Capacite Infraprojects Ltd Q2 FY2025 Concall Summary

Source transcript PDF: https://assets.stockscans.in/docs/q2xk26auph1cau0fptq76h4p.pdf

Key Takeaways


Margin & Portfolio Quality

Katyal: "the idea of taking limited projects is that we do not want to have any project in the portfolio which gives less than Rs. 10 crores per month. And once that happens, only then will you see the growth of that 25%, 30% on a higher base, and that is what exactly we are focused on."

Order Book & Inflows

Katyal: "There is ample opportunity, there is no reason to go and just pick up orders and then cry over spilt milk for two years down the line. So, yes, we will be choosy."

Working Capital & Asset Realization

Katyal: "we stand committed to that 100-day level by the year end, this I have repeated earlier"

Project Execution & Key Assets

CIDCO

MHADA

Data centers & factories


Industry & Competitive Position

Katyal: "on the contrary, to anticipate shortage of quality contractors from Quarter 4 of the current fiscal, so I do not see any slowdown."

Past Concerns & Clean-up


Guidance & Commitments

CommitmentSpecificsTimeline
Revenue growth25% YoY growthFY25
Order intake (ex-MHADA)₹3,000 cr target; ₹1,500 cr done, another ₹1,500 cr targetedRemaining five months of FY25
EBIT margin sustainabilityCurrent levels to continueAt least next four quarters
Net working capital days100-day levelBy FY25 year-end
Contract assets reductionDown to ~₹900 crNext four to five quarters
CIDCO monthly billingRamp to ₹80-90 cr/monthNext three to four months
CIDCO total billing₹1,500 cr cumulativeBy March 2026
MHADA quarterly executionCross ₹100 cr/quarterFrom FY26
MHADA LLP profit bookingCapacite's 35% profit share to flow into standalone booksFrom FY26
Asset monetization₹80 cr from fixed asset salesBy March 2025
Full asset realizationComplete realization from fixed assetsNext seven to eight quarters

Key Metrics

MetricQ2 FY25
Revenue from operations₹518 cr, up 23% YoY vs ₹422 cr in Q2 FY24
EBITDA₹101 cr, up 30% YoY vs ₹77 cr in Q2 FY24
EBITDA margin19.3%, up from 17.7% in Q2 FY24
EBIT₹79 cr, up 60% YoY vs ₹50 cr in Q2 FY24
EBIT margin15.2%, up from 11.4% in Q2 FY24
PAT₹45 cr, up 126% YoY vs ₹20 cr in Q2 FY24
PAT margin8.6%, up from 4.5% in Q2 FY24
Gross debt₹343 cr, flat vs March 31, 2024; gross debt to equity 0.21x
Standalone order book₹9,203 cr as on Sep 30, 2024; public sector 73%, private sector 27%
Order inflow YTD FY25₹1,500 cr (excluding BDD addition of ₹858 cr)
CIDCO monthly execution run rate~₹50 cr in October, expected to reach ₹65 cr by December and ₹75 cr by January
MHADA monthly execution run rate~₹20 cr as subcontractor, expected to increase to ₹25-28 cr in Q4
Collection in October₹200+ cr
Total bank guarantees issued₹730 cr, with ~₹250 cr free for future projects
Uncertified bills₹434 cr, with target to reduce contract assets to ~₹900 cr over next 4-5 quarters
Permanent workforce1,800+ staff (80% engineering, 20% support commercial) and 1,400+ technicians