Anawil Wire and Engineering Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- IPO proceeds - ₹115 crore for repayment/pre-payment of borrowings in FY 2026-27
Delivered - The DRHP committed ₹11,500.00 lakhs (₹115 crore) of issue objects to repayment/pre-payment of borrowings in F.Y. 2026-27, against an estimated ₹117 crore planned. By 30 September 2026 the full ₹115 crore was utilised - ₹113 crore against car loan and term loan, ₹2 crore against working capital borrowings.
- New order for 10 steel wind turbine towers (₹58.32 Cr incl. GST) - completed by Q1 FY28
On track - The 29 October 2026 announcement disclosed a one-time domestic order for 10 steel wind turbine towers (140-metre hub height, \~474 tonnes) worth ₹58,32,42,345 inclusive of GST, expected to be completed by Q1 FY 27-28. It is included in the confirmed order book of ₹395.6 Cr as of 31 October 2026.
- Largest-ever order (₹133.98 Cr, 38 towers) - completed by Q4 FY27
On track - The 10 September 2026 announcement disclosed the largest-ever order of ₹133.98 Cr ex-GST (₹140.68 Cr incl. GST) for 38 EN-156/3.3 MW towers for an FDRE wind project in Andhra Pradesh, to be completed by Q4 2026-27. It is included in the confirmed order book of ₹395.6 Cr as of 31 October 2026.
- No further capex or new plant - focus on 100% utilization of both facilities
On track - At the Q2 FY27 call, management said they do not plan any further capex or a new plant, focusing on 100% utilization of both facilities funded internally. Capital work-in-progress rose to ₹3,069.27 lakh as at 30 September 2026 from ₹584.80 lakh at 31 March 2026; no new plant announced.
- Internal manufacturing (tower internals) - add \~₹20 lakh per tower to margin
On track - At the Q2 FY27 call, management stated internal manufacturing would add \~₹20 lakh per tower to margin, building on the Koppal internals plant presented in the Q1 FY27 PPT. Trial production has started at the Karnataka plant, with own internals to be used from December-February.
- FY28 tower production - at least 500 towers (200+ Kutch, 300+ Karnataka)
On track - At the Q2 FY27 call, management set FY28 targets of at least 200 towers from Kutch and 300+ from Karnataka, with EBITDA rising from \~₹100 crore to ₹175-180 crore next year. Combined installed capacity is 612 towers - 420 at Koppal, 192 at Kutch; Karnataka is fully booked and Kutch is to be fully running in FY28.
- FY27 financial guidance - revenue ₹450-500 Cr, PAT ₹55-60 Cr
On track - The Q2 FY27 PPT guided FY27 revenue of ₹450-500 Cr and PAT of ₹55-60 Cr, reiterated in the 6 November 2026 announcement with confidence in stronger H2 execution. H1 FY27 revenue was ₹153.97 Cr (up 272.2% YoY) and PAT ₹14.39 Cr, surpassing full-year FY26 revenue of ₹143.27 Cr.
- H2 FY27 EBITDA per tower - minimum ₹35 lakh
Pending - At the Q2 FY27 call, management guided EBITDA per tower at a minimum of ₹35 lakh in H2 FY27 versus ₹32.8 lakh in H1. H1 FY27 EBITDA per tower was ₹32.82 lakh. The horizon has not been reached and no H2 actuals are yet available.
- H2 FY27 tower production - 300+ towers
On track - At the Q2 FY27 call, management targeted 300+ towers in H2 FY27, confirmed "100%" to the IR's summary. H1 FY27 production was 107 towers; Karnataka tracks toward \~200 in H2 with \~70+ from Kutch, and October dispatches were \~20 towers with \~35 expected over the next five months.
- Confirmed order book ₹395 crore - executable by Q1 FY28
On track - At the Q2 FY27 call, management confirmed an order book of ₹395 crore (320 towers) as of 13 October 2026, executable by Q1 FY28. As of 31 October 2026 the confirmed order book stood at ₹395.6 Cr covering 320 towers and 8 customers, excluding LOIs of ₹44.05 Cr.