Key Takeaways
- Volume miss, management dissatisfied: 9M volumes grew 20% YoY but fell short of the 0.3 crore ton full-year target, a miss management takes direct responsibility for and calls "very dissatisfied on the organization level."
- Three delays collided in one quarter: Raipur greenfield commissioning slipped 4-5 months, Dubai production started 3 months late, and domestic steel prices stayed elevated for 8 months before finally softening in December, compressing the window for recovery.
- December inflection now visible: Steel price corrections of ₹2,500/ton in December and ₹1,500/ton in January reopened the market; Q4 volume of 7,00,000 tons is "not a tough challenge" and January exports are up 50% YoY.
- Balance sheet stretched temporarily: Working capital rose to 9 days and debt doubled to ₹400 cr, both tied to the volume loss and inventory pile-up; normalization to mid-single digits is expected by March, with a debt-free balance sheet targeted for FY25.
- What to watch next quarter: Whether Q4 volumes hit the 7,00,000-ton mark, the pace of Raipur and Dubai utilization ramp-up, and any margin recovery toward the hoped-for ₹2,500-3,000 per ton range.
Volume Miss: What Broke and What Is Recovering
- Raipur plant came 4-5 months late: Full commissioning only in December, with the last line starting in early January, delaying the capacity needed to serve demand.
- Dubai plant started 3 months behind plan: Production was expected in September but began only in December; the plant did 8,000 tons in January and targets 12,000 tons in March.
- Steel prices stayed high for 8 months: Domestic steel prices did not soften as expected from new mill capacities, persisting through October and squeezing the price gap APL needs to compete.
- October-November destocking crushed sales: Regional steel prices fell sharply while domestic prices stayed high, triggering heavy channel destocking and a sales collapse in November.
- December recovery took hold: New steel mill commissioning finally brought prices down, the market opened up, and the ground recovered in December; trends continued into January.
- Retail sales were soft independently: Construction retail sales weakened in Q2/Q3 due to high inflation, high interest costs, and partial demonetization impacting money supply.
Sanjay Gupta: "20% to 25% growth is with us without any favorable condition we are very comfortably innovation and branding and spread the distribution. 20% to 25% is not a big challenge for us this is we can do easily, but when I am talking like you know I am the aggressive person. I am not satisfied this year we do not do 0.3 crore ton which is a clear visibility so we are very dissatisfied on the organization level."
Margin Dynamics: Price Gaps, Branding, and the Secondary Market
- Primary-secondary price gap narrowed: The gap between primary and secondary steel reduced from ₹15/kg to ~₹12/kg after steel plants cut prices; management expects it to return to the historical ₹5/kg.
- APL survived the worst gap: When the gap was ₹15/kg, margins were ₹200-400/ton; the company covered and survived that period, which management calls "impossible to run this type of gap in the industry."
- Branding push is improving margins: APL increased the speed of branding in the last 1.5-2 months; general sections are now getting good demand and response with improving margins.
- Branded pipe commands a premium: APL's competitive brand sells at ~₹62 vs normal pipe at ~₹59; by December end, margins were kept and material was still sellable due to services, quality, and branding.
- Pre-galv margin compression is structural: The extraordinary margin of ₹8,000-10,000 per ton on pre-galv is no longer maintainable, but holding close to ₹6,000 per ton is achievable through quality, costing, and innovation.
- Structural margin hope, not yet a forecast: Management is "very hopeful" structural margins may increase from ₹1,500-1,700 to ₹2,500-3,000 per ton, but says "it's too early to say something."
- No inventory loss booked: APL's policy is to look only at the buy-sell gap; management says there was "no major number" for inventory loss in Q3.
Sanjay Gupta: "We have come from the tough time. We have sustained in Rs. 15 kg price and the margin Rs. 200, Rs. 400 we have covered and survived it. This is impossible to run this type of gap in the industry."
Capacity Ramp-Up: Raipur, Dubai, and the 5-Million-Ton Path
- Raipur plant now fully operational: All lines commissioned by December, last line in early January; super light segment was at 33% utilization as of December, with utilization levels expected to go up "pretty solid" in coming months.
- Dubai plant ramping on schedule: February target 8,000-10,000 tons, March target ~12,000 tons, Q1 FY25 target 30,000 tons, with a June 2024 run-rate target of 25,000 tons per month.
- Dubai cost advantage is real: APL's HR coil purchase cost is 2-3% lower than local Dubai players ($590-600 vs $620-625 per ton) due to India relationships, goodwill, and supplier terms.
- Dubai expansion already planned: Another 0.02 crore tons capacity in Dubai with CAPEX of ₹50-60 crores; overall export capacity target is 0.1 crore tons by 2026.
- 5-million-ton capacity by FY26 reiterated: 4-million-ton capacity now, 1-million-ton incremental in the next year; 4.5-million-ton by April, 5-million-ton by December.
- CAPEX is modest from here: Residual CAPEX for the 0.5 crore ton target is not more than ₹350 crores from January onwards; next year's residual plus organic CAPEX not more than ₹200-300 crores.
Product Mix Shift: Value-Add and Innovation as the Moat
- Value/super value add mix target is aggressive: By 2026, value/super value add to increase to 0.35 crore tons from 0.13 crore tons; general segment capped at not more than 0.15 crore tons.
- New products contribute 10% of volume every year: 5-6 lakh tons will be totally new product annually, driven by an innovation cycle management describes as "snake and stair play."
- Super light tubes are a new frontier: Thickness down to 0.18mm, as narrow as 8mm x 8mm; mills currently at 30% utilization.
- Thicker coated sheet is a world-first: Mill started late December/early January; no competitor has done this before.
- New pre-galv volume tube coming: Being introduced in Raipur plant; Malur plant adding two lines; two more lines to come in North India; new product expected by June 2024.
- Heavy structural and roofing are scaling: Heavy structural tubes at 50% utilization, roofing sheets above 70% utilization.
- Innovation cycle creates a 5-year lead: When APL does something new, competitors follow after five years; management says "the innovation will keep running."
Sanjay Gupta: "This is a chapter of snake and stair play and it will continue running in the industry. When we do something new then old people come and if we do something good then they will follow us after five years that is for a given time so the innovation will keep running."
Market Structure: The Secondary Market Fade and Demand Drivers
- Secondary market is dying: Secondary players are selling at ₹50 per kg with no margin; HR coil capacity is increasing in India, and management believes the secondary market "ultimately will end."
- APL is not worried about secondary competition: Management does not even discuss the secondary market in internal meetings, calling it "a matter of time maybe two months, maybe one month, maybe one year."
- Structural shift favors HR coil-based tubes: New mill commissioning and capacity increases will reduce unfair competition from scrap steel tubes; HR coil-based tubes expected to gain share.
- APL holds ~75% of primary structural tubes: 2.3 lakh tons out of 3 lakh tons in the primary structural market; secondary market has 4 lakh tons structural.
- Market share commitment is 55%: In the HR coil-based steel tube segment, management commits to maintaining 55% market share.
- Sector demand is concentrated: Railway, airport, and solar sectors are getting good response; bigger sections' growth rate is very high.
- Post-election construction outlook is brighter: Construction and infrastructure sector expected to pick up after elections.
- Retail recovery push is aggressive: APL is in "aggressive mode" to gain volume in retail, launching schemes including a Maharashtra offer of a foreign tour for every 200 tons of metal sold.
Sanjay Gupta: "I am not thinking of secondary market there will be a huge impact. We are not even discussing in our internal meeting I am not worrying about the secondary market this is a matter of time maybe two months, maybe one month, maybe one year."
Balance Sheet and Capital Allocation
- Working capital spiked to 9 days: Driven by volume loss and inventory pile-up; normalization back to mid-single digits expected by the March quarter.
- Debt doubled to ₹400 cr: Rose from ₹200 cr due to elevated working capital, despite ₹500 cr CAPEX being funded from internal cash flows.
- Debt-free balance sheet is the first priority: Management's aim is FY25 March with "zero debt and zero liabilities," after which they will consider shareholder returns and cash consumption.
- Cash deployment question is open: When asked what APL will do with 50%+ free EBITDA every year, management said first priority is debt freedom, then "we talk about our shareholders and we think inhouse and now how we consume the cash."
Sanjay Gupta: "My aim for FY25 March you see the balance sheet of zero debt and zero liabilities then we talk about our shareholders and we think inhouse and now how we consume the cash."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Q4 FY24 volume | 7,00,000 tons | Q4 FY24 (March 2024) |
| FY24 full-year volume | 0.3 crore tons | FY24 |
| FY25-26 volume target | 0.5 crore tons | FY26 |
| Capacity | 0.5 crore tons (0.4 crore now, 0.1 crore incremental) | FY26 |
| Dubai plant ramp-up | 25,000 tons per month run-rate | June 2024 |
| Dubai expansion | Additional 0.02 crore tons capacity (₹50-60 cr CAPEX) | Not specified |
| Export capacity | 0.1 crore tons total | By 2026 (next two years) |
| Value/super value add mix | 0.35 crore tons (from 0.13 crore tons); general segment ≤0.15 crore tons | By 2026 |
| Working capital | Normalize to mid-single digits | March quarter (Q4 FY24) |
| Balance sheet | Zero debt, zero liabilities | FY25 (March 2025) |
| Residual CAPEX (0.5 cr ton target) | Not more than ₹350 crores | From January 2024 onwards |
| Next year CAPEX (residual + organic) | Not more than ₹200-300 crores | FY25 |
| Market share | Maintain 55% in HR coil-based steel tube segment | Ongoing |
| New pre-galv product launch | New product from Raipur plant | Expected by June 2024 |
Key Metrics
| Metric | Q3 FY24 |
|---|---|
| Sales volume (9M FY24) | 0.19 crore tons, up 20% YoY |
| Full-year volume run-rate (9M FY24) | 0.26 crore tons, lower than initial guidance of 0.3 crore tons |
| EBITDA (9M FY24) | Up 30% YoY |
| Net profit (9M FY24) | Up 30% YoY |
| FY26 sales volume target | 0.5 crore tons (0.5 crore tons), maintained |
| Current capacity | 0.4 crore tons, with 0.1 crore tons incremental capacity ready in next 1 year |
| Working capital | 9 days, increased from mid-single digits due to Q3 volume loss and inventory pile-up |
| CAPEX (9M FY24) | ₹500 crores, funded mainly from internal cash flows |
| Net debt | ₹400 crores, increased from ₹200 crores due to elevated working capital |
| Raipur plant overall utilization | Above 50% |
| Raipur heavy structural tubes utilization | 50%, reached within first year of operation |
| Raipur roofing sheets utilization | Above 70% |
| Raipur super light tubes utilization | 30% (33% as at December 2023) |
| APBL (subsidiary) Q3 volume | 1,15,000 tons |
| APBL (subsidiary) Q3 EBITDA per ton | ₹4,500 |
| Export sales growth (9M FY24) | Up 60% YoY |
| Dubai plant Q3 FY24 volume | 8,000 tons in January 2024; plant commissioned in December 2023 |
| Dubai plant Q4 FY24 target | 30,000 tons for the quarter |
| Primary vs secondary steel price gap | Close to ₹12 per kg, reduced from ₹15 per kg |
| Market share in primary structural tubes | ~75% (2.3 lakh tons out of 3 lakh tons per month) |
| Overall primary tube market share | 55% |
| Value-added and super value-added product target by FY26 | 0.35 crore tons, up from 0.13 crore tons in FY23 |
| Residual CAPEX to reach 0.5 crore tons | Not more than ₹350 crores from January 2024 |
| FY25 balance sheet target | Debt-free and liability-free |