Apollo Pipes Ltd Q2 FY2026 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/ne7gv37cljcferwhecevsms2.pdf

Key Takeaways


Demand & Volume: A Quarter Lost to Rain and Destocking

Sameer Gupta: "So channel doesn't have that, you can say, confidence on what date it is coming. So they don't want to incur any loss because every time the Reliance or local producers... increase the rates and they stock... and again, it is backed out because of the delay from the government side and the resin prices again goes down."

Margins: Price War and Negative Operating Leverage


The Anti-Dumping Duty Catalyst


Strategy & Product Mix: Building Beyond PVC Pipes

Sameer Gupta: "Lubrizol has an upper hand in terms of quality with them. And next thing is that Lubrizol is also starting, you can say, production plant in India by FY '27, yes. FY '27 they will be starting their local production. So they will be very competitive."

Capacity & Capex: Building for a Recovery That Has Not Yet Arrived

Anubhav Gupta: "Demand situation becomes weak. It's a short-term phenomenon, right, which it will change. Why we are not too much worried is that all this expansion has come without any debt, right? All this was funded from equity or internal cash flows. So we have not bloated our balance sheet."

Distribution & Retail Push


Guidance & Commitments

CommitmentSpecificsTimeline
Full-year volumeAchieve ~100,000 tonsFY26
Next-year volumeAchieve 125,000 tonsFY27
Capacity expansionTotal installed capacity of 2,86,000 tonsNext 2 years
CPVC sales mixTake CPVC share beyond 25%Next 2-3 years
Product mix shiftShift to 75% housing plumbing, 25% agri + water infraNext 2-3 years
Capacity utilizationReach 70%-75% utilizationNext 2-3 years
ROCE improvementMove from single digit to double digit, eventually hit 20%-22%1-2 quarters for double digit; eventual target undated
Retail connectivityConnect 25,000-30,000 retail shops via mobile appBy end of FY26
Capex₹150 crores in FY26; below ₹100 crores in FY27; ₹40-₹50 crores normalized thereafterFY26 / FY27 / ongoing
South India plantKitara Capital-funded plant; 6-9 month delay possibleUndated (delayed)
Next greenfield expansionTriggered when quarterly volume hits 30,000-40,000 tons consistentlyCondition-based, no date

Key Metrics

MetricQ2 FY26
Consolidated sales volume growth8% YoY
Consolidated sales volume21,000 tons, down QoQ
Apollo standalone EBITDA per ton~₹10,000, despite price war and negative operating leverage
Kisan EBITDA marginBroke even, down from 4–5% EBITDA margin in prior quarters
CPVC volume contribution15% of total volume
H1 FY26 capex₹92 crores, full-year target ₹150 crores
FY26 full-year volume guidance100,000 to 105,000 tons (revised down from 20%+ growth)
FY27 volume target125,000 tons
Current capacity utilization~43%
Total installed capacity target2,86,000 tons over the next 2 years
Product mix: housing plumbing60% of volume, target 75% in 2–3 years
Product mix: agri plus water infrastructure40% of volume, target 25% in 2–3 years
CPVC volume target>25% of sales mix in next 2–3 years
Expected PVC resin price increase post-ADD7% to 8% from current Reliance prices
FY27 capex guidanceBelow ₹100 crores, then normalized ₹40–₹50 crores per year