Birla Corporation Ltd Q3 FY2024 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/v68ha1rp09hq1elpjxzll0qd.pdf

Key Takeaways


Mukutban Ramp-Up & Market Strategy

Ghose: "We have not predicted something ahead of expectation. Whatever we have indicated to you, it has been either met or exceeded."

Cost Structure & Fuel


Premium Positioning & Brand

Ghose: "This is a company, while everybody else is now talking of increasing their premium share and they consider taking it to 10% or 12% premium share, we have been above 50% for a long time."

Demand Environment & Near-Term Outlook

Ghose: "In this quarter, what we are seeing, January has not been a particularly good month for the industry. Even right now, we are not seeing any kind of sharp firming up of volumes and all prices have slipped a little bit in the last week or so."

Expansion Pipeline & Capital Allocation

Saraogi: "We have a clear policy of maintaining debt to EBITDA ratio at the maximum level of three on a sustainable basis. So, on that basis, only we made a capital allocation. So, on that basis, only we are going to start this project of expansion next year."

Guidance & Commitments

CommitmentSpecificsTimeline
FY24 EBITDA per ton~INR850, inclusive of Mukutban incentives and factoring in 3–4% price dropFY24 full year
FY24 volume growth13% (revised from 15%)FY24 full year
Mukutban monthly volumeAt least 6 lakh tons in Q4Q4 FY24
Mukutban incentive recognitionStart accruing in P&LQ4 FY24
FY24 net debtBelow INR3,400 croresFY24 year-end
FY24 capexBelow INR700 croresFY24 year-end
Bikram coal block production startQ2 of next financial yearQ2 FY25
Prayagraj grinding unit commissioningEnd of FY25 (Q4 FY25)Q4 FY25
Maihar Line 2 commissioningFY27; capex work starts FY25, subject to debt/EBITDA ≤3xFY27
Project Shikhar cost savingsINR100/ton target; INR55 already achievedWithin 2 years
Green energy capacity augmentationSolar at Mukutban, Kundanganj, MaiharBy FY26
Capacity target30 MTPABy FY30

Key Metrics

MetricQ3 FY24
RevenueNot stated
EBITDA per ton₹903 achieved in Q3; full-year guidance maintained at ~₹850
EBITDA per ton guidance for FY24~₹850, maintained despite pricing pressure; factors in Mukutban incentive and cost savings
Volume growth guidance for FY2413%, revised from 15% due to subdued market conditions
Fuel cost per 1,000 kcal₹1.58, down from ₹1.75 in Q2 FY24, a sequential reduction of 10%
Imported fuel composition25% of fuel mix, down from 31% in Q2 FY24 and 43% in Q3 FY23
Kundanganj incentive booked₹33 cr
Mukutban incentive recognitionNot recognized in Q3; expected to start in Q4 FY24
Mukutban capacity utilization60%
Mukutban monthly production2 lakh tons achieved by end of January 2024
Mukutban quarterly volume4.9 lakh tons in Q3; Q4 expected at 6 lakh tons, a sequential improvement of 22%
Mukutban volume from Maharashtra65%
Mukutban lead distance~300–310 km
Company overall lead distance~350 km
Premium share of trade volumes40%
Premium share of total volumesAbove 50%
Blended cement shareClose to 85%
Green energy share (WHRS + solar)23.3%, up from 23% in Q2 FY24
Cost reduction YoY₹400+ per ton, approximately 8%
Project Shikhar cost savings achieved₹55 of targeted ₹100 over 2 years
Net debt₹3,470 cr as of 31 December 2024; expected to end FY24 below ₹3,400 cr
Capex in 9M FY24₹415 cr; full-year FY24 expected below ₹700 cr
Borrowing cost7.98%
NSR improvement QoQ2% in Q3
Bikram coal block production startQ2 FY25
Sial Ghoghri captive coal cost₹1.45 per 1,000 kcal
Bikram captive coal cost~₹1.00 per 1,000 kcal
Marki Barka captive coal cost~₹1.25 per 1,000 kcal
Captive coal coverage post-Maihar Line 260% of enhanced clinker capacity
Capacity target by FY272.5 crore tons (25 MTPA)
Maihar Line 2 clinker capacityDoubling from 10,000 TPD to 20,000 TPD
Prayagraj grinding unit commissioningEnd of FY25 (Q4 FY25)
Gujarat sales from MukutbanMore than 1 lakh tons; approximately 10% of Mukutban volume
Existing markets expected Q4 volume growth8% to 9%