Key Takeaways
- Volume hit by de-stocking, not demand destruction: Sales volume fell short by ~60,000 tons as steel prices collapsed 13% in Q1 and a further 10% in July, forcing channels to run on minimum inventory. Management calls this temporary and expects recovery when prices stabilize.
- EBITDA held the line in a brutal quarter: Despite a ₹20/kg raw material price drop on 2 lakh tons of inventory, EBITDA fell only ₹400–500 per ton, staying within the guided ₹4,500/ton lower band. Management calls it the "best quarter" given that historically such drops had wiped out EBITDA entirely.
- Raipur plant is the growth engine, now near launch: 70–75% of capex done, first-of-its-kind products (color-coated tubes, heavy structural tubes up to 500 sq mm) are being market-tested, and the plant is expected operational from Q3 FY23. Target EBITDA of ₹6,000–8,000/ton vs the existing ₹4,500–5,000/ton.
- Steel price correction is framed as a structural win: Falling HRC prices narrow the gap vs low-grade secondary tubes and vs conventional materials like TMT bars, which management argues will accelerate market share gains and make this a "golden era" once prices bottom.
- What to watch next quarter: Whether the ~60,000 tons of lost volume actually returns as de-stocking ends, the pace of Raipur plant commissioning, and whether Tricoat EBITDA normalizes back to the ₹7,000–8,000/ton long-term average from the Q1 spike of ₹9,200/ton.
Volume & the De-Stocking Shock
- The mechanism: Steel prices fell 13% in Q1 and another 10% in July, so distributors and channel partners slashed inventory from 25–30 days to 15–20 days, knowing they could buy cheaper later. The phenomenon normally lasts 4–8 weeks.
- The damage: Almost 60,000 tons of sales volume was lost in Q1, with Q1 sales at 4.2 lakh tons against capacity of 6 lakh tons. Some goods were sold on discount and some exported to manage volumes.
- Recovery signal already visible: Tamil Nādu sales, which had collapsed from a 1.5 lakh ton annual run-rate to 84,000 tons annualized in Q1, reached 12,000 tons in July with 4–5 days still left in the month, nearly back to the prior run-rate.
- Demand is deferred, not dead: Management argues projects may be delayed by 1–2 months but must eventually be completed because steel has no alternative in industrial sheds, housing towers, and commercial buildings. July sales are on track despite maintained higher prices.
Anubhav Gupta: "I may delay my project by one, two months but then eventually, I have to finish that project. So, demand will always come back, always."
Margin Resilience in a Falling Steel Market
- The inventory headwind: The company was selling inventory procured at ₹60–61/kg raw material cost while current raw material cost had fallen to ₹57/kg, and it did not reduce selling prices in line because it held old high-cost inventory. Freight costs also rose ₹700–800 per ton.
- The outcome: Despite raw material prices dropping from ₹74,000/ton to ₹54,000/ton (a ₹20,000/ton swing) on an inventory of 2 lakh tons, EBITDA fell only ₹400–500 per ton. Management contrasts this with historical episodes where similar drops had driven EBITDA to zero.
- No inventory write-down: Raw material costs are passed through to customers, so no write-down was taken during the quarter.
- Tricoat EBITDA spike is temporary: Tricoat EBITDA per ton hit ~₹9,200 in Q1 because of a better sales mix with a higher proportion of super-high-value-added products. Management expects it to retract to the normal long-term average of ₹7,000–8,000/ton.
- Raw material pricing shift: From May 2022, raw material pricing shifted from beginning-of-month to end-of-month determination because of the downside market conditions, a defensive move to reduce inventory risk.
Sanjay Gupta: "This is my best quarter, if you ask me. It has reduced only by ₹400 per ton to ₹500 per ton. If I show you the past history, sometimes the fall is so much that the raw material costs, reduce from ₹74,000 to ₹60,000... Apollo's EBITDA used to be zero. The company is so strong now that it has tolerated all this."
Raipur Plant: The Next Growth Leg
- Capex progress: Almost 70–75% of capex completed, with more lines starting each month. Residual capex to be completed over the next 2–3 months, funded from internal cash flows. The plant is expected to become operational from Q3 FY23, with some lines potentially starting in August or September.
- Three product categories: (1) Color-coated tubes, claimed as first in the world; (2) Heavy structural tubes up to 500 sq mm diameter, claimed as first in India; (3) Color-coated sheets, an established market.
- Heavy structural demand validation: 400–500 tons of 500 sq ft material already supplied from Faridabad with fabrication. Management reports "50 odd projects" and intense contractor excitement, with one contractor claiming a project he thought would take one year could now be completed in two months. The company is investing further for a 1,000 sq ft line up to 40 mm thickness.
- Target economics: Raipur products are expected to deliver EBITDA of ₹6,000–8,000 per ton, a significant step-up from the existing ₹4,500–5,000 per ton.
- Market creation underway: Seminars are being held in cities inviting architects, structural consultants, and steel construction contractors to educate them about Raipur plant products. New distributors are being added for specialized products. A Delhi hospital project serves as proof of concept for heavy structural tubes, and a 15-storey commercial tower order has been received in the NCR region.
Sanjay Gupta: "People are too much excited. We have 50 odd projects... The contractor who had an order of 1500 tanks, he was so excited, that he said that this should be passed anyhow. My work will be made easy. The project that I felt was difficult to complete in one year, I will complete that in two months."
The "Golden Era" Thesis: Why Falling Steel Prices Are Good
- The competitive wedge: As steel prices fall, the price gap between Apollo's primary-steel tubes and low-grade secondary-steel tubes narrows, making Apollo's products more competitive. Simultaneously, Apollo's tubes become more competitive versus conventional construction materials like TMT bars, V bars, and light structural sections.
- The structural shift: If steel prices fall to ₹40–45/kg, management estimates the secondary steel market shrinks from 0.4 crore tons to 0.2 crore tons while the primary market grows to 0.5 crore tons. Apollo claims it has the only capacity to serve that extra 0.2–0.3 crore tons of primary demand.
- Margin trade-off: Management acknowledges margin may adjust by 1–2% in the short term but argues the volume opportunity makes this a "golden era" long-term. Capacity takes time to build, and Apollo has "unlimited capacity" relative to the demand shift.
- Market share recapture: As high-priced raw material inventory is finished and prices normalize, the company expects to recapture market share from secondary steel. Demand is not seen as a problem.
Sanjay Gupta: "When you need 0.2 crore tons or 0.3 crore tons extra of primary steel, then only we have that. Then this is golden era for us, because capacities are never grown in one day and I have unlimited capacity. I have the money, I have the capacity, I have the raw materials, I have the market."
Balance Sheet & Capital Allocation
- Debt increased: Debt levels rose because of capex commitments of up to ₹170 crore and inventory buildup, partly from the Raipur plant startup and the loss of sales volume.
- Operating cash flow: Quite strong despite the volume shortfall.
- Working capital: Consolidated net working capital remained flat at 8–9 days. Tricoat business achieved negative 11 days net working capital because it is a small business (~10–15% of volume) with only two plants, highly innovative products, and better payment terms. The consolidated figure reflects the larger group operations.
- Capacity expansion discipline: Management explicitly ruled out any further capacity expansion until reaching 0.3 crore tons (0.3 crore tons), stating it does not want to enter a "debt trap again" and is not thinking of any further capex, even ₹50–100 crore, until that milestone.
- Import stance: The company is not keen on imports and will do only limited imports for export purposes, prioritizing long-term relationships with Tata Steel, JSW, and other domestic suppliers who are currently facing high raw material costs.
Sanjay Gupta: "I don't want to go in a debt trap again. I am not even dreaming. I am not even thinking. I have only one answer. I just want to create some capacity. Till the time I don't reach 0.3 crore tons, I am not thinking of anything else."
Strategic Initiatives & Corporate Updates
- Moongipa Securities acquisition: The promoter family acquired an NBFC focused exclusively on steel-sector bill discounting, with a capital infusion of ₹300 crore and bank tie-ups for an additional ₹200–300 crore, targeting a book size of ₹500–700 crore. The entity is completely separate from APL Apollo but is expected to help increase sales by bringing back customers who were dropped due to credit constraints, with credit risk passed to the new entity.
- Apollo Tricoat merger update: The last court hearing was mid-July, all data has been provided, and the next hearing is the first week of August. Management is hopeful it will be the last hearing, with shareholders receiving swap shares in 30–60 days post court order.
- Dubai plant: Land identified and agreement done with the Dubai Inventory Authority; contract to be given to a local contractor; the process has started.
- Kolkata plant: Land identified but not yet finalized; process ongoing.
- Aalishaan app: Reached ~55,000 downloads and ~25,000 fabricators enrolled across ~150 cities, aimed at B2C promotion of the Apollo brand for home decor products.
- B2B trading platform: Internal discussions ongoing; management expects to have a "better concrete plan" to discuss in the next quarter's call.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Volume recovery | Lost ~60,000 tons to recover when prices stabilize and channels re-stock | Coming quarters |
| FY25 sales volume | 0.4 crore tons (0.4 crore tons) | FY25 |
| Volume CAGR | 30% over FY22, achievable till FY25 | FY22–FY25 |
| Raipur plant operational | Plant to start; residual capex completed in 2–3 months | Q3 FY23 (some lines Aug/Sep) |
| Raipur EBITDA | ₹6,000–8,000 per ton | Once operational |
| Tricoat EBITDA normalization | Retract to ₹7,000–8,000/ton long-term average | Ongoing |
| First-half FY23 volume | ~0.11 crore tons (0.11 crore tons) "definitely" met | H1 FY23 |
| Full-year volume split | H1: 11 lakh tons; H2: 12–13 lakh tons | FY23 |
| HRC price bottom | May fall another ₹3–4/kg to ₹52–53/kg | Next 1–2 months |
| Market share target | 60–75% of structural steel market | By 2025 |
| Capacity expansion freeze | No further capex until 0.3 crore tons reached | Until 0.3 crore tons milestone |
| Apollo Tricoat merger | Shareholders receive swap shares 30–60 days post court order | Court hearing Aug 2022 |
| NBFC book size | ₹500–700 crore target | Undated |
Key Metrics
| Metric | Q1 FY23 |
|---|---|
| Sales volume | 4.2 lakh tons, short of expectations; ~60,000 tons lost due to channel de-stocking |
| Revenue | Not stated |
| EBITDA per ton | ₹4,500, lower range of guidance maintained despite steel price collapse |
| EBITDA per ton change QoQ | Reduced by ₹400–500 per ton, described as best quarter given the raw material price drop |
| Value-added product sales mix | 60% to 65% of total volume |
| Tricoat EBITDA per ton | ₹9,200, above long-term guidance of ₹7,000–8,000 due to higher high-value product sales in the quarter |
| Consolidated net working capital | 8 days, flat QoQ; was 7–8 days on 31st March |
| Tricoat net working capital | Negative 11 days |
| Capex incurred | Up to ₹170 crore, funded from internal cash flows |
| FY25 sales volume guidance | 0.4 crore tons (0.4 crore tons), maintained; 30% volume CAGR over FY22 till FY25 |
| FY23 full-year volume target | 0.23 crore tons (0.23 crore tons); first half ~0.11 crore tons, second half 0.12–0.13 crore tons |
| Raipur plant capex completion | 70% to 75%; expected to become operational from Q3 FY23 |
| Raipur plant expected EBITDA per ton | ₹6,000 to ₹8,000 |
| Heavy structural tube project pipeline | 50 odd projects, amounting to 200,000 tons |
| Market share target by FY25 | 60% to 75% of primary structural steel market; primary market expected to reach ~0.6 crore tons by 2025 |