Key Takeaways
- Pre-sales momentum intact, Gurgaon normalizing: 9M FY25 pre-sales reached ₹1,362 crores, up 45.6% YoY, while the Gurgaon market shed its "extraordinary exuberance" and settled into what management calls a healthier normal.
- Q3 profitability hit by one-offs and a delivery slip: PAT of ₹10.88 crores was weighed down by a ~₹5 crores exceptional GST payout, and the high-margin Advik Phase-1 delivery slipped to Q1 FY26 on stricter GRAP pollution rules.
- Q4 margin warning issued upfront: Margins will be "very, very muted" because the quarter's deliveries are dominated by low-margin legacy projects (Anmol Phase-2, Amantran). The inflection begins in FY26.
- The five-year ambition is high-teen PAT margins: Management expects operating leverage, land-cost advantages locked in during 2021-22, and a mix shift toward senior living to lift PAT margins to that level, without relying on aggressive price hikes.
- What to watch next quarter: The velocity of bookings at the Amarah Phase-5 launch, whether the Advik Phase-1 delivery actually closes in Q1 FY26, and any progress on closing the Bangalore or Jaipur land deals.
Pre-Sales & Demand Environment
- Area booked: Q3 FY25 area booked was 6.77 lakh sq ft, up from 3.35 lakh sq ft in Q3 FY24 but down from 7.29 lakh sq ft in Q2, when the Amarah Phase-4 launch in Gurugram drove a spike.
- 9M performance: Pre-sales for the first nine months hit ₹1,362.02 crores, a 45.56% jump from ₹935.68 crores in the same period last year, supported by broad-based bookings across projects.
- Gurgaon market reset: The market is softer than 8-9 months ago, with the "extraordinary exuberance" gone, but management characterizes current conditions as normal rather than weak and sees normal markets as the best places to operate.
- Ex-Gurgaon strength: Sales outside Gurgaon this quarter (5,50,000 sq ft) exceeded all of Q1 (4,40,000 sq ft, which had no Gurgaon contribution), indicating secular demand across other markets.
Varun Gupta: "Markets are more normal. They are not weak. But the extraordinary exuberance that the market had probably nine months ago, that is not there anymore. And which is fair, you know, normal markets are probably the best places to be in."
Project Delivery & Margin Trajectory
- Q3 revenue jump: Revenues rose to ₹139.93 crores from ₹59.53 crores in Q2, driven by deliveries of Tarang Phase-4A in Bhiwadi and Umang Phase-6 in Jaipur.
- Q3 PAT drag: PAT of ₹10.88 crores was partially offset by an exceptional payout of ~₹5 crores on a GST matter related to the Treehouse Hotel.
- Advik Phase-1 delay: This high-GP-margin project, expected to deliver the bulk of Q4 profits, slipped to Q1 of next financial year because stricter GRAP regulations in NCR lowered the pollution threshold for construction stoppage, costing 20-25 extra days.
- Q4 margin warning: Q4 margins will be "very, very muted" because the quarter's deliveries are Anmol Phase-2 (a low-margin/no-margin hangover from the last cycle) and Amantran (also low-margin).
- FY26 inflection: Margins are expected to improve significantly from FY26 onward as better-margin projects begin delivering, with operating leverage, land-cost advantages from 2021-22 acquisitions, and a growing senior living mix all contributing. Management is not factoring in significant price increases beyond inflation.
- Five-year PAT target: Management expects to average high-teen PAT margins over the next five years.
Varun Gupta: "So, there is a whole host of things that is playing out, and I expect to average high teen margins on the PAT level over the next five years and that we definitely expect to happen."
Launches & Pipeline
- Q3 launches: Three projects launched in the quarter: Ashiana Swarang, the third senior living project, in Chennai (Nemmeli); Ashiana Ekansh Phase-4 in Jaipur; and Ashiana Amodh Phase-2 in Pune.
- Amarah Phase-5 imminent: The next Amarah phase in Gurgaon is set to launch approximately two weekends from the call date, and its booking velocity is critical to hitting the full-year pre-sales target.
- Aaroham delayed: The Ashiana Aaroham launch in Gurgaon has been pushed to Q2 or Q3 of next financial year after last-minute regulatory changes forced a redesign of building plans. The asset size is unchanged.
- Existing launchable stock: The company holds ~48 lakh sq ft available to launch across existing projects, representing roughly three years of supply.
- Next-year launch ambition: Management aims to launch Aaroham (Gurgaon), a parcel in Jaisingpura (Jaipur), and the Jamshedpur parcel in the next financial year, plus at least one of the three land parcels under discussion (Bangalore, Jaipur, one more).
Land Acquisitions
- Jaipur 20-acre agreement: An agreement has been executed for a 20-acre parcel in Jaipur, previously disclosed via stock exchange announcement, but it remains at the agreement stage with conditions precedent for the landlord to perform.
- Bangalore deal progressing: The Bangalore land deal is moving forward, though landlords must still complete certain conditions on land approval. Management hopes to close this quarter, but regulatory issues may push it to the next.
- Cumulative profit target dependency: To stay on track for the cumulative profit target of ₹2,000 crores, management needs to launch all three projects outside Milakpur (Aaroham, Amaya, Jaisingpura) plus get one of the three projects under discussion (Jaipur or Bangalore) launched in the next financial year.
Cash Flow & Balance Sheet
- Operating cash flow: Pre-tax operating cash flow was ₹120.42 crores in Q3, up from ₹78.18 crores in Q2, and ₹273.53 crores for 9M FY25, healthy due to higher collections from better sales across projects.
- Unsold inventory: The Umang project is expected to sell out in H1 of next financial year or across the full financial year. Surbhi in Bhiwadi has a dedicated team working on it.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| FY25 pre-sales | ₹2,000 crores, contingent on Amarah Phase-5 launch velocity | FY25 (one quarter remaining) |
| Q4 FY25 revenue | ~₹300 crores, driven by Anmol Phase-2 and Amantran Phase-3 deliveries | Q4 FY25 |
| FY25 full-year revenue | ~₹550 crores (~₹575 crores including other income) | FY25 |
| Q4 FY25 profitability | Profitable quarter expected | Q4 FY25 |
| Advik Phase-1 delivery | High-GP-margin project delivery, slipped from Q4 FY25 | Q1 FY26 |
| FY26 revenue delivery | 1,300-plus units | FY26 |
| FY27 revenue delivery | 1,700-plus units | FY27 |
| FY28 revenue delivery | 1,700-plus units | FY28 |
| Five-year PAT margin | Average high-teen PAT margins | Over the next five years |
| Aaroham launch | Launch pushed due to regulatory redesign | Q2 or Q3 FY26 |
| Cumulative profit target enabler | Launch all three Milakpur-area projects plus one new land parcel | FY26 (to leave ~4.5 years for delivery) |
Key Metrics
| Metric | Q3 FY25 |
|---|---|
| Area booked | 6.77 lakh sq ft, vs 3.35 lakh sq ft in Q3 FY24 and 7.29 lakh sq ft in Q2 FY25 |
| Value of area booked | ₹454.16 cr, vs ₹672.54 cr in Q2 FY25 |
| Total pre-sales (9M FY25) | ₹1,362.02 cr, up 45.56% vs ₹935.68 cr in 9M FY24 |
| Total revenue | ₹139.93 cr, vs ₹59.53 cr in Q2 FY25 |
| PAT | ₹10.88 cr, driven by two phase deliveries; includes exceptional item of ~₹5 cr for GST matter |
| Pre-tax operating cash flow | ₹120.42 cr, vs ₹78.18 cr in Q2 FY25 |
| Pre-tax operating cash flow (9M FY25) | ₹273.53 cr |
| Construction | 5.19 lakh sq ft, vs 4.77 lakh sq ft in Q3 FY24 and 6.01 lakh sq ft in Q2 FY25; QoQ decline of 13.64% due to GRAP restrictions in Delhi-NCR |
| Construction (9M FY25) | 16.11 lakh sq ft, vs 13.7 lakh sq ft in 9M FY24 |
| FY25 pre-sales guidance | ₹2,000 cr, maintained; contingent on Ashiana Amarah Phase-5 launch velocity |
| Expected FY25 total revenue | ~₹550 cr, or ~₹575 cr including other income |
| Expected Q4 FY25 revenue | ~₹300 cr, with muted margins due to low-margin project deliveries |
| Unsold stock in ongoing projects | 11 lakh sq ft |
| Future phases launchable area | 48 lakh sq ft |
| Land bank | 25 lakh sq ft, excluding Bangalore and Jaipur parcels under agreement |
| Future delivery revenue trend | ₹1,300 cr+ next year, ₹1,700 cr+ in each of the two following years |