BIGBLOC Construction Ltd Q4 FY2023 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/2ivgqvujs0dzn8ntahki12yb.pdf

Key Takeaways


The FY23 Stall: Capacity-Constrained, Not Demand-Constrained

Manish Saboo: "So, frankly, there are no issues or challenges relating to demand in the industry, but the thing is we had delay in our expansion at Wada, which we had thought of starting commercial production in March, but because of delay in boiler permission from the Pollution Control Board, the expansion got delayed and it started commercial operations in April."

The FY24 Ramp-Up: Two Plants, One Year


Demand Backdrop: Real Estate Strength and Brick-to-Block Conversion

Mohit Saboo: "85% to 90% of the overall building material must be red bricks and AAC blocks might be just about 8% to 10%."

Margins and Competitive Moat

Manish Saboo: "So, even though there will be a fantastic growth in the consumption of AAC blocks. So, looking at both of these aspects, we see that the margins are quite sustainable."

ALC Panels and the JV Product Mix


The Pan-India Roadmap

Manish Saboo: "Moving forward, once we complete the expansion at Wada and the JV CAPEX with SCG in which we will do manufacturing panel, our vision is to set up a plant near Delhi and another plant near Bangalore. So, after that, we plan to have a Pan India presence..."

Guidance & Commitments

CommitmentSpecificsTimeline
Volume growth6,00,000–6,50,000 cubic meters sales volume (vs. ~4,60,000 in FY23), implying ~30% growthFY24
Quarterly revenue growth₹20–25 crores addition every quarter; ₹25–30 crores every 3–6 monthsStarting Q1 FY24
Wada utilization rampFrom 20–25% to optimum 75–80%, adding 10–15% per month4–5 months from mid-April
Wada Phase 2 expansionCapacity doubled to 5,00,000 CBM; capex ₹18–20 croresAfter optimum utilization reached
JV plant construction startConstruction at site to begin30–45 days
JV plant commercial productionInitial utilization 15–20%, scaling to 70–80% over 5–6 monthsQ4 FY24
Total capacity13.75 lakh CBM per annum, making it the largest AAC blocks manufacturer in IndiaPost-completion of both expansions
Selling price realizationStable in ₹4,200–4,300 rangeThroughout FY24
EBITDA and PAT marginsSimilar to FY23 levelsFY24
Carbon credits2,00,000–3,00,000 credits per year across all facilitiesAfter 2 years
Pan-India plants (Delhi, Bangalore)Vision to set up plants near Delhi and Bangalore2–3 years maximum

Key Metrics

MetricQ4 FY23
Revenue from operations₹46.5 cr, declined QoQ and YoY
EBITDA₹10.6 cr
EBITDA margin~22.8%
Net profit after tax₹5.6 cr
PAT margin~12.04%
Consolidated capacity utilization80.11%
FY23 revenue from operations₹200 cr, grew 14.2% YoY
FY23 EBITDA₹50 cr, grew 85% YoY
FY23 EBITDA margin25%
FY23 net profit after tax₹30 cr, grew 87% YoY
FY23 PAT margin15.04%
FY23 sales volume~4,60,000 cubic meters
FY24 volume target6,00,000 to 6,50,000 cubic meters
Selling price realization₹4,200 to ₹4,300 per cubic meter, stable over last three quarters, expected to continue
Total capacity post-Wada expansion8,25,000 cubic meters per annum
Wada unit capacity utilization~20% to 25%, started mid-April, expected to reach 75–80% in 4–5 months
Revenue growth target₹25 to 30 cr every 3 to 6 months starting next quarter
JV plant Ahmedabad commercial productionQ4 FY24
Total capacity expected by end of FY2513.5 lakh cubic meters
Carbon credits expected after 2 years2,00,000 to 3,00,000 credits per year across all facilities
Sales mix through dealers55% to 60% of builder sales
Sales mix to corporates~15% to 20% of total sales
Dealer payment termsaverage ~45 days; builders/corporates average 60 days, delays extend to 75–90 days
AAC block market share of building materials~8% to 10%; red bricks ~85% to 90%
Own truck fleet~65 trucks