% YoY, but the composition improved markedly: the interest-bearing portion fell from 58% to 40% as private-sector clients provided interest-free advances, while the interest-bearing share is expected to decline further.
- Finance cost rose on CSMT advance: Finance cost increased from ₹48 crores to ₹58 crores YoY, driven largely by the ~₹200 crore mobilization advance taken in February–March for the CSMT project; management expects interest cost to grow slower than the 15% revenue growth as the interest-bearing advance share keeps falling.
- Trade receivables write-off contained: ~₹12–14 crores was written off from two clients (Logix and JP) taken to NCLT, with legal remedies being pursued; an additional ₹2 crores was provided on an ECL basis.
- Working capital days stable: Management expects net working capital to remain at similar levels of around 88 days.
- Other income boosted by FD interest: Other income rose substantially in FY25, with ~₹45 crores from interest on fixed deposits and ~₹8 crores written back from supplier outstandings.
- Capex stepping up for high-rise kit: FY26 capex is guided at ~₹200 crores, up materially, to fund specialized shuttering and cranes required by the growing pipeline of high-rise building orders.
Growth Levers & Constraints
- 15% growth is the base case, 30% is the ceiling: Management projects 15% revenue growth for FY26 but says that in an ideal scenario with no government inertia, no labour shortage, and no macroeconomic shocks, the company could deliver nearly 30%.
- Labour is the binding constraint: The company is explicitly cautious on growth because of labour availability, flagging the risk of skilled workforce from Bihar returning home for state elections in October, which could disrupt site productivity.
- Order booking is not the bottleneck: Management stated flatly that winning orders is not an issue and that clients are aggressively pursuing the company; the constraint is execution capacity, not demand.
- Conservative growth philosophy intact: The company reiterated its commitment to remain zero-debt and grow conservatively, a stance that caps the pace of balance-sheet expansion even when the opportunity set is large.
- FY27 ambition conditional on stability: Management said it could eye ~₹6,000 crores of revenue in FY27 if there is no slowdown, no labour shortage, no cash shortage, and no international event impacting the economy, a string of conditions that makes the number aspirational rather than guided.
Uppal: "We want to grow conservatively, and that's what we have been doing all these years. We want to continue to remain a zero-debt company."
Project Portfolio: What Is Moving, What Is Stuck
| Project | Status | Revenue Run-Rate / Timeline |
|---|---|---|
| CSMT (greenfield) | Approvals in place; billing started | ₹15–20 cr/month; ₹400–500 cr in FY26 |
| CSMT (brownfield) | Design approvals phased; structural done | Completion in 2–2.5 years (FY28) |
| Medical College Chapra | Extra works added; scope now ₹600+ cr | Completion in ~6 months |
| Edition 66 (~₹600 cr) | ₹70–80 cr billed so far; moving fine | Substantial portion still left |
| DLF Commercial (0.65 cr sq ft) | Construction started after redesign | Just begun |
| Signature Global | Site handed over | ₹15–20 cr/month since last month |
| Gems & Jewellery Park | Awaiting clearances | Likely Q3 FY26 start; ~₹150 cr in FY26 |
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | ~15% growth | FY26 |
| Order inflow | ₹7,000–8,000 crores | FY26 |
| EBITDA margin | Double-digit margins sustained | FY26 |
| CSMT revenue contribution | ₹400–500 crores | FY26 |
| CSMT project completion | Full completion | 2–2.5 years from now (FY28) |
| Medical College Chapra completion | Project finished | Within 6 months |
| Capex | ~₹200 crores (high-rise equipment) | FY26 |
| Working capital days | ~88 days | FY26 |
| Interest-bearing mobilization advance | Decline further from 40% | FY26 |
| Private:Government mix | Maintain ~60:40 | Near term |
| Zero-debt status | Remain zero-debt | Ongoing |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Revenue | ₹1,215.84 cr, +4.48% YoY |
| EBITDA margin | 10.17%, up from 8.96% in Q4 FY24 |
| PAT margin | 6.74%, up from 4.67% (excl. exceptional items) in Q4 FY24 |
| PAT | ₹83.16 cr, +51.44% YoY (excl. exceptional items) |
| EPS | ₹12.41, vs ₹8.20 (excl. exceptional items) in Q4 FY24 |
| FY25 full-year revenue | ₹4,098.62 cr, +6.3% YoY |
| FY25 full-year EBITDA margin | 8.34%, vs 10.08% in FY24 |
| FY25 full-year PAT | ₹201.51 cr, vs ₹230.61 cr (excl. exceptional items) in FY24 |
| FY26 revenue growth guidance | ~15% |
| FY26 EBITDA margin guidance | Double-digit |
| Net order book | ₹15,775.08 cr, to be executed over 2–2.5 years |
| Order inflow in FY25 | ₹8,436.69 cr |
| FY26 order inflow target | ₹7,000–8,000 cr |
| L1 projects (not yet awarded) | ₹1,796 cr across two projects |
| Working capital cycle | 88 days |
| Mobilization advance | ₹639 cr, 40% interest-bearing |
| Capex for FY26 | ~₹200 cr |
| Private sector share of order book | 58% |
| Fixed-price contracts share of order book | 11% |
| Trade receivables write-off | ₹12 cr, related to Logix and JP clients taken to NCLT |