Behari Lal Engineering Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- Single-piece casting capability raised from 20 MT to 25 MT per piece
Delivered - At the Q1 FY27 PPT, management listed single-piece casting capability increased from 20 MT to 25 MT per piece as executed. The cast piece size was taken from 20 metric tons to 25 metric tons, with castings up to 25 MT single-piece shown in the Q2 FY27 PPT, and approximately 22-23 tons single-piece casting recently made for a thermal power sector customer.
- Maintain a conservative, essentially debt-free balance sheet
Delivered - At the Q1 FY27 PPT, management stated focus ahead on maintaining a conservative balance sheet, and at the Q2 FY27 call said the rest of the year includes keeping the balance sheet essentially debt-free with issue proceeds deployed carefully rather than quickly. Net worth at 30 September was ₹427.3 crores with all term loans paid off and ₹114.6 crores in cash and bank balances; short-term borrowings were ₹0.2 Cr at H1 FY27 vs ₹17.5 Cr in FY26 and Debt/Equity 0.0.
- Report both EBITDA definitions and utilization every quarter
Delivered - At the Q1 FY27 call, management committed to report both EBITDA definitions (including and excluding other income) and utilization every quarter. Q1 FY27 showed EBITDA (incl. other income) of ₹29.7 crores at 19.6% margin and operating EBITDA of ₹27.6 crores at 18.2%; Q2 FY27 showed EBITDA (incl. other income) of ₹27.6 crore at 17.9%; utilization was reported at 90.5% for Q1 FY27 and 88.2% for Q2 FY27.
- IPO proceeds deployment schedule - FY27-FY28
On track - At the DRHP, the company provided an IPO Net Proceeds deployment schedule: ₹242.88 million for equipment/civil work at Facility 1 (₹204.04 million in Fiscal 2027, ₹38.84 million in Fiscal 2028), ₹39.00 million for roof-top solar there (all Fiscal 2027), ₹438.81 million for Facility 2 (₹400.51 million Fiscal 2027, ₹38.30 million Fiscal 2028), ₹39.00 million for solar there, ₹7.00 million for debt repayment (Fiscal 2027), and GCP capped at 25% of Gross Proceeds. Up to 30 September 2026, ₹23.75 million of ₹630.39 million planned capex was utilised, debt repayment of ₹5.70 million and GCP of ₹190.60 million fully utilised, and ₹303.56 million of ₹930.00 million in total, with no deviation from the Prospectus objects.
- NABL-accredited laboratory within the premises
Delivered - At the Q1 FY27 PPT, management listed establishing a NABL-accredited laboratory within the premises as a future growth lever. The NABL laboratory was set up in-house; certification took \~1.5 years and was received in the previous quarter, and the company now regularly participates in defense/aerospace tenders via the GEM portal, where the NABL lab was a major requirement.
- Machined roll capacity addition at Unit 1 - IPO-funded
On track - At the Q2 FY27 PPT, management disclosed IPO net proceeds of ₹82.67 Cr to fund machined roll capacity addition at Unit 1; the DRHP earmarked an estimated ₹17.85 crore for upgradation of the rolls and castings machine shops with advanced CNC and VTL machines and more heat treatment furnaces. CNC machining capacity exceeds 20,000 MTPA across a 100,000+ sq. ft. machine shop; no specific capacity addition disclosed yet.
- Forging expansion - +15,000 MTPA at Unit 2
On track - At the Q2 FY27 PPT, management disclosed a +15,000 MTPA forging expansion underway at Unit 2 for specialty alloy steel products, with the in-house forging press project "under process" to eliminate job-work outsourcing and unlock forged rolls & die blocks; the DRHP detailed a 2000T hydraulic open die forging press and two hammers of 1MT and 3-5 MT to establish 15,000 MT annual forged capacity, with ₹27.78 crore of Net Proceeds earmarked. No completion or capacity addition disclosed yet; IPO net proceeds of ₹82.67 Cr fund the +15,000 MTPA rolling/forging capacity.
- Inventory normalization from Q3 FY27
Pending - At the Q2 FY27 call, management stated that from the next quarter (Q3 FY27), inventory will normalize, against a deliberate ₹23.6 crore buildup made for confirmed orders. H1 FY27 cash generated from operations was ₹16.9 crores vs ₹1.8 crores in H1 last year, including the deliberate inventory buildup of ₹23.6 crores; no Q3 FY27 read yet.
- Rooftop solar installed by end of FY27
On track - At the Q2 FY27 call, management planned rooftop solar power plants to be installed by the end of the current financial year (FY27), with a ground-mounted plant planned for H1 FY28. Rooftop solar is already installed at both operating units with further rooftop and ground-mounted capacity being planned; captive solar is being scaled from 1,862 kW toward 3.86 MWp funded by IPO proceeds, against the DRHP's \~3MW roof-top proposal using ₹7.8 crore of Net Proceeds.
- ICDP/HSS roll commercial sales - first-half of next year (H1 FY28)
On track - At the Q2 FY27 call, management stated commercial sales of ICDP/HSS rolls: "first-half of next year maybe. It is expected", with first trial lots to be sent as soon as the plant starts and repeat orders expected within one or two months of production start. ICDP and HSS rolls are currently imported into India, the company is among the first to invest in these lines with huge daily inquiries, and Unit 3 is under construction; no trial lots or commercial sales disclosed yet.
- Cash conversion cycle - hold at 90-100 days
On track - At the Q1 FY27 call, management intended to hold the cash conversion cycle to around 90-100 days even as high-value products grow. The cycle was 94 days in Q1 FY27 vs 93 at March; no Q2 FY27 read in the notes.
- Operating EBITDA margin - 20-25% over next two to three years
On track - At the Q1 FY27 call, management expected operating EBITDA margin to grow to 20-25% over the next two to three years, from \~18.2% operating margin in Q1 FY27. Q1 FY27 operating EBITDA (ex-other income) margin was 18.2% and Q2 FY27 EBITDA (incl. other income) margin was 17.9%; no disclosed read on the 20-25% target yet.
- High-value product mix - around 70% of revenue "in the near future"
On track - At the Q1 FY27 call, management targeted raising the high-value product mix to around 70% of revenue "in the near future", from \~60% in Q1 FY27 and 57% in FY26. High-value products were 60.4% of Q1 FY27 revenue and 62.9% of Q2 FY27 revenue; the trajectory is upward but no disclosed read on the 70% target yet.
- Defense/aerospace revenue - "good numbers" from FY28
On track - At the Q1 FY27 call, management expected proper revenue from defense/aerospace to start by next year (FY28) given the long approval/prototype cycle, with a small portion already started at the prototyping stage and "good numbers" targeted from FY28, no definite mix percentage committed; at Q2 FY27 this was revised to "by next year, we will see a considerable amount in our this product mix". Orders have begun from defense PSUs like Bharat Dynamics Limited and Nuclear Power Corporation of India; NABL certification was received in the previous quarter and the company now regularly participates in GEM portal tenders; Q1 FY27 aerospace & defense end-user share was 0.08%.
- FY27 capex - \~₹80 crores
On track - At the Q1 FY27 call, management targeted \~₹80 crores of capex in FY27, split across IPO-funded capex, Unit 3 from internal accruals, and a ground-mounted solar plant from internal accruals. ₹5 crores was spent in Q1 FY27 with the balance ₹75 crores targeted over the next three quarters; H1 FY27 capex was ₹12.1 crores plus ₹4.1 crores capital advances, and of the ₹93 crores fresh issue, ₹30.4 crores was utilized at 30 September 2026 with ₹23.75 million of ₹630.39 million planned capex utilised.
- Unit 3 commissioning - Q1 FY28
On track - At the Q1 FY27 call, management targeted commissioning of Unit 3 in the first quarter of the next financial year (Q1 FY28), with shed under construction and most machinery ordered, exact capacity and capex to be shared via exchange filings, and Unit 3 "right on the target" to come into production by next year; at Q2 FY27 the ICDP/HSS expansion commissioning was "expected by next year" with construction going on full swing and the project "well in time". Unit 3 is under construction as of Q2 FY27 with capital work in progress of ₹8.4 Cr at H1 FY27 vs ₹4.1 Cr in FY26; no commissioning disclosed yet.