Key Takeaways
- Record order book, margin squeeze: FY22 delivered the highest-ever order intake and closing order book, but Q4 standalone EBITDA margin compressed to 13.5% as commodity and fuel price spikes outpaced the pass-through available in fixed-price contracts.
- Three asset sales can reshape the balance sheet: The KKR affiliate deal (5 BOT SPVs), Chennai ORR sale to NIIF (Rs. 686 crore), and a potential Jaora-Nayagaon sale are all in advanced stages; if they close, consolidated debt could halve from ~Rs. 7,000 crore to ~Rs. 4,000 crore.
- FY23 growth bet is aggressive: Management guided 22–25% revenue growth and Rs. 10,000-plus crore order inflow, anchored on an expanded MoRTH program of ~18,000 km and a pipeline spanning railways, metros and power distribution.
- Commodity relief is arriving, but late: Government duty measures in the last 8–10 days have started pulling steel prices down, with cement expected to follow; the damage to Q4 and early Q1 is already done, and only ~10% of the order book is exposed to fixed-price margin pressure.
- What to watch next quarter: Whether the KKR and Chennai ORR deals close by their September/Q2 FY23 deadlines, the pace of Belgaum-Khanapur execution now that the bypass is released, and whether the guided 11–12% margin holds as new bids replace old fixed-price contracts.
Asset Monetization: The Balance-Sheet Reset
- KKR affiliate deal (5 BOT SPVs): Share subscription and purchase agreement signed with Galaxy Investments; closure targeted by September 2022, with a possible 1–2 month delay but no more, subject to remaining lender and NHAI approvals, some of which are already in hand.
- Chennai ORR sale to NIIF: 100% equity sale for Rs. 686 crore aggregate consideration; closure expected in Q1 FY23 or latest by Q2 FY23, with gain booking possible upon closure. ABL retains Rs. 450 crore from the proceeds, with the balance passing through to GVR Infra.
- Jaora-Nayagaon in play: Discussions with investors are underway and a closure is expected in a couple of months, definitely within FY23; Ashoka Buildcon, Ashoka Concessions and Macquarie are separate investors negotiating.
- Proceeds cascade: Chennai ORR cash (~Rs. 450 crore) plus Jaora-Nayagaon proceeds will first be used to give exit to Macquarie (~Rs. 1,200 crore initial portion); the balance goes to working capital and other capital structure decisions.
- Surplus cash policy: Anything above ~50% of cash balance is considered surplus; 50% is retained for growing the business (HAM seed capital); the surplus is available for disposal, and management flagged a special dividend or buyback as a possibility if surplus cash materializes.
- Buyback eligibility: If the deals go through, the company is confident it would be eligible for a buyback, subject to certain compliances; the amount was not specified.
- Real estate monetization: ~Rs. 270 crore book value of real estate assets; management expects not less than 2x on monetization and is actively looking for opportunities, though progress is currently slow via developer partnerships.
- ACL loan reclassification: Rs. 1,094 crore of non-current loans to ACL moved to current on the standalone balance sheet because the deals are expected to happen and accounts to be squared off; no further write-offs are expected on the ACL portfolio.
Parakh: "These are at advanced stages now. So, definitely, September is our targeted time lines. But even if a delay happens, it could be another 1 or 2 months. It cannot be more than that."
Order Book & Growth Engine
- Record intake: Order inflow of ~Rs. 9,793 crore from April 2021 till date, producing the highest-ever closing order book; FY23 inflow is guided at Rs. 10,000-plus crore.
- FY23 revenue guidance: 22–25% growth, driven by the aggressive MoRTH program of ~18,000 km across NHAI, MRTH, NHIDCL and state NH, plus a pipeline of railways, metros, semi high-speed railways and power distribution bids yet to open (~Rs. 3,000 crore).
- Recent wins: LoA from NHAI for Rs. 829 crore (Belgaum-Sankeshwar EPC), LoA for railway electrification Rs. 618 crore (Assam), LoA from MCGM for Rs. 1,046 crore sewage treatment plant, and a HAM construction agreement with NHAI for Rs. 1,079 crore (Baswantpur-Singnodi, 6-lane greenfield highway).
- Order book mix: Roads and highways remain the first preference, followed by railways, then power, then buildings; the exact mix is uncertain given the large number of competing players.
- Buildings order book: ~Rs. 2,200 crore of buildings orders are slow-moving and will pick up only in Q3/Q4 FY23; the company focuses on government EPC contracts, not real estate developers.
- Maldives project: Fixed-price but dollar-denominated; dollar appreciation has already occurred and steel prices are normalizing; the contractor remains within budgeted margins, with no margin risk seen unless erratic price rises recur; work expected to start in Q3 FY23.
Parakh: "The order inflow should be 10,000-plus in this year, and revenue guidance will remain like we should grow by 22%, 25% in this year."
Margins: The Commodity Hit & Recovery
- Q4 margin pressure: Standalone EBITDA margin was 13.5%, squeezed by rising commodity and fuel prices that were not fully matched by the pass-through available in projects; other expenditure also spiked as COVID-era fixed-expense reductions normalized and ~Rs. 9 crore of CSR expenditure was booked in the quarter.
- The mechanism: NHAI/MoRTH projects have no direct pass-through linked to commodity indices; when indices do not move in tandem with market prices, sudden rises in steel or cement impact working, and the company tries to delay purchases, sometimes delaying turnover.
- WPI inflation impact: Double-digit WPI increase is not factored into fixed-price contracts; partially offset by dollar appreciation on overseas contracts; the margin hit is estimated at 1–1.5% (from 11–11.5% to 10–10.5%), depending on price behavior during execution.
- Relief arriving: In the last 8–10 days, government measures on export/import duties have started bringing steel prices down to normal, with cement expected to follow; management expects to retain projected margins going ahead.
- FY23 margin guidance: Confident of maintaining 11–12% margins; volatility will be captured in new bids, and fixed-price contracts suffering margin pressure are hardly 10% of the order book.
- Quarterly trajectory: Q1 will be good; Q2 affected by monsoon; Q3 and Q4 will see robust growth, as the pickup normally happens in the second half.
- Bid margin retention: Management asserts bid margins are normally retained through engineering around the project; despite aggression, the company secured ~Rs. 5,000 crore of MoRTH/NHAI orders recently.
Parakh: "Going ahead, this volatility will be captured in the new bids. So, what we are suffering is only on the fixed price contracts. And our fixed price contract, where we are suffering is hardly 10% of the entire order book. So, margins definitely we'll be able to maintain at 11%, 12%."
Execution Pipeline & Project Milestones
- Belgaum-Khanapur: Progress was slow because a major 10 km bypass was released only after pre-COD at 56%; now released, execution will pick up, with completion expected within one year (i.e., within FY23).
- Tumkur-Shivamogga HAM: TS1 pre-COD already recommended; TS2 pre-COD expected end of Q1 or early Q2 FY23; TS3 and TS4 are at an early stage and may go into next year.
- Kandi Ramsanpalle HAM: COD expected in Q2 FY23; at an advanced stage of completion.
- New project starts: Maldives project clearance from Exim Bank expected Q1 or early Q2, with project start in Q2; Zodiac Hospital start in Q1 or early Q2; Sewage treatment agreement signing in Q1, with real project take-off in Q3/Q4.
- HAM monetization: Only 1 HAM project has received full COD; 5 projects are eligible for sale but the company is waiting for better market pricing signals, including the impact of RBI lending rate increases.
- HAM annuity GST: 2 HAM projects have started receiving annuity, but the GST component (~Rs. 12 per Rs. 100 billed) is yet to be received; the procedure is being sorted, and since the company already has GST credit, it will be a cash flow item when received.
Balance Sheet, Cash & Debt
- Standalone cash position: CFS-level cash of ~Rs. 730 crore is largely parked at SPVs; free cash balances as of 31 March were only ~Rs. 200 crore, with more than 50% tied up for guarantees, leaving normal operational cash of ~Rs. 50 crore to Rs. 100 crore.
- Standalone debt: Reported balance sheet debt of Rs. 559 crore includes related-party debt from subsidiaries; external debt is Rs. 486 crore. The cash discrepancy arises from ~Rs. 40 crore received at year-end not yet appropriated and ~Rs. 120 crore leaned to bankers for guarantees and non-fund-based facilities.
- Consolidated debt trajectory: FY23 debt guidance of ~Rs. 7,000 crore assumes no deal closure; if the KKR and other deals happen, debt should decline to ~Rs. 4,000 crore. HAM execution and new project debt will continue to add, while debt reduces as HAM projects are sold.
- Contract assets/liabilities: Contract assets (unbilled revenue) have risen significantly but are expected to come down by ~Rs. 150 crore as billing progresses; the increase in contract liabilities reflects higher mobilization advances.
- CapEx: FY23 CapEx expected at Rs. 125–150 crore; FY22 total CapEx was not more than Rs. 125–130 crore. A question on whether ~90% of FY22 CapEx was done in Q4 went unanswered on the call.
- Other income and tax: Other income was higher due to write-backs of payables and miscellaneous receipts like insurance; a tax saving/credit arose because interest receivable from ACL was written off and taken as a credit in tax bookings.
Mehta: "We don't really expect any hindrances in the KKR deal irrespective of what's happening in the market, presently. I think so our markets have been rather buoyant. From both perspectives, we have had good toll rate rise, also interest rate rise are there, but they are not as significant, and they're already factored."
Competition & Sector Dynamics
- Aggression persists: A large number of players are still participating and aggression remains; slight tightening of NHAI/MoRTH bidding norms (net worth requirements) from FY23 is not expected to materially reduce competition.
- Opportunity offsets aggression: Despite competitive intensity, management sees ample opportunity, citing the expanded MoRTH program (~18,000 km vs. ~12,000 km last year) and a diversified pipeline across railways, metros and power distribution.
- BOT toll collection: BOT division toll collection rose to Rs. 269 crore in Q4 FY22 from Rs. 261 crore in Q4 FY21 and Rs. 257 crore in Q3 FY22, reflecting steady operational performance.
Parakh: "Slight tightening has happened, but that may not completely reduce the aggression in the sector. I think this aggression will remain for some time more."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| KKR affiliate deal closure (5 BOT SPVs) | Complete share subscription and purchase, subject to remaining lender/NHAI approvals | By September 2022; possible 1–2 month delay, not more |
| Chennai ORR sale to NIIF | 100% equity sale for Rs. 686 crore; gain booking upon closure | Q1 FY23, latest by Q2 FY23 |
| Jaora-Nayagaon asset sale | Close with investors; Ashoka Buildcon, Ashoka Concessions and Macquarie negotiating separately | Within a couple of months; definitely in FY23 |
| FY23 revenue growth | 22–25% growth | FY23 |
| FY23 EBITDA margin | Maintain 11–12% | FY23 |
| FY23 order inflow | Rs. 10,000-plus crore | FY23 |
| Belgaum-Khanapur completion | Full project completion after bypass release | Within one year (within FY23) |
| Tumkur-Shivamogga TS2 pre-COD | Pre-COD recommendation | End of Q1 or early Q2 FY23 |
| Kandi Ramsanpalle HAM COD | Commercial operations date | Q2 FY23 |
| Maldives project start | Exim Bank clearance, then construction start | Clearance Q1/early Q2; project start Q2 FY23 |
| Consolidated debt (no deals) | ~Rs. 7,000 crore | FY23 |
| Consolidated debt (if deals close) | Decline to ~Rs. 4,000 crore | FY23, contingent on deal closures |
| FY23 CapEx | Rs. 125–150 crore | FY23 |
| Surplus cash deployment | Special dividend or buyback possible if surplus cash materializes | Contingent on deal closures generating surplus |
Key Metrics
| Metric | Q4 FY22 |
|---|---|
| Consolidated total income | ₹2,057 crore, +15% YoY |
| Consolidated EBITDA | ₹632.6 crore, margin 30.8% |
| Consolidated PAT | ₹224.6 crore |
| Standalone total income | ₹1,622.7 crore, +13.2% YoY |
| Standalone EBITDA | ₹219.8 crore, margin 13.5% |
| Standalone PAT | ₹188 crore |
| FY23 revenue growth guidance | 22% to 25% |
| FY23 margin guidance | around 11% to 12% |
| FY23 order inflow expectation | 10,000-plus |
| Order book as of March 31 | ₹13,731 crore |
| Current order book including post-March wins | ₹14,633 crore |
| BOT division toll collection | ₹269 crore, vs ₹261 crore in Q4 FY21 and ₹257 crore in Q3 FY22 |
| Total consolidated debt | ₹6,698 crore, of which ₹3,090 crore will be transferred with 5 BOT SPVs |
| Effective consolidated debt post BOT sale | ₹3,608 crore |
| Standalone debt | ₹486 crore, comprising ₹201 crore equipment loan and ₹285 crore working capital loans |
| HAM portfolio total equity requirement | ₹1,080 crore, with ₹739 crore invested as of March 2022 |
| Pending HAM equity infusion | ₹345 crore, of which ₹255 crore in FY23 and ₹90 crore in FY24 |
| Q4 CapEx | ~₹90 crore |
| FY23 planned CapEx | ~₹125 crore to ₹150 crore |
| Aggregate consideration for 5 BOT projects sale to KKR affiliate | ₹1,337 crore |
| Chennai ORR sale to NIIF aggregate consideration | ₹686 crore, ABL expected to receive ₹450 crore |
| Fixed-price contracts share of order book | hardly 10% |
| Cement and steel including bitumen share of construction cost | 30% to 35%, fuel another 10% to 12% |
| Unbilled revenue as of March 2022 | ~₹813 crore |
| Net unbilled revenue | ₹613 crore |
| Total debtors including hold and retentions | ₹1,112 crore |
| Retention money | ₹232 crore |
| Real estate assets book value | ~₹270 crore, management expects not less than 2x on monetization |
| Jaora-Nayagaon project equity | ₹287 crore, term loan ₹165 crore |