Key Takeaways
- Profit dips on delivery timing, not demand: PAT fell to negative ₹7.55 crores because no new phases were delivered in H1 FY25 except one Chennai phase. Management expects ₹666 crores of deliveries in H2, which would reverse the picture.
- Pre-sales guidance held at ₹2,000 crores: Area booked rose on the Amarah Phase-4 launch, and the company reaffirmed its full-year pre-sales target despite a deliberate slowdown in sales pace at some projects to capture better pricing.
- Margin expansion story is back-end loaded: FY25 profitability stays similar to last year (9% PAT margin) except for the high-margin Advik project. Management guided to 12-13% net margin in FY26 and 20% in FY27 as higher-margin projects and operating leverage kick in.
- Land strategy is explicitly cautious: Management finds land overpriced in key markets like Gurgaon, is walking away from auctions, and would rather live with a thin launch pipeline than overpay. Two new land deals (Jaipur, Bangalore) were done on terms it considers sensible.
- What to watch next quarter: Whether H2 deliveries hit the ₹666 crore plan, the pace of Bhiwadi inventory clearance, and any concrete launch date for the Bangalore project.
Delivery-Led Profitability & the H2 Bet
- H1 was an air pocket: No new phases were delivered in the first six months except one phase at Ashiana Shubham in Chennai, which pushed PAT to negative ₹7.55 crores. Revenue recognition in this business is lumpy and tied to project completion, so a soft H1 was always the base case.
- H2 delivery pipeline is large: Management expects ₹666 crores of deliveries if things go to plan, which is the balance of the full-year target after removing H1. An additional ₹90 odd crores of unsold stock in delivery projects plus completed unsold inventory like Ashiana Town could add further upside.
- Cash flows stayed healthy despite the P&L dip: Pre-tax operating cash flows remained strong on higher collections driven by better sales across projects, so the quarter was a P&L event rather than a liquidity event.
- FY26-28 margin shift is the core thesis: Profitability this year stays similar to last year except for Ashiana Advik, a high-margin project on cheaper land. From FY26 onwards the profit profile changes significantly: FY26 net margin guided to 12-13%, FY27 to 20%, on a revenue trajectory of ₹700-750 crores (FY25), ₹1,100 crores (FY26), and up to ₹1,700 crores (FY27), subject to on-time delivery.
- Two margin levers at work: Operating leverage spreads fixed costs over a higher revenue base, and gross profit margin at the project level is expanding on projects launched in the last three years where pricing has been on an upswing.
Varun Gupta: "From a management perspective, this challenge comes in right now is to should we deploy capital at these times in the market largely, we find the lands overpriced, but sales velocity is good, should we keep speeding the sales pipeline to improve pre-sales and is that the only thing we should look at or should we be a little bit more fearful that if things turn off and if we have overpaid for land, where will we get stuck and how will the markets behave?"
Pre-Sales & Pricing Strategy
- Pre-sales guidance reaffirmed at ₹2,000 crores: The company continues to hold its full-year pre-sales target. Area booked increased in Q2, driven primarily by the launch of Ashiana Amarah Phase-4 in Gurugram.
- Amarah Phase-4 traded volume for price: The phase did not sell as well in square foot volume as Phase-3, but nearly achieved the same total revenue because sale prices were raised. Launch discounts have since been taken off and effective pricing is higher; management hopes to continue increasing pricing.
- Malhar Phase-3 is a deliberate slow-sell: Phase-3 launched in Q2 with a strategy shift: instead of selling very quickly at launch, management wants to sell progressively at better prices. Phase-1 and 2 needed volume to get the project going, but the project now has financial security so future phases can be slower. Pricing will definitely move up in future phases.
- Advik sells at a steady grind, not a launch spike: Senior living projects do not get a rush of sales at launch; they sell through the life of the project. At 40,000 square feet a quarter, management is comfortable with the pace.
Land & Capital Allocation
- Two new land deals closed: One large outright purchase in Jaipur and one transaction in Bangalore done through a joint development agreement (JDA). The Jaipur deal is expected to conclude early next quarter (90-day period from agreement); the Bangalore deal has about four months for condition precedents from the date of agreement.
- Gurgaon land is priced out of the model: Management finds land in Gurgaon expensive relative to achievable sale prices and has no active ongoing negotiations there. The company participated in two auctions in NCR and walked away both times because the final closing price was significantly above its walk-away price. The rate of land in Gurgaon should be reduced to sell goods at current sale prices.
- Capital allocation governed by ROE, not momentum: Where land is expensive, the company will deploy lower capital through joint ventures, look at smaller-scale projects, and find pockets of value where others are not looking. Management would rather live with the problem of not having something to sell for a year or two than the problem of holding land so expensive that selling at a regular return becomes very difficult.
- Sector 80 land provides a buffer: The last auction in that micro-market took place 6-8 months ago; land would have sold for more than twice the price the company paid, providing a very good cushion. The Sector 80 project is expected to launch in Q1 or Q2 of FY26, with clearances ongoing.
- Funding is lined up: The company will raise money via debentures or loans, will utilize its IFC platform of ₹225 crores, and has obtained approval to raise secured debentures. Construction finance will be a small piece since most funding needed is for land acquisition.
Varun Gupta: "I would rather live with the problem of not having something to sell for a year or two rather than having the problem of having such an expensive land that selling it at profits or even a regular return just becomes very difficult and we don't have the flexibility of having the liquidity available to respond to it as well. Between those two errors, I would rather make the error of not having enough stock to sell."
Project Pipeline & New Launches
- H2 launch slate is crowded: Planned launches include Amarah Phase-5, Phase-2 of Nitara, Ekansh Phase-4, Ashiana Swarang, Ashiana Amodh Phase-2, and more in Tarang. The biggest piece is Ashiana Amarah Phase-5, expected in Q4 of this financial year, with the RERA application in progress.
- Bangalore is the new city entry: The JDA transaction in Bangalore will take roughly 18 months from now to launch, longer than usual because the company does not know the city, the approval methodology, and needs to set up a team, show flat, and sales office. Management pegs this at roughly 6 months more than a typical launch, 4 months more than what it would take in a known market.
- Jaipur gets two plays: A small-scale project called One 44 (4 lakh square feet) and an Elite Homes play. The Elite Homes market in Jaipur is estimated at 2-4 lakh square feet annually for Ashiana to address, but will take time to build out and needs a couple more projects first.
- Smaller infill projects added: A small project in Jamshedpur was taken up with very little capital employed. Panvel is being explored as an extension of the Talegaon micro-market serving Bombay.
- Lavasa remains unresolved: Ashiana Utsav in Lavasa received its Completion Certificate in July 2024 but has not been launched. Management is exploring alternative options including finding a single buyer or leasing. ₹50 crores worth of goods are stuck and not yet untangled, though the remaining land value is miniscule. Court proceedings have no clear timeline.
Inventory Clearance & Legacy Projects
- Bhiwadi inventory nearly done: Ashiana Town inventory has been reduced from 5.5 lakh square feet to just 53,000 square feet through consistent selling and should be cleared in the next 3-4 quarters. Ashiana Surbhi will be addressed after that.
- Bhiwadi market outlook is positive: New builders have not entered, the supply situation is fine, and sale prices are increasing. The price delta from Gurgaon is attracting both investors and end-users. The company is actively looking for land in Bhiwadi for another project.
- Milakpur land is a slow government process: The government wants to acquire the land for housing colonies but lacks budget. The company is happy with either getting the land or the money, but it will take time.
- Profit stock from current inventory is large: Management intends to realize roughly ₹2,000 crores of profits from the current stock by 31st March 2030, with average profit margins in the high teens over the life cycle.
Varun Gupta: "I can tell you this much in my opinion now we can see some signs of frothiness in a few markets, sales are not going as well for some developers that we are hearing some slight reduction in prices, oversized units and some of that will start getting talked more and more about in some micro markets."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Pre-sales | ₹2,000 crores | FY25 |
| H2 deliveries | ₹666 crores, plus ₹90 odd crores of unsold stock potential | H2 FY25 |
| Ashiana Town clearance | Remaining 53,000 sq ft sold out | Next 3-4 quarters |
| Jaipur land deal conclusion | Transaction closed | Early next quarter (90 days from agreement) |
| Bangalore land deal CPs | Conditions precedent completed | Middle of next quarter (~4 months from agreement) |
| Bangalore project launch | First launch in the new city | ~18 months from now |
| Sector 80 launch | Project launch | Q1 or Q2 FY26 |
| Amarah Phase-5 launch | Launch, RERA application in progress | Q4 FY25 |
| FY26 net profit margin | 12-13% | FY26 |
| FY27 net profit margin | 20% | FY27 |
| FY26 revenue | ~₹1,100 crores, subject to on-time delivery | FY26 |
| FY27 revenue | Up to ₹1,700 crores, subject to on-time delivery | FY27 |
| Profit realization from current stock | ~₹2,000 crores of profit | By 31st March 2030 |
Key Metrics
| Metric | Q2 FY25 |
|---|---|
| Area booked | 7.29 lakh sq ft, vs 4.43 lakh sq ft in Q1 FY25 |
| Value of area booked | ₹672.54 cr, vs ₹235.32 cr in Q1 FY25 |
| Total pre-sales (H1 FY25) | ₹907.86 cr |
| Revenue (FY25 guidance) | ₹700-750 cr expected for full year |
| PAT | negative ₹7.55 cr |
| PAT margin (FY25 guidance) | ~9%, maybe a tad bit better than last year |
| PAT margin (FY26 guidance) | 12%-13% expected |
| PAT margin (FY27 onwards guidance) | 20% expected |
| Pre-tax operating cash flow | ₹78.18 cr, vs ₹75.29 cr in Q2 FY24 and ₹74.92 cr in Q1 FY25 |
| Pre-tax operating cash flow (H1 FY25) | ₹153.11 cr |
| Construction | 6 lakh sq ft, vs 4.9 lakh sq ft in Q1 FY25 |
| Construction (H1 FY25) | 10.92 lakh sq ft |
| Full-year pre-sales guidance | ₹2,000 cr, maintained |
| Expected deliveries (FY25) | ₹666 cr, plus ~₹90 cr of unsold stock in those projects |
| IFC platform for investment | ₹225 cr tied up |
| Ashiana Town remaining inventory | 53,000 sq ft, down from 5.5 lakh sq ft; expected clearance in 3-4 quarters |
| Lavasa stuck goods | ₹50 cr worth |