Key Takeaways
- Volume-led beat, cost engine firing: Revenue rose 11% YoY on strong micro-market execution, while kiln fuel cost dropped 14% and logistics cost fell 2%, together delivering a sharp QoQ EBITDA per ton improvement.
- The INR 1,500 EBITDA/ton target now has a visible path: Management committed to a INR 3,650/ton cost by FY28, backed by a detailed blueprint spanning green power, logistics, raw material and fuel mix levers, with INR 100+ per ton savings expected in FY26 alone.
- Sanghi is the clinker-cost jewel, but it is late: Both kilns are finally running after refractory and infrastructure fixes, and April showed significant improvement. Management calls it the future hub of clinker, but the ramp-up is months behind the original plan.
- Capacity engine is on schedule, integration is the FY26 priority: The company crossed 10 crore tons, targets 11.8 crore tons by FY26 and 14 crore tons by FY28, all organically funded. FY26 focus shifts to integrating Penna, Sanghi and Orient rather than chasing new deals.
- What to watch next quarter: Whether Sanghi’s April improvement sustains into a full-quarter run-rate, the pace of the INR 500/ton cost gap closure toward INR 3,650, and any demand-led price traction in the subdued eastern and northern markets.
Cost Reduction: The INR 3,650/ton Blueprint
- Kiln fuel cost: Down 14% YoY to INR 1.58 per 1,000 kCal from INR 1.84, driven by better fuel management, fuel mix and source mix optimization, plus a push to maximize captive coal consumption. 40% of the kiln heat mix now comes from domestic coal.
- Green power ramp: Share of green power in the power mix jumped to 26% from 15.6%, a nearly 10-percentage-point improvement. The full 1,000 MW renewable energy project is expected to commission by Q2 FY26, with 300 MW already achieved.
- Logistics savings: Transportation cost declined 2% to INR 1,238 per ton. Primary lead reduced by 15 km to 265 km, secondary lead by 2 km to 46 km, and direct dispatch increased by 600 bps to 58%. 11 GPWI rakes are running, and 8 of 26 BCFC rakes were delivered in FY25.
- Raw material and fly ash: An 8–10% raw material cost optimization is expected from secured competitive sourcing and efficiency capex. A 10-year agreement with Adani Power secures 0.5 crore tons of fly ash supply at nearly negative INR 400 per ton.
- The gap to close: Current cost per ton is roughly INR 4,250 against the INR 3,650 target, leaving about INR 500 to bridge. Management expects greater than INR 100 per ton savings in FY26 and another INR 150 in FY27, and says the whole team is working to beat the committed timeline.
Bahety: "I'm going to also work -- the whole team is committed here to work to achieve it before what we have committed. So that is like the spirit what we are working on."
Sanghi & Penna: The Jewel and the Work-in-Progress
- Sanghi ramp-up delay: The plant is a few months behind target because it is an island plant that required power and dredging investments. It was not well maintained, with refractory lining issues. Both kilns are now up and running, and significant improvement was visible in April.
- Sanghi’s strategic promise: Management calls Sanghi the "jewel" and the "hub of clinker," citing 100 crore tons of limestone reserves and the expectation that it will deliver the best clinker cost in the portfolio once fully ramped.
- Penna performance: Clinker utilization is a healthy 75–80%, but cement capacity utilization is lower because south Indian markets have been sluggish. Management is very happy with the asset quality.
- Integration confidence: FY26 is the year of organic growth and integration. Management points to the successful Ambuja-ACC integration as proof it can handle large combinations, and argues that smaller acquisitions like Penna, Sanghi and Orient will be easier. Employees are motivated by being part of a 10 crore ton platform.
Bahety: "Sanghi for me is one of the best assets in terms of the cost. It will be my jewel, I tell you, in terms of the overall clinker cost. It will be my hub of clinker."
Capacity Expansion: On Track to 14 Crore Tons
- Milestone achieved: Ambuja crossed 10 crore tons of capacity, growing nearly 50% in 30 months, and became the ninth-largest cement company globally.
- FY26 commissioning pipeline: Q1: Bhatapara clinker unit (87% progress) and Sankrail grinding unit (88% progress). Q2: Salai Banwa grinding unit in Uttar Pradesh. Q3: Kalamboli expansion, Bhatinda, Marwar, Dahej, and the Jodhpur integrated unit with a 3 MTPA clinker line. Q4/FY26-end: Maratha 4 MTPA clinker line and Warisaliganj grinding unit in Bihar, enabling 11.8 crore tons by FY26.
- FY28 path: Nine additional grinding unit projects are identified, with land acquisitions and statutory approvals underway, to reach 14 crore tons by FY28. The entire capex program adheres to that target.
- Funding: FY26 capex is roughly INR 9,000 crores (INR 6,000 crores growth, INR 2,500–3,000 crores efficiency), met entirely from existing cash, working capital recovery and monthly operating cash flows.
- Old asset rationalization: Proactive impairment taken on three old ACC clinker units (Bargarh, Chaibasa, Wadi line 1) totaling roughly 0.25 crore tons. These were opportunistic, coal-price-dependent assets; new 10,000–12,000 TPD clinkering units will have a higher cost arbitrage. The assets can still be operated if coal prices fall heavily.
Bahety: "Others have taken decades, but we have achieved this in 30 months."
Market & Pricing: Demand Outpacing Supply
- Q4 demand: Cement consumption grew roughly 6.5–7% in Q4, with cumulative FY25 industry growth between 4% and 5%. Ambuja delivered better than industry results.
- FY26 outlook: Management expects 8% overall demand growth for FY26, supported by improved construction activity, rural demand, housing and increased government spending.
- Pricing momentum by region: Good momentum over the last four months, backed by buoyant demand and government capex. The south has seen good improvement off a low base. Central-to-western markets are healthy. Eastern and northern markets are a little subdued. The country-level weighted average shows healthy traction.
- Industry structure to 2030: Management sees supply growing at a 6% CAGR against demand at 7–7.5% CAGR, with demand outpacing supply. Industry capacity is expected to reach 95 crore tons, with utilization inching from 65% to 67–68%, supporting positive price upticks.
Bahety: "To me, industry supply will be at, say, 6% CAGR while demand will be at 7% to 7.5% CAGR. And therefore, I am at least bullish in terms of demand outpacing supplies."
Premiumisation & Operating Model
- Premium product push: Share of premium cement in trade sales rose to 29.1%, up 5.3 percentage points, from an average of 25–26%. The FY26 target is around 35%, driven by deeper ground engagement and customer demand.
- Blended cement: Blended cement now stands at 82% of the mix, supporting both cost and sustainability goals.
- Operating model reset: A shared services setup (GCC) has been implemented, moving HR, IT, procurement and finance functions under clear service level agreements. A new leadership team is in place, including a new CFO, Chief Digital Officer and Head of Manufacturing.
- Digital and talent: Over 1,000 campus graduates were hired from prestigious institutions via touchless hiring. The company plans to drive Industry 4.0 predictive analytics, automation, AI and ML to enhance efficiency and improve overall EBITDA.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| EBITDA per ton target | Achieve INR 1,500 EBITDA per ton | FY28 |
| Cost per ton target | Achieve INR 3,650 per ton cost | FY28, with intent to beat the timeline |
| Cost savings | Greater than INR 100/ton savings in FY26, another INR 150/ton in FY27 | FY26 and FY27 |
| Capacity target | 11.8 crore tons (118 MTPA) | FY26 |
| Capacity target | 14 crore tons (140 MTPA) | FY28 |
| Renewable energy | Full 1,000 MW commissioned | Q2 FY26 (by June 2026) |
| WHRS target | Achieve 30% WHRS including all new projects | At 14 crore ton capacity |
| Lead distance target | Reduce lead distance by roughly 100 km to 170 km | Not dated |
| Premium cement mix | Reach around 35% premium cement in trade sales | FY26 |
| Industry demand growth | 8% overall cement demand growth | FY26 |
| Sanghi ramp-up | Significant improvement; become clinker-cost hub | FY26 (this year) |
| Orient Cement open offer | INR ~2,000 crores deposited in SEBI escrow; awaiting clearance | Undated, pending SEBI |
| Northeast strategy | Evaluate setting up a unit in due course | Undated |
Key Metrics
| Metric | Q4 FY25 |
|---|---|
| Revenue | ₹9,889 cr, up 11% YoY |
| Operating cost per ton | ₹4,104, driven by better fuel management and green power |
| EBITDA | ₹1,868 cr, margin of almost 19% |
| EBITDA per ton | ₹1,001 |
| Kiln fuel cost | ₹1.58 per 1,000 kcal, reduced 14% from ₹1.84 |
| Transportation cost per ton | ₹1,238, declined 2% |
| Premium products share of trade sales | 29.1%, up 5.3 ppt |
| Blended cement share | 82% |
| Green power share in power mix | 26%, up from 15.6% |
| Primary lead distance | 265 km, reduced by 15 km |
| Secondary lead distance | 46 km, reduced by 2 km |
| Direct dispatch to customers | 58%, up 600 bps |
| Consol cash and cash equivalents | ₹10,125 cr as on 31 Mar '25 |
| Net worth | ~₹64,000 cr, up from ~₹50,000 cr a year ago |
| Total capacity | >10 crore tons, crossed in Q4 |
| FY26 capacity target | 11.8 crore tons |
| FY28 capacity target | 14 crore tons |
| FY28 EBITDA per ton target | ₹1,500 |
| FY28 cost per ton target | ₹3,650 |
| Cost reduction achieved so far | ₹150–175 per ton from Sep '22 baseline |
| Industry demand growth expectation for FY26 | ~8% |
| Industry demand growth in Q4 FY25 | 6.5% to 7% |
| Industry cumulative growth for FY25 | 4% to 5% |
| Penna and Sanghi combined volume | ~0.16 crore tons for the quarter |
| Sanghi capacity utilization | 40% to 45% in FY25 |
| Penna clinker utilization | 75% to 80% in FY25 |
| Penna cement utilization | 45% to 50% in FY25 |
| Orient Cement utilization | 60% to 75% in FY25 |
| Renewable energy capacity commissioned | 300 MW out of 1,000 MW target |
| WHRS capacity | ~218 MW |
| New limestone reserves secured in Q4 | 36.7 crore tons, total reserves >900 crore metric tons |
| ACC impairment provision for old clinker units | ~₹200 cr (Bargarh, Chaibasa, Wadi Line 1) |
| Organic capex expectation for FY26 | ~₹9,000 cr (growth ~₹6,000 cr, efficiency ₹2,500–3,000 cr) |
| Post-Orient cash position | ~₹5,000 cr |
| Orient acquisition outflow | ~₹5,500–5,600 cr for 46% stake |
| Open offer amount deposited in SEBI escrow | ~₹2,000 cr |
| Premium cement extra realization | ₹200–300 per ton |
| FY26 premium cement share target | ~35% |
| Power cost reduction from green power | ₹0.20–0.25 per unit vs last quarter |
| Logistics cost reduction | 2%, from ₹1,258 to ₹1,238 per ton |
| GPWI rakes delivered and running | 11 |
| BCFC rakes ordered | 26, of which 8 delivered in FY25 |
| Campus graduates hired | >1,000 |