Key Takeaways
- Steel price reversal unlocks long-term gain, near-term pain: Steel prices are falling after 4 years, a structural positive for India's largest steel buyer, but Q1 and Q2 absorb destocking, discounting and inventory write-downs.
- Gross margins are expanding, EBITDA spreads are not yet: Gross margin improved INR442/ton QoQ on better product mix, but higher freight, power and one-off brand spends kept reported EBITDA at INR4,183/ton.
- The scrap-steel threat is set to recede: A 4-year price arbitrage that let pollutive scrap-based producers capture structural tube growth is closing as new blast-furnace capacity hits the market, and management expects the scrap segment to shrink from 0.45 to 0.4 crore tons by 2030.
- Three new regional plants signal the next growth leg: Siliguri, Gorakhpur and Ahmedabad plants were announced, while Dubai's fourth mill (300 x 300 mm) was commissioned last week, making Apollo the only local supplier of that size.
- What to watch next quarter: Whether steel prices bottom as assumed, the pace of Raipur and Dubai utilization gains, and any EBITDA-per-ton recovery toward the INR5,000 level management says is achievable in H2.
Steel Price Reversal: The Core Thesis Playing Out
- The trigger: New upstream steel capacity began commissioning in December 2023, with more expected over the next 2-3 years. This ended a 4-year period of elevated HR-coil prices and flipped the cycle in Apollo's favor as India's largest steel buyer.
- The near-term cost: Falling steel prices force industry-wide destocking as dealers fear holding inventory, heavy discounting to win volumes, and minor inventory write-downs. Management calls this "short-term pain, long-term gain."
- The Q2 assumption: Steel prices can fall another INR3,000-INR4,000/ton, and whatever decline must happen will happen by Q2. Q2 will remain under pressure, then bottom out, giving a clean slate for growth from October.
- The H2 promise: The second half should be "pretty solid" and significantly better than the first half, with FY25 volume guidance of 0.32 crore tons reaffirmed.
Gupta: "Our assumption is that steel prices can further go down by INR3,000, INR4,000 a ton and whatever fall has to happen, it will happen by Q2, and we'll see all the pain from July to September months, after which second half should be pretty solid."
Margin Mechanics: Gross Gains, EBITDA Lag
- Gross margin expansion: Improved INR335/ton YoY and INR442/ton QoQ, driven by better product mix from the Raipur and Dubai plants. This is not yet visible in EBITDA spreads because operating leverage has not kicked in.
- Freight cost headwind: Freight cost per ton rose because Raipur's value-added products (roofing sheets, thicker-coated sheets) have lower volume per truck load, increasing per-unit freight.
- Power cost headwind: Raipur is not yet on renewable power. Solar power producers have been signed, but benefits will only flow from FY26, roughly 9 months out. Power costs stay elevated for the rest of FY25.
- One-off brand spends: A Siliguri brand campaign for new product launches added a non-recurring expense in Q1. Reported EBITDA of INR4,183/ton would have been INR150/ton higher without this and notional ESOP costs.
- The margin recovery path: Six levers are in play: better product mix, operating leverage from Raipur and Dubai, better pricing for general products as the scrap-steel gap closes, stronger steel-buying negotiation power, lower brand spends for the rest of FY25, and continuous cost rationalization on power, steel wastage and consumables.
- The INR5,000/ton target: If the market stabilizes in Q2 and quarterly volumes reach 800,000-850,000 tons in Q3/Q4, Apollo is capable of achieving INR5,000/ton EBITDA during those quarters by FY26.
The Scrap-Steel Displacement Opportunity
- The structural tube growth that Apollo missed: The structural steel tube segment grew 25% in FY24, but that growth was captured by scrap-steel-based producers. They exploited a price gap that opened when HR-coil prices inflated during COVID and the Russia-Ukraine war, while scrap steel production costs stayed stagnant.
- Why the gap is closing: Blast furnace steel production cost is now lower than scrap steel production cost. Blast furnace producers have room to lower prices further; scrap steel producers do not. New HR-coil capacity from NMDC Steel, JSW, Tata Steel, Jindal Steel Power and ArcelorMittal Nippon Steel should increase blast-furnace HR-coil capacity by 50% from December 2023 to December 2025.
- The general segment stagnation: General segment sales have barely moved from ~0.09 crore tons in FY20 to 0.11 crore tons last year, held back entirely by low-grade scrap steel tube availability. Management is confident HR-coil will substitute scrap steel as the gap narrows further by September.
- The 2030 prediction: Management expects the scrap steel segment to degrow from 0.45 crore tons to 0.4 crore tons by 2030, citing lower blast furnace prices, high pollution from scrap-based production, and a pro-climate government stance.
Gupta: "We are fairly confident that as HR-coil prices remain stable around INR45,000, INR48,000 per ton, we have a very good chance to take the market share back from our scrap steel segment."
Rust-Proof Segment: Arbitrage Fades, Geography Expands
- The margin decline explained: Rust-proof segment margins fell from INR7,000-INR8,000/ton (2-3 years ago) to below INR5,000/ton. Post-COVID, Indian steel producers exported coated coils, creating a domestic shortage. Apollo, with in-house galvanization plants, bought HR-coils, galvanized them and made coated tubes, enjoying a strong arbitrage for 3-4 quarters. That situation has now corrected: galvanized coil prices have fallen, the arbitrage is gone, and competitors have set up their own galvanization mills.
- The growth constraint: Apollo holds 65%-70% market share in coastal markets, but growth is now limited to the natural rate of those coastal markets. To return to 15%-20% growth, the company must expand beyond coastal markets.
Gupta: "When there was a shortage of galvanized coils in the country, our competitors were buying expensive coils from the market. And then they were converting the tubes, right? So we had a very good arbitrage for 3, 4 quarters in that segment. And we have highlighted that in our investor calls earlier as well, now that situation got course corrected."
Capacity Build-Out: Regional Penetration and Dubai
- Three new regional plants: Siliguri (East market), Gorakhpur (Eastern UP, Bihar, Odisha) and Ahmedabad (Gujarat) were announced as part of a regional penetration strategy. Land payments are in process for Siliguri and Gorakhpur; plant and building capex will follow once land is in possession.
- Dubai's fourth mill: The 300 x 300 mm mill was commissioned last week, making Apollo the only company in Dubai offering that size. The sales team is now booking orders. Two lines were commissioned last year, and two more in the last few weeks.
- The 0.5 crore ton pathway: Capacity expansion to 0.5 crore tons in the next 12-15 months is on track. Four quarters from now, Apollo will have 0.5 crore tons of sellable capacity, with a target to utilize it by FY27. Volume growth is pegged at 20%-25% next year.
- Dubai ramp-up and exports: By FY27, Apollo should utilize all 300,000 tons of available capacity in Dubai. India exports may stay at ~100,000 tons or see some cannibalization. If the 300 x 300 mill ramps up faster than expected, Apollo may install a 500 square mill in Dubai.
- Outsourcing stance: No outsourcing of finished goods (0%) because Apollo has yet to utilize its own capacity. The only exception is 12-meter tubes for solar structures where galvanization is done externally because Apollo's zinc baths handle only up to 8 meters. Management will not look for outsourcing jobs until Apollo sells 300,000-400,000 tons for 2-3 consecutive months, still 1-2 years away.
Balance Sheet and Working Capital
- Net debt commitment: Management will stick to a net-zero balance sheet for the rest of FY25, with surplus cash visible from FY26 onwards.
- Working capital: Net working capital days moved from 0 to 3 due to minor factors like 4-5 day payment delays from clients on some projects. Inventory devaluation is expected in the September balance sheet as steel prices have fallen recently.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY25 sales volume | 0.32 crore tons | FY25 |
| Steel price bottom | Further fall of INR3,000-INR4,000/ton; whatever fall must happen will happen by Q2 | Q2 FY25 |
| H2 performance | Second half "pretty solid," significantly better than first half | H2 FY25 |
| Capacity expansion | 0.5 crore tons sellable capacity added | Next 12-15 months |
| Capacity utilization | 0.5 crore tons utilized | FY27 |
| Volume growth next year | 20%-25% growth | FY26 |
| Net debt | Remain near net-debt-zero | Throughout FY25 |
| Dubai ramp-up | Utilize all 300,000 tons of available capacity | FY27 |
| Power cost normalization | Solar benefits begin; power cost settles down | FY26 |
| Scrap steel segment | Degrow from 0.45 to 0.4 crore tons | By 2030 |
| HR-coil blast furnace capacity | Increase by 50% | December 2023 to December 2025 |
Key Metrics
| Metric | Q1 FY25 |
|---|---|
| Sales volume | 721,000 tons |
| Sales volume guidance (FY25) | 0.32 crore tons |
| Reported EBITDA per ton | ₹4,183, would have been higher by ₹150 per ton absent ESOP and brand campaign expenses |
| Gross margin expansion YoY | ₹335 per ton |
| Gross margin expansion QoQ | ₹442 per ton |
| Employee cost | ₹80 cr, up from ~₹70 cr in Q4 FY24; includes ~₹5 cr ESOP notional expense and 7-8% increment |
| Employee cost run-rate (rest of FY25) | ₹75 cr per quarter |
| Net working capital | 3 days, up from 0 days in Q4 FY24 |
| Net debt | ~₹150 cr on balance sheet of ~₹5,000 cr; management expects near net-zero for rest of FY25 |
| Current sellable capacity | 0.45 crore tons |
| Target sellable capacity | 0.5 crore tons in 12-15 months; utilization targeted by FY27 |
| Capex for expansion to 0.5 crore tons | ₹500 cr–₹600 cr; ~₹200 cr–₹250 cr already spent |
| Raipur plant utilization | 61% overall; heavy structural 58%, roofing sheet 89%, super-light structural 52%, coated thicker sheet 48% |
| Dubai plant utilization | ~30% in Q1; 300,000 tons capacity, target full utilization by FY27 |
| HR-coil vs scrap steel price gap | ₹3,000–₹4,000 per ton (~5%), down from ₹20 per kg at peak |
| Exports | ~100,000 tons |