Key Takeaways
- Record volume, margin miss: Q1 volume hit a record 660,000 tons despite a 5-10% steel price decline, but EBITDA per ton slipped to INR4,600 (vs INR4,800-5,000 expected) as destocking and an INR38 crore inventory loss weighed on spreads.
- Raipur ramp-up is the margin story: The new Raipur plant ran at just 30% utilization, delivering near-zero EBITDA (INR3 crores). Management expects spreads to climb from INR3,000-4,000 to INR6,000-7,000 per ton as utilization reaches 80-90% over 2-2.5 years.
- Old business held up well: Excluding Raipur, the legacy APL business delivered ~INR5,700 per ton EBITDA on 574,000 tons, demonstrating resilience even as raw material prices fell.
- Heavy structural and railways are the next growth vector: Heavy structural volumes jumped 25% QoQ to 50,000 tons, and the Tirupati railway station's 100% tubular approval has "opened the floodgates" for a pipeline of station redevelopment projects.
- What to watch next quarter: Whether Raipur volumes hit the promised 100,000 tons in Q2, the pace of EBITDA per ton recovery toward INR6,000 by Q3, and any concrete order inflow from railway station tenders.
Raipur Ramp-Up & Margin Recovery
- Utilization trajectory: Raipur did 75,000 tons in Q1 (30% utilization). Management targets 100,000 tons in Q2, 150,000 tons in Q3, and 175,000-200,000 tons in Q4, reaching 500,000-600,000 tons for the full year.
- Spread improvement path: At 30% utilization, EBITDA spreads are INR3,000-4,000 per ton. Stabilized spreads at 80-90% utilization are projected at INR6,000-7,000 per ton, a level management expects to reach in 2-2.5 years.
- Narrow-line galvanizing catalyst: An in-house galvanizing line for color-coated sheets up to 4 mm thick will be fired by end August/early September, completing back-to-back production. Management calls this "a complete innovation from the House of APL Apollo" since such thick coated sheets were previously unavailable in India.
- ABPL drag should fade: ABPL (Raipur) contributed only INR3 crores in EBITDA this quarter due to infrastructure setup costs and stock loss from raw material build-up. As utilization rises, this drag should reverse.
- State incentive tailwind: Chhattisgarh has allotted INR500 crores in incentives (75% of 9% state GST on local sales for 10 years), with another INR500 crores applied for under Phase II. This represents ~INR50 crores in annual other income.
Sanjay Gupta: "This is the product, which is high-thickness coated sheets... it's a complete innovation from the House of APL Apollo, because so far if you see in India or globally, the color-coated sheets, which are available are full thickness of 1 mm, 1.2-mm. But we started -- we thought that we should be able to produce a color-coated sheet of up to 4 mm thick."
Volume & Demand Environment
- Record quarter despite headwinds: Q1 volume of 660,000 tons was the highest ever for a quarter, achieved even as steel prices declined 5-10% globally and in India, triggering destocking across the supply chain.
- Channel inventories are depleted: Management stated channel inventories are "almost blank," which it reads as a strong signal of underlying demand creation heading into the post-monsoon period.
- July-August recovery expected: Management expects to make up the Q1 EBITDA shortfall in the coming months, citing promising July and August-September trends.
- Full-year volume target maintained: FY25 volume target of 28-30 lakh tons, scaling to 36-40 lakh tons next year and 46-50 lakh tons in FY26.
Sanjay Gupta: "Channel inventories are almost blank. So there is a very good symptom of demand creating."
Heavy Structural & Railways: The Next Growth Engine
- Heavy structural volumes accelerating: Volumes grew from 40,000 tons in Q4 to 50,000 tons in Q1, with management expecting 40-50% year-over-year growth. Demand is coming from both project-based design approvals and retail replacement of RCC.
- Tirupati station as proof of concept: All four structures at Tirupati railway station (concourse, FOBs, ceiling roofing truss, office complexes) have been approved 100% on tubular steel. This has "opened the floodgates" to approach contractors for other stations.
- Railway station pipeline is large but unquantified: 1,500 stations are targeted for redevelopment. The New Delhi station tender alone could consume 20,000-30,000 tons of tubes. Management is "very, very bullish" but cannot commit to quarter-by-quarter demand figures.
- Other project wins: Max Hospital and Nanavati Hospital first phases completed; 2,000 tons of material supplied to Tirupati railway station so far.
Anubhav Gupta: "So, glad to share that Tirupati railway station has been approved 100% on tubular, like all the four structures are 100% on tubes. Okay. So with that, it has opened the, like, I would say floodgates right, to go and approach the contractors..."
Cost Reduction Program
- Four cost heads targeted: Management is attacking employee cost, store/consumables, power, and freight with specific per-ton targets, aiming to reduce total expenses by INR1,000 per ton over two years.
- Employee cost trajectory: Already reduced from INR1,000 to INR900 per ton. Target is below INR700 per ton in the near term, and below INR600 per ton once 0.5 crore ton capacity is reached.
- Freight cost ambition: Management is piloting EV vehicles to bring freight cost down from INR1,400-1,500 to INR1,000 per ton.
- Power and consumables targets: Power targeted at INR400 per ton (from INR500); store/consumables below INR200 per ton.
Sanjay Gupta: "Mr. Dhananjay, I promise you, when we reach the 0.5 crore ton of capacity, my employment cost will come down from INR600, less than INR600 per ton."
Balance Sheet & Capex
- Capex nearing completion: Another INR300-350 crores to be spent over the next 3-4 quarters to complete the 0.5 crore ton capacity. All brownfield/greenfield expansions except the East India plant will be completed by March 2024.
- Capex holiday ahead: No capex planned for 1.5 years after the 0.5 crore ton capacity is reached. The next round of INR2,000 crores runs from January 2026 to December 2027, targeting 1 crore ton capacity by 2030.
- Debt reduction expected: Net debt should start declining as Raipur ramps up and operating cash flows remain strong, supported by a 6-7 day working capital cycle. Management targets recovering the INR600 crores equity infused into ABPL within three years.
- Inventory loss manageable: The INR38 crore inventory loss this quarter (from a INR5,500/ton price drop on 70,000-80,000 tons of unsold material) was described as "very less" compared to historical impacts, because stronger branding and distribution now allow most material to be covered with bank financing.
Sanjay Gupta: "After a long battle, now Apollo come out with this inventory loss and gained wholesale but little bit company impact comes... Almost all materials get covered with the bank. So, in our books you would have seen inventory loss and profit no impact is there from the last two years since we have made our branding and distribution stronger..."
Product & Market Development
- Coated products distribution launched: Distribution of coated products has begun with good pull demand from distributors.
- Water tank opportunity emerging: A sample water tank near Lucknow was approved by government authorities, and a small order of 50 water tanks has been approved. Management is working to scale this to 5,000-10,000 tanks.
- Dubai plant focused on structural tubing: The Dubai facility will focus on structural tubing up to 300 square mm.
- East India plant still in planning: Land not yet finalized; the plant will be small (2 lakh ton capacity) and focused on commodity products, with value-added products serviced from Raipur.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Full-year volume | 28-30 lakh tons | FY25 |
| Full-year absolute EBITDA | INR1,400-1,500 crores | FY25 |
| Raipur quarterly ramp-up | Q2: 100k tons; Q3: 150k tons; Q4: 175-200k tons | FY25 quarters |
| Raipur full-year volume | 500,000-600,000 tons | FY25 |
| EBITDA per ton stabilization | INR6,000 per ton from Q3 once narrow line starts | Q3 FY25 |
| Long-term EBITDA per ton | INR5,000 in FY24, gradually to INR6,000 | FY25/FY26 |
| Capacity completion | 0.5 crore tons (0.48 crore with Siliguri) | March 2024 |
| Capex completion | INR300-350 crores remaining | Next 3-4 quarters |
| Employee cost per ton | Below INR600 | When 0.5 crore ton capacity reached |
| Total cost reduction | INR1,000 per ton reduction | Two years |
| ABPL equity recovery | INR600 crores returned | Within three years |
| Revenue doubling | On a March 2026 fiscal year basis | Calendar 2025 / FY26 |
| Next capex round | INR2,000 crores | January 2026 to December 2027 |
| 1 crore ton capacity | Full capacity target | By 2030 |
Key Metrics
| Metric | Q1 FY24 |
|---|---|
| Sales volume | 660,000 tons, highest ever for a quarter |
| Revenue | Not stated |
| EBITDA per ton | ₹4,600, vs expected ₹4,800–₹5,000; ₹5,700 excluding ABPL |
| EBITDA | 58% YoY growth in absolute terms |
| Net profit | 60% YoY growth |
| EBITDA margin (old APL+AMPL) | ₹5,700 per ton, on 574,000 tons volume and ₹330 cr EBITDA |
| Full-year volume target | 0.28 cr to 0.3 cr tons (28–30 lakh tons) |
| Full-year EBITDA target | ₹1,400 cr to ₹1,500 cr |
| H1 FY24 volume target | 13–14 lakh tons, with EBITDA of ₹650–₹700 cr |
| H2 FY24 volume target | 15–16 lakh tons, with EBITDA of ₹750–₹800 cr |
| Working capital days | 6 days |
| Net debt | ₹280 cr, up ₹40 cr QoQ; gross debt ₹950 cr, FDR ₹650 cr |
| Capex (Q1) | ₹180 cr spent, mainly for Raipur |
| Capex (full-year FY24) | ₹275–₹300 cr pending to reach 0.5 cr ton capacity |
| Raipur volume (Q1) | 75,000 tons, annualized utilization 30% |
| Raipur volume ramp-up | 100,000 tons in Q2, 150,000 tons in Q3, 175,000–200,000 tons in Q4 |
| Raipur full-year volume target | 500,000–600,000 tons |
| Raipur stabilized EBITDA spread | ₹6,000–₹7,000 per ton |
| Heavy structural volume (Q1) | 50,000 tons, up from 40,000 tons in Q4 |
| Market share (structural steel tubes) | Above 60% (8 mm to 1000 mm dia) |
| Value-added product capacity share | ~70% (0.35 cr tons VAP, 0.15 cr tons commodity) |
| Employee cost per ton | ₹900, target below ₹600 at 0.5 cr ton capacity |
| Freight cost per ton | ₹1,400–₹1,500, target ₹1,000 via EV vehicles |
| Chhattisgarh state incentive | ₹50 cr annual benefit, 6.75% of local sales GST returned |
| Inventory loss impact | ~₹38 cr technically; EBITDA would have been ₹375–₹380 cr without it |