Key Takeaways
- H2 recovery, full-year reset: H2 FY26 revenue of INR78.01 crores and PAT of INR6.38 crores drove full-year figures to INR124.93 crores and INR9.96 crores, but raw material costs compressed the full-year EBITDA margin from ~15.5% to ~13.5%.
- The order book is fully loaded: The existing plant is running at 80-85% utilization and is booked solid through October 2026, with the company not accepting orders requiring immediate delivery.
- Phase 1 expansion is the FY27 story: A new facility targeting INR350-400 crores of revenue at full tilt is set to begin commercial production by October 2026, with management guiding INR200-225 crores in FY27 revenue, back-ended around that start date.
- Margins are defended, not expanding: Management expects EBITDA margins to hold at 14-14.5%, as the deliberate elimination of low-margin conductors and the introduction of higher-margin HT and instrumentation cables offset the mix dilution from filling new capacity.
- What to watch next quarter: Whether the October commercial production date holds after the Q1 delay, the pace of order intake for the new HT cable capacity, and any movement on the investor disclosure commitments made on the call.
The Phase 1 Expansion: Timeline, Capacity & Revenue Bridge
- What got built: Phase 1 adds LT and HT cable capacity up to 33kV, a leap from the existing plant's 1.1kV ceiling. The five-year plan sequences this into Phase 2 (66kV) and Phase 3 (up to 220kV Extra High Voltage).
- Timeline slip, explained: Management had said it would "try for Q1" but never committed to it; the push to October is pinned on machine supply delays and civil site issues outside the company's control.
- FY27 revenue bridge: The existing plant carries forward roughly INR100 crores; the new facility is expected to add close to INR80 crores in FY27, yielding the INR200-225 crore target. That implies only 15-20% utilization of the new plant in its first partial year.
- Next-year ramp: Management expects to capitalize 50% of Phase 1's INR350-400 crore revenue potential in the following financial year, targeting INR350-400 crores total.
- Order pipeline for the new capacity: The company is already in talks with major players for HT cables and expects INR50-60 crores of tender wins in the next 4-5 months based on an 8-10% win rate.
Shashank Bhadora: "So you will get a revenue of INR350 crores to INR400 crores, which we expect the next financial year to at least capitalize 50% of this capacity."
Margin Structure & Sustainability
- The conductor exit: The company has completely eliminated conductors, a product carrying 1.5-2.5% margins that peers still use for 15-20% of revenue. This structural choice keeps the baseline higher than competitors'.
- Raw material pass-through works: 98% of orders carry price variation clauses, adjusting billing monthly to the prior month's average raw material price. The 2% raw material cost increase in H2 was therefore largely neutralized.
- The mix offset: Directing some new capacity to lower-margin products is inevitable, but management is simultaneously introducing higher-margin HT cables, instrumentation cable, and MVCC. The net expectation: EBITDA margins stay at 14-14.5%, not down.
- Raw material supply is not a constraint: All procurement is domestic, from large players like Hindalco and NALCO whose combined aluminium and copper capacity is set to expand 45-50% in the next two financial years. Insulation material capacity is also expanding.
Shashank Bhadora: "I have not said that my EBITDA margins will go up. They will remain exactly where they are because I mean, as you said to compensate for the higher capacity, I will have to direct it to certain lower margins. But to compensate that we are also introducing a lot of higher margin products... We do not expect them to go down."
Demand Environment & Order Book
- The demand runway is long: Management sees increasing demand year-on-year for at least the next 10 years, driven by renewable energy, government infrastructure upgrades (RDSS, smart cities, metros), industrialization, and urbanization.
- RDSS is scaling up: The first phase carried a INR1.2 lakh crore outlay for cables and conductors; the second phase, live this year, has a INR1.5 lakh crore outlay.
- State utility tendering is accelerating: Gujarat discoms have plans through 2035 with requirements expected to grow fourfold; large states like UP and MP have three-to-four-year plans, and both tender frequency and size are increasing year on year.
- Data center and EV demand is higher-margin: Data centers use specialized LT cables, not standard power cables, which carry higher margins. The company will cover a portion of data center cables in Phase 1 itself.
- Revenue mix is stable: Roughly 20-25% from government supplies, 75-80% from private EPCs, a split management expects to continue at approximately 30/70.
- The largest order yet: The company announced its largest single order in history, valued at over INR100 crores, from a reputed multinational customer.
Competitive Position
- Approvals as a moat: The company holds over 40 approvals, each requiring 3-5 years to obtain, creating a meaningful barrier for new entrants when competing for tenders.
- EPC relationships are sticky: Trust with large EPC contractors takes 5-6 years to build, and the company's long-standing relationships are a structural advantage that cannot be replicated quickly.
- Location matters: A central geographic position provides a transportation cost advantage over peers.
- Retail market is off the table: Management will not consider entering the retail market until revenue crosses INR700-800 crores, citing abundant demand in current segments and a desire to avoid diverting focus.
Shashank Bhadora: "So currently we are holding over 40 approvals, which gives us an edge when we compete with other peers. That is one. Then being the kind of relationship which we are carrying with the large EPCs, right? So those are also built over, I mean those trusts is also built over time. So it requires five to six years of time to build a trust or a relation with large EPC contractors."
Phases 2 & 3: The Longer Roadmap
- Phase 2 scope and timing: Work is planned to start in FY28, roughly a year after Phase 1 goes live. It will focus exclusively on 66kV cables, with capex of INR75-80 crores and additional revenue potential of INR400-450 crores.
- Phase 3 is directional: Phase 3 covers cables over 66kV (66kV, 132kV, and 220kV), with capex close to INR150 crores. Management said work "will have started" by 2030, with full Phase 1 and Phase 2 capacity live by then, but gave no specific timeline.
- Funding preference: Phase 2 will be funded primarily through debt; management may consider a small equity raise if targeted numbers are achieved earlier than planned.
Shashank Bhadora: "Now I have divided that into three phases. The Phase 1, we are going up to 33kV cables from currently we are doing only 1.1kV. So from there in the Phase 1, I am going up to 33kV. In Phase 2, we will go up to 66kV. And in Phase 3, we will go up to Extra High Voltage 220kV. This is the next five-year plan right, to integrate all these three phases combined."
Investor Engagement & Disclosure
- New commitments made on the call: Management agreed to start building investor decks and providing them to exchanges, to consider sharing quarterly highlights (revenue growth, EBITDA, profit margin, or volume increase), and to invite investors for a plant visit around the inauguration.
- A newly listed entity: The company completed its IPO and listed on the NSE Emerge platform during FY26, and has shifted to a new corporate office to strengthen collaboration and attract talent.
- Term loan secured: A term loan of approximately INR40 crores has been sanctioned for Phase 1, with required working capital facilities also arranged.
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Phase 1 commercial production | New facility operational, production commences | October 2026 (management trying to expedite by 1-2 months) |
| FY27 revenue | INR200 crores to INR225 crores | FY27 (back-ended, post-October ramp) |
| FY27 EBITDA margin | 14% to 14.5% | FY27 |
| New facility utilization in FY27 | At least 15-20% of Phase 1 capacity | FY27 |
| Phase 1 revenue at full tilt | INR350 crores to INR400 crores | Next financial year (FY28), with 50% capacity capitalized |
| Phase 2 start | Work begins on 66kV cable facility | FY28 (mid-2027, after Phase 1 runs for a year) |
| Phase 2 capex | INR75-80 crores, primarily debt-funded | FY28 onwards |
| Phase 2 revenue potential | Additional INR400 crores to INR450 crores | Post-Phase 2 completion |
| Phase 3 start | Work "will have started" on cables up to 220kV | By 2030 |
| Phase 3 capex | Close to INR150 crores | Post-Phase 2 |
| Retail market entry | Will consider only after crossing INR700-800 crores revenue | No date (conditional threshold) |
| Investor deck | Begin building and providing to exchanges | No date (commitment made on call) |
| Quarterly disclosures | Consider sharing quarterly highlights (revenue, EBITDA, margin, or volume) | No date (commitment made on call) |
Key Metrics
| Metric | Q4 FY26 |
|---|---|
| Revenue from operations (full year FY26) | ₹124.93 cr |
| Revenue from operations (H2 FY26) | ₹78.01 cr |
| PAT (full year FY26) | ₹9.96 cr |
| PAT (H2 FY26) | ₹6.38 cr |
| EBITDA margin | ~14% to 14.5% (FY27 guidance), down from ~15.5% in FY25 due to raw material price fluctuations |
| FY27 revenue guidance | ₹200 cr to ₹225 cr, back-ended with new plant starting October 2026 |
| H1 FY27 revenue expectation | ~₹70 cr, a 40% to 50% jump from H1 FY26 (₹46 cr) |
| Order book | >₹100 cr, current plant fully booked through October 2026 |
| Largest single order | >₹100 cr, from a reputed multinational customer |
| Tenders filled | ~₹500 cr, with expected win rate of 8% to 10% adding ₹50 to 60 cr in next 4–5 months |
| Current plant utilization | 80% to 85% (optimum for the old plant) |
| New facility completion | ~80% complete, commercial production expected by October 2026 |
| Phase 1 capex | >₹75 cr, with a term loan of ~₹40 cr sanctioned |
| Phase 1 revenue potential | ₹350 cr to ₹400 cr at optimum utilization, 3.5x to 4x of existing unit |
| Phase 2 capex | ₹75 cr to ₹80 cr, additional revenue potential of ₹400 cr to ₹450 cr |
| Phase 3 capex | ~₹150 cr, covering cables up to 220kV |
| Revenue mix: government vs private | ~20% to 25% government, 75% to 80% private EPCs in FY26; expected to shift to ~30% government, ~70% private |
| Orders on price variation clause | 98% of orders, with monthly price escalation based on prior month average |
| Copper business share | ~10% of production, rest 90% aluminium |
| Approvals held | >40, providing competitive edge |
| Domestic cable market size | $10 bn to $12 bn currently, expected to reach $17 bn by 2032 |
| RDSS scheme outlay | ₹1.5 lakh cr per phase; Phase 1 had ₹1.2 lakh cr for cables and conductors alone |
| HT vs LT cable gross margin | 1.5% to 2% additional margin in HT cables |
| Retail market entry | Not planned until revenue crosses ₹700 cr to ₹800 cr |