Antony Waste Handling Cell Ltd Q2 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/hr6u5fnamfewfgmpk91z4awr.pdf

Key Takeaways


Revenue & Volume Drivers

Jose Jacob: "I want to emphasize that our strong financial performance continued in our second quarter, with another all-time high quarterly core operating revenue of ₹200 Crore, representing a 25% year-on-year increase with a steady growth trajectory going forward."

New Project Wins & Pipeline


Waste-to-Energy & Power Sales


New Business Lines: Vehicle Scrapping & Diversification

Mahendra Ananthula: "The jury is still out on these projects, what we feel is that prima facie in the initial few years going forward, the main critical success factor of this kind of project is sourcing of vehicles... So, at this stage we do not want to say anything about specific viability of these projects on an individual basis. But, going forward in five years from now this should be a very profitable business segment."

Balance Sheet, Receivables & Compliance

Subramanian N G: "In bulk of our employees who are actually in the marginalized class of society. They don't have these details in place, the names do have a mismatch. For example, the Aadhaar cards the surnames are normally alphabets in our case."

Corporate Structure & Capital Allocation

Subramanian N G: "Unlike industry like in the cement or steel industry where lateral recruits are possible in waste management it's very difficult to get replacement of these people who have got more than two and a half decades of experience in this business."

Guidance & Commitments

CommitmentSpecificsTimeline
Core revenue CAGR20-25% compounded annual growth in core revenuesOngoing (no end date)
Sustainable EBITDA margin21-23% range, with 21-22% sustainable on a normal basisOngoing
C&D project launchConstruction and demolition processing project to commence operationsMid-February 2024
WtE plant ramp-upIncrease power supply from 8 MW to nearly 11.76 MWBy end of FY24
Old receivables recoveryBalance of old dues from one corporation to be fully repaidBy FY24 end, possibly H1 FY25
PF name-mismatch resolutionReduce affected employees from 82 to zero and update recordsBy end of FY24
Non-municipal revenue mixReach 15-20% of revenue from non-municipal sourcesIn five years
Dividend declarationBoard has discussed; first step is completing subsidiary mergerSometime in the next year
Vehicle scrapping announcementPositive update on first plant location and progressBy end of this year

Key Metrics

MetricQ2 FY24
Core operating revenue₹200 Cr, +25% YoY
Consolidated EBITDA₹57 Cr, +23% YoY; margin 25%, +210 bps YoY
Core EBITDA₹55 Cr, +28% YoY; margin 25% reported, 21.6% excluding prior-period escalation
Profit after tax₹32 Cr, up from ₹28 Cr in Q2 FY23
Half-yearly operating revenue₹379 Cr, +20% YoY
Half-yearly EBITDA₹109 Cr, +15% YoY
Half-yearly PAT~₹54 Cr
Half-yearly cash flow from operations₹92.5 Cr, up from ₹30 Cr in H1 FY23
Total debt~₹370 Cr; net debt ~₹294 Cr, net debt-to-equity 0.4x
Weighted cost of debt~9.1%
Total waste managed0.11 Cr tonnes, +9% YoY
C&T volume handled0.05 Cr tonnes, +7% YoY
Waste processing volume handled0.07 Cr tonnes, +11% YoY
Kanjur MSW processing volume~6,000 tonnes per day average, ~14% increase
RDF sales~29,000 tonnes, vs ~10,500 tonnes in Q2 FY23 and ~27,800 tonnes in Q1 FY24
Compost sales~2,200 tonnes, softer YoY on reduced fertilizer demand
WTE plant power supplyUp to 8 MW commenced 2 Oct 2023; plan to ramp to ~11.76 MW
WTE plant load factor~70% in initial testing phase
WTE power generated (testing)~0.29 Cr units
Ground staff strength9,814; expected to surpass 10,000 with Panvel project
Day sales outstanding78 days, similar to previous quarter
Total debtors outstanding~₹110 Cr less than 6 months; ~₹88 Cr more than 6 months (incl. retention, min. wage reimbursement)
Disputed receivables~₹6.8 Cr, in arbitration/litigation
Prior-period escalation recognized in Q2₹12 Cr, for Dec 2021–Mar 2023 period
Sustainable core EBITDA margin guidance21% to 23%; 60% of costs have escalation pass-through
Panvel C&T contract value₹386 Cr over 5 years, plus 2-year extension option
PCMC mechanical sweeping contract value₹80 Cr over 7 years
Nagpur mechanical sweeping contract value~₹12 Cr over 7 years
C&D project minimum off-take guarantee600 tonnes per day
Scope 1 emissions6,374 tonnes CO2e, up from 5,830 in Q1
Scope 2 emissions625 tonnes CO2e, down from 891 in Q1
Voluntary attrition22% to 24%