BEW Engineering Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/u0v8i2odzf1wrrflhdivg4bx.pdf

Key Takeaways


Revenue Shock: Rainfall, Credit Policy, and a Lost Nation

Rohan Prakash Lade: "it was going to go on for full at least complete two years. But unfortunately, that has not taken up for now."

The Hastelloy Bet: Inventory as a Margin Weapon

Rohan Prakash Lade: "if a stainless equipment is costing you 50 lacs the similar equipment, when I'm manufacturing a nickel alloy it will cost you 2 CR. So, you just see the difference. So what does Nicholas equipment does? It will not only generate a good revenue, but also a better margin because you are buying the raw material from directly from the mill."

Margin Story: Procurement Gains Outrun the Top-Line Drag

Rohan Prakash Lade: "we are more targeting now good orders also like we are not trying to work on in very extremely low margins as well like we are sometimes we are letting off very low margin orders as well."

Capacity Expansion: Late, But the Door Is Opening

Rohan Prakash Lade: "we are approaching to customers in a very different manner. Basically, earlier whenever we used to approach to the customers, we used to target only few sets of equipments like the filters or dryers but now like suppose there are there is a complete project is going on and there are multiple equipments which are very small and which are very small in volumes like small in prices but it helps to get your good package."

Order Book & Export Traction


Guidance & Commitments

CommitmentSpecificsTimeline
New plant operationalOne bay operational first, second bay in 3-4 months, fully operational in 6-8 monthsNext month / 6-8 months
Revenue target₹300 CR top lineFY27
Order book growthFrom current ₹90 CR to ₹150 CREnd of FY25
Delivery cycle reductionFrom ~9-10 months to ~5-6 monthsComing year
EBITDA margin20-22% with new facility commissioning and inventory cycle reductionFY27
PAT margin~7.5%2-3 year horizon
Inventory reductionInventory expected to reduceEnd of FY26
Hastelloy order mix50-50 from current ~30%End of March
Inventory turnoverNot more than 120 days once delivery lines drop to 4-5 monthsConditional on delivery cycle reduction

Key Metrics

MetricQ2 FY25
Revenue (H1 FY25)₹51.1 cr, down 22% from ₹65 cr in H1 FY24
EBITDA (H1 FY25)₹10.6 cr, up 21.39% from ₹8.19 cr in H1 FY24
EBITDA margin (H1 FY25)20.75%, up 825 bps from 12.5% in H1 FY24
PAT (H1 FY25)₹6.02 cr, up 40-44% from ₹4.18 cr in H1 FY24
PAT margin (H1 FY25)11.79%, up 532 bps from 6.37% in H1 FY24
EPS (H1 FY25)₹18.43, up 28.52% from ₹14.34 in H1 FY24
Order book₹90 cr as of Sep 30, 2024; targeting ₹150 cr by end of FY25
Order book compositionFilter dryers 70%, paddle and protocol dryers 20%, remaining equipment 10%
Revenue target FY27₹300 cr
EBITDA margin target20-22% with commissioning of new facility
PAT margin target~7.5% (management confirmed)
Inventory₹133 cr total; raw material 60-70% of inventory, of which ~₹70 cr is Hastelloy
CreditorsUnder ₹10 cr, reduced from ~₹35 cr last year
Revenue from repeat customers40% of total revenue
Delivery cycle9-10 months currently; committed to reducing to 5-6 months
Revenue mix (H1 FY25)70% stainless steel, 30% Hastelloy
Short-term borrowing cost9-10%
Bonus equity shares3:1 ratio issued
New facility area2,700 sq meters vs current 4,500 sq meters
Orders delayed in September~₹20 cr; ₹10-15 cr delivered since, some pending
Harman Finochem order₹25 cr secured
Net worth₹130 cr as per balance sheet
Market cap~₹300 cr; trading at 15x earnings