Antelopus Selan Energy Ltd Guidance Report - SOIC x StockScans Report
as of Oct 2026
- 100% participating interest in Elao transferred with operatorship, approved December 2023
Delivered - The FY24 annual report stated that after farming into Elao in July 2022, the regulator in December 2023 approved transfer of 100% participating interest with operatorship to Selan, taking the portfolio to four fields - Bakrol, Lohar, Karjisan and Elao. An announcement of 20th December 2023 confirmed the Ministry of Petroleum & Natural Gas approved the 100% PI transfer from PFH Oil and Gas for contract area CB/ONDSF/ELAO/2016.
- Karjisan FY24 average sales \~160 boepd
Delivered - The FY24 annual report guided Karjisan FY24 average sales of \~160 boepd, with five new wells drilled per the approved FDP and three put on production, field production crossing 300 barrels of oil and 20,000 m³ of gas per day at \~159 boepd average. The Q4 FY24 PPT reported Karjisan FY24 average sales of c.159 boepd, a c.238% y-o-y increase.
- Lohar FY24 average sales \~84.50 boepd with one new well
Delivered - The FY24 annual report stated Lohar FY24 average sales of \~84.50 boepd, a \~10% y-o-y decrease, and that the one new well drilled "did not perform in line with our expectations". The Q4 FY24 PPT reported Lohar FY24 average sales of c.84 boepd, c.10% y-o-y down.
- Bakrol FY24 - 6 new wells drilled, production doubled
Delivered - The FY24 annual report stated Bakrol FY24 average sales of \~498 boepd, a \~35% y-o-y increase, with drill, hydro-frac and commencement of production from 6 new wells, and a stimulation campaign that doubled production from the field. The Q4 FY24 PPT reported 13 new wells drilled and on production in phase 1, including Bakrol BK#30-35.
- FY24 drilling campaign completed as scheduled and within budgets
Delivered - The FY24 annual report stated the FY24 drilling campaign across Bakrol, Lohar and Karjisan was completed as scheduled and within budgets. All 10 wells drilled in the year proved hydrocarbon bearing and 8 were put on production during FY24.
- FY24 sales \~740 boepd, a \~45% y-o-y increase
Delivered - The FY24 annual report reported FY24 sales averaging \~740 boepd (\~742 boepd per the segment note), up \~45% from \~510 boepd in FY23, with Q4 FY24 volumes of \~981 boepd. The Q2 FY27 PPT restates FY24A average sales of 740 boepd.
- FY23 revenue ₹122 crores, 53% y-o-y growth
Delivered - The FY23 annual report stated FY23 revenue of ₹122 crores (53% growth), PAT of ₹31 crores (3x), EBITDA of ₹63 crores (80%), cash profits of ₹58 cr (2x), Bakrol sales of 1,34,868 boe and net 2P reserves of 0.2 crore barrels. The Q2 FY27 PPT restates FY23A EBITDA of INR 63.0 Cr at a 48% margin.
- Duarmara well cost \~INR 70 crores
Delivered - At the Q2 FY27 call, management stated a Duarmara well costs \~INR 70 crores, targeting the Tipam 1, 2 and 3 zones at \~3.5 km depth versus 1.5-1.6 km in Cambay. CWIP stands at \~INR 190 crores, of which \~INR 100 crores is Duarmara to be capitalized once the field is on production.
- FY27 EBITDA >2X growth vs FY26A EBITDA of INR 167.5 Cr
On track - The Q2 FY27 PPT guided FY27E EBITDA at ">2X Growth" against FY26A EBITDA of INR 167.5 Cr at a 58% margin. H1 FY27 EBITDA was \~INR 180 crores, with Q1 at INR 93.2 Cr and Q2 at INR 90.0 Cr - full-year >2X would require more than INR 335 Cr.
- Karjisan fourth well in Fault Block 2 to appraise and develop potential
Delivered - The Q2 FY26 PPT planned a fourth Karjisan well in Fault Block 2 to further appraise and develop its potential, alongside substantial production growth expected that year. Four new wells were drilled and Karjisan average sales rose c.48% to 684 boepd, with Feb and Mar'26 monthly sales above 1,000 boepd, the third well having significantly de-risked Fault Block 2.
- Cambay immediate gas monetization via MDPE pipelines; 20 km evacuation pipeline medium-term
Delivered - The Q2 FY26 PPT planned immediate Cambay gas monetization via MDPE pipelines and minimal processing for early sales, with a medium-term 20 km evacuation pipeline tied into the state gas grid. In Q1 FY27 additional gas was monetized by laying new MDPE pipelines in the Western/Central areas; Cambay gross sales were 130 boepd in Q1 FY27 and 57 boepd (50% PI) in Q2 FY27.
- Duarmara commercial sales from Q4 FY26
Partial - The Q2 FY26 PPT scheduled Duarmara commercial sales to commence from Q4 FY26, with short-term evacuation via AGCL pipeline and MDPE pipeline and long-term via the Oil India Limited network. A 2-zone hydrocarbon column was confirmed with light oil flow up to 37° API at TS-1, and by the Q2 FY27 call oil was obtained twice from TS1 with focus shifting to oil monetization, but commercial sales had not commenced.
- KG Onland adds volumes from next year (FY28)
Pending - The Q2 FY27 PPT stated KG Onland adds volumes from next year, FY28. The KG Onland portfolio expands from 2 fields to 9 with DSF-IV adding 7 new fields, RSCs signed on 22nd October 2026 and FDPs and environmental work under way, but no production yet as of 29th October 2026.
- Karjisan wells pay back within 1 year
Pending - The Q2 FY27 PPT stated Karjisan wells pay back within 1 year. Two of 7 wells are already drilled with new barrels from end November, and each Karjisan barrel adds two times a Bakrol barrel to the P&L, but no payback outcome is yet available as production is just starting.
- Bakrol regulatory approval for up to 55 more wells, drilling until 2030
On track - The Q2 FY27 PPT stated Bakrol has regulatory approval for up to 55 more wells, with drilling to continue without a break until 2030. All 10 wells of the current campaign are drilled and fracked, post-frac production flowing since mid-Q2 at 950+ boepd, with no further drilling beyond the campaign reported as of 29th October 2026.
- 2 onshore licenses won in DSF Bid Round IV (Cambay & KG basin)
Delivered - The Q1 FY27 PPT reported 2 onshore licenses won in DSF Bid Round IV, awaiting formal award. Revenue sharing contracts with the Government of India were signed on 22nd October 2026 for KG onshore (East) and Cambay Basin (West), with DSF-IV adding 7 new KG fields and FDPs under way.
- Cess refund of c. ₹6.56 Cr recognized upon receipt of final order
Delivered - The Q1 FY27 PPT stated a c. ₹6.56 Cr refund of excess Cess paid FY21-FY23, allowed by Commissioner (Appeals), would be recognized upon receipt of the final order. The c. ₹6.5 Cr refund was received and recognized as other income in Q2 FY27, realized in cash as a one-off flagged the prior quarter.
- FY26 focus - monetize 2P In-Place Resources increased >2x in Bakrol & Karjisan
Delivered - An announcement of 9th May 2025 set FY26 focus on monetizing the 2P In-Place Resources increased >2x in Bakrol and Karjisan. FY26 average sales were 1,355 boepd versus 1,193 boepd in FY25, with 4 new Karjisan wells and Bakrol's 10-well campaign bringing 2 wells online from end Feb'26 and a third in mid April'26.
- Cambay FIFO amendment - staggered drilling of 3 wells within $10m Carry
Delivered - At the Q4 FY25 PPT, management stated the Cambay FIFO amendment was executed allowing Selan to stagger drilling of 3 wells within the $10m Carry, versus originally envisaged continuous drilling. The FY25 annual report confirmed the farm-in amendment to the FIFO Agreement was executed allowing staggered drilling of three wells under the $10 million carry commitment.
- D-12 field - drill one well in the current weather window
Pending - At the Q4 FY25 PPT, management planned to drill one well at D-12 in the current weather window, subject to statutory approvals, with tendering ongoing for drilling rig, services and tangibles. No further mention of D-12 drilling appears in later filings or transcripts in our record.
- Inter-connecting pipelines to monetize gas and move towards zero flaring
Delivered - At the Q4 FY24 PPT management planned inter-connecting pipelines to monetize gas and move towards zero flaring, following the Q3 FY24 PPT's interconnecting MDPE gas pipeline between Bakrol well pads. The MDPE gas pipeline was completed by Q2 FY25, piping gas from legacy wells to commercial sale, the Bakrol network connecting most wells to the gas grid per the FY25 annual report, and new MDPE pipelines monetized more gas at Cambay in Q1 FY27.
- Revised Karjisan FDP submitted to DGH, envisaging 7 additional wells
Delivered - The FY26 annual report stated a revised Field Development Plan for Karjisan had been submitted to DGH and was under consideration, and the Q4 FY26 PPT said the new FDP envisages 7 additional wells with drilling from end FY27. By Q2 FY27 the FDP was in final stages of approval with 2 of 7 wells already drilled, ahead of the end FY27 plan.
- Revised Bakrol Field Development Plan to be submitted in FY 2024-25
Delivered - The FY24 annual report stated the company would submit a revised Field Development Plan for Bakrol in FY 2024-25, incorporating all newly acquired data. The FY26 annual report records Bakrol Proved & Developed oil addition of 0.104 MMBBL based on the approved Revised Field Development Plan.
- PSC extension beyond 2030 for Bakrol and Lohar
Delivered - At the Q4 FY24 PPT management stated the PSC extension application beyond 2030 was submitted for Bakrol and Lohar, with an announcement of 9th May 2025 noting the application for Bakrol and Karjisan. The Q4 FY25 PPT listed extension of the Bakrol and Lohar PSCs till 2030 among completed milestones.
- Elao field stimulation activities to bring the field online
Pending - The FY25 annual report planned Elao field stimulation activities to bring the field online following its FY2023-24 acquisition, and the Q4 FY25 PPT said efforts were ongoing to initiate production through well stimulation. No outcome on Elao production or stimulation results is disclosed in later filings or transcripts in our record as of 29th October 2026.
- FY25 sales maintained at Q4 FY24 levels of \~981 boepd
Delivered - The FY24 annual report stated "our endeavor for FY' 25 shall be to maintain the sales at these levels" - the Q4 FY24 volume of \~981 boepd - and the Q2 FY25 PPT reiterated that volume guidance was unchanged. FY25 average sales came in at c.1,193 boepd, a c.61% y-o-y increase, with Q2 FY25 at \~1,250 boepd, exceeding the target.
- Phase 2 drilling campaign at Bakrol and Karjisan starting by end Q1 FY26
Delivered - At the Q4 FY25 PPT, management stated the Phase 2 drilling campaign at Bakrol and Karjisan would start by end Q1 FY26 on approved Appraisal and Development plans, augmenting production volumes from Q3 FY26 onwards. The Bakrol 10-well campaign launched in FY26 with first two wells completed, and Karjisan's 4 new wells lifted average sales c.48% to 684 boepd.
- Cambay well drilling completed by end-November 2025
Delivered - At the Q2 FY26 PPT, management expected Cambay well drilling to be completed by end-November 2025, following the Q4 FY25 plan of one new well in Q2 FY26 to understand recovery and production potential. One well was drilled under the approved three-well FDP, shut-in wells were revived via workovers on the western flank, and Mar'26 gross sales exceeded 200 boepd.
- Merger with Antelopus Energy Private Limited - completion and listing of fresh shares
Delivered - At the Q4 FY24 PPT, management laid out the remaining merger steps from exchange and SEBI approvals through NCLT sanction to issue and listing of fresh Selan shares, later expecting completion by July 2025 with NCLT Chandigarh reserving the order on 8th May 2025. The merger was successfully completed in FY 2025-26, the company renamed Antelopus Selan Energy Limited with interests in nine contract areas across five basins.
- Investor calls as a regular occurrence at end of quarterly Board meetings
On track - At the Q2 FY27 call, management promised investor calls as a regular occurrence at the end of quarterly Board meetings, hopefully the same day, plus responses to investor email queries within a week. The Q2 FY27 call itself was held in Sep 2026; no subsequent quarterly call has occurred as of 29th October 2026, the next falling due after the Q3 FY27 Board meeting.
- Duarmara full plan formulated over the next five to six months
Pending - At the Q2 FY27 call, management stated the Duarmara full plan would be formulated "over the next five to six months" and shared with investors, with good estimates "next fiscal". No Duarmara full plan has been shared as of 29th October 2026; focus is on oil monetization since gas faces evacuation constraints, with TS1 entered and recirculated twice yielding oil both times.
- KG onshore resource estimate to be published after third-party reserves estimation
Pending - At the Q2 FY27 call, management said they will publish a resource estimate of KG onshore after third-party reserves estimation - "the first thing that you will see us coming up at some point". No resource estimate has been published as of 29th October 2026; KG onshore potentially holds more resource than the offshore portfolio, with 7 new discoveries among around 9 new KG fields.
- FY27 capex \~INR 250 crores
Pending - At the Q2 FY27 call, management expected capex of \~INR 250 crores this year versus INR 220 crores last year. No FY27 capex actuals are disclosed as of 29th October 2026; capex history is INR 51 crores (FY23), INR 160 crores, INR 87 crores and INR 220 crores, with FY26 development capex funded entirely through internal cash accruals.
- FY27 EBITDA margin "substantially better" than \~58%, around 70%
On track - At the Q2 FY27 call, management expected FY27 EBITDA margins "substantially better" than last year's \~58%, "around 70% mark", with the CFO soft-committing to endeavor to hold margins above 65%. Q1 FY27 margin was c.70% on EBITDA of INR 93.2 Cr, and Q2 FY27 EBITDA of INR 90 crores was \~71% margin (\~69% excluding the one-off INR 6.5 crores refund).
- Dangeru ramp-up - de-bottleneck evacuation, frac existing wells, new well early FY28
On track - At the Q4 FY26 PPT, management planned a Dangeru ramp-up from the existing well, de-bottlenecking evacuation short-term with ONGC and connecting to a common carrier pipeline linked to the GAIL network medium-term, fracing existing wells, and drilling a new well targeted early FY28. Dangeru commenced production in August 2025 with FY26 average sales of 36 boepd, Q1 FY27 at 49 boepd and Q2 FY27 at 46 boepd; no read yet on fracs or the new well.
- Cambay one to two wells in FY27
On track - At the Q2 FY27 call, management planned one to two optionality wells at Cambay this fiscal, "probably March or late Feb, early March", in 50% JV with Synergia, with success potentially making Cambay "as big as Bakrol, if not larger"; the Q1 FY27 update had planned one new well in H2 FY27 targeting the deeper Eocene reservoir. No drilling of the planned well(s) has yet occurred as of 29th October 2026, with Q2 FY27 Cambay sales of 57 boepd (50% PI) from existing wells.
- Bakrol 10-well campaign - remaining wells on production by H1 FY27
Delivered - At the Q4 FY26 PPT, management guided that the remaining 8 of 10 Bakrol wells would complete drilling in H1 CY2026, with remaining new wells on production by H1 FY27. All 10 wells are drilled and fracked with post-frac production flowing since mid-Q2 at 950+ boepd October average, Q2 FY27 sales of 750 boepd versus 701 boepd in Q1, after frac delays from supply chain constraints were sorted.
- Karjisan seven-well drilling campaign completed in FY27
On track - At the Q2 FY27 call, management planned \~7 wells at Karjisan and expected to finish the campaign "in this fiscal year itself", built into the 2,500 exit, with the Q2 FY27 PPT stating all 7 wells drilling by April 2027 against an original end FY27 start. As of the Q2 FY27 call the rig was drilling, 2 of 7 wells were done and described as "very interesting on the log", with drilling "ahead of plan".
- 5,000 BOEPD onshore portfolio by FY29
On track - At the Q2 FY27 call, management "committed" 5,000 BOEPD by FY29 via a trajectory of \~2,500 barrels in FY27 and \~3,500 in FY28, excluding offshore and with "very minimal" contribution from new KG fields and Duarmara; the Q2 FY27 PPT restates FY24A 982, FY25A 1,180, FY26A 1,758, FY27E 2,500, FY28E 3,500, FY29E 5,000 boepd. October 2026 production was \~2,000 boepd, with full capital guidance for the 3,500-5,000 ramp-up to come as FDPs are filed with regulators.
- FY27 exit production \~2,500 BOEPD
On track - Management first stated the 2,500 boepd FY27 exit target at the Q4 FY26 PPT as "Road to 2,500 boepd in FY'27, entirely self-funded; begins FY'27 with a base of 1800+ boepd", reiterated it as intact in Q1 FY27 and "on track" in the Q2 FY27 PPT, calling it "reasonably sure" at the Q2 FY27 call. October 2026 production was \~2,000 boepd (\~1,950 per the CFO) against H1 FY27 average sales of \~1,700 BOEPD, with the 2,500 exit built into the Karjisan seven-well campaign.