  1. Unit 3 on 40,000+ sq. ft. KIADB land at Devanahalli Pending - In the FY26 annual report, the company proposed establishing Unit III on a 40,000+ sq. ft. industrial land parcel allotted by KIADB at Devanahalli, subject to allotment terms; at the Q2 FY27 call, construction was planned to start by FY29. No construction has started and Unit 3 capex is not yet budgeted.
  2. IPO proceeds of ₹27.02 crore for Unit 2 machinery On track - In the DRHP, ₹27.02 crore of IPO Net Proceeds was proposed for establishing Manufacturing Unit - II at Yalahanka, Bengaluru, with utilization scheduled across FY26-FY28. H1 FY27 saw ₹23.33 cr invested including advances, gross additions of ₹13.30 cr, and no deviation reported for the half year ended September 30, 2026.
  3. Net working capital days around 60-65 going forward Pending - At the Q2 FY27 call, management said net working capital days are expected to remain around 60-65 days going forward. H1 FY27 showed receivable days 45, inventory days 56, payable days 38, and a net working capital cycle of 63 days; the forward-guided range remains unreached as of 14 Nov 2026.
  4. PAT margin around 23% for FY27 and FY28 On track - At the Q2 FY27 call, management expected PAT margin around 23% for FY27 and FY28, adding that margins up to 25% and EBITDA up to 35% will be maintained for the next 2 years. H1 FY27 PAT margin was about 18.7% with diluted EPS of ₹3.29, below the target.
  5. \~50 new components at RFQ, 100+ developed parts to production in FY27-FY28 On track - At the Q2 FY27 call, management targeted moving up the value chain with around 50 new components at RFQ stage and more than 100 developed parts turning into production orders during FY27 and FY28. Last year \~250 new parts were deployed, \~140 already in production, expected to generate around ₹15 crore this year.
  6. FY28 revenue of approximately ₹80 crore with both units at full capacity Pending - At the Q2 FY27 call, management planned FY28 revenue of about ₹80 crore with both units at full capacity, stretchable to ₹90-95 crore with vertical integration; the Q2 FY27 PPT roadmap shows FY28 \~₹80 cr (plan). H1 FY27 revenue was ₹21.17 crore with Unit 2 at 30-35% utilization; no FY28 actuals yet.
  7. Pipeline beyond order book of more than ₹100 crore with \~30% conversion Pending - At the Q4 FY26 call, management disclosed a pipeline of more than ₹100 crore beyond the existing order book for FY27, with a typical conversion rate in the range of 30%; this was restated at the Q2 FY27 call as a minimum ₹100 crore bid pipeline converting at roughly 30-35%. Order book stood at ₹31.8 crore as of 30 September 2026, with no current pipeline disclosure.
  8. Steady-state EBITDA margin of 37% to 40% On track - At the Q4 FY26 call, management said "we can confidently say we can manage an EBITDA margin of 37% to 40%" as steady-state, later committing to at least 35% for the next 2 years with blended EBITDA around 35% and PAT around 23% for FY27-FY28. FY26 EBITDA margin was 37.32%; H1 FY27 came in at 30.8-30.9%, down from 35.2%, on material costs and Unit 2 ramp-up.
  9. Revenue of \~₹500 crore per year by 2031 On track - At the Q4 FY26 call, management targeted around ₹500 crore revenue per year over the next 5 years, confirmed as per year not cumulative. At the Q2 FY27 call, the ₹500 crore aspiration was retained while the committed concrete plan was revised to ₹300 crore by FY32; FY26 revenue was ₹30.65 crore and H1 FY27 ₹21.17 crore.
  10. Revenue mix - defence \~60%, aerospace \~30%, other sectors \~20% On track - At the Q4 FY26 call, management guided a revenue mix going forward of defence around 60%, aerospace approximately 30%, and around 20% from other sectors such as healthcare. H1 FY27 delivered defence ₹12.86 cr (60.7%), aerospace ₹5.79 cr (27.3%), healthcare ₹2.24 cr (10.6%) and others ₹0.29 cr (1.4%), versus a FY26 mix of defence \~65% and aerospace \~26%.
  11. FY27 revenue of approximately ₹48 crore On track - At the Q4 FY26 call, management guided FY27 revenue of approximately ₹48 crore - \~₹30 crore from Unit 1 and \~₹18 crore from Unit 2 at less than 50% capacity utilisation. H1 FY27 revenue reached ₹21.17 crore (44%), up 55% YoY, with H2 needing \~₹26.8 crore covered 1.19-1.2x by the ₹31.8 crore order book.
  12. Unit 2 go live by July/August 2026, \~₹60 cr investment, 25 machines On track - At the Q4 FY26 call, management guided Unit 2 at Hitech Aerospace and Defence Park to go live by July or tentatively August 2026 with approximately ₹60 crore investment and almost all 25 machines installed during the year; revisions set full machine delivery by December 2026 and full-fledged condition in FY28. Unit 2 was inaugurated on 14 August 2026 with 15 machines by September 2026; ₹23.33 cr was invested in H1 FY27 and utilization stood around 30-35%.