Margin & Profitability

Kaushik Khona: "We don't say we are between scale 2 to scale 3 and going up. So earlier, the margins were, let's say, when we began before 2 years, margins were around 15% to 17%, and we are now going up to 24%."

Working Capital & Jal Jeevan Mission


Segment Performance & Order Book

Abhay Kimmatkar: "We are definitely building up one of the project, which can be really a game changer for us every other year, probably you may find such project coming in."

New Orders & Announcements

Order / AnnouncementDetailsValueTimeline
Madhya Pradesh PMAY LOIManpower agency for beneficiary-led construction under Pradhan Mantri Awas Yojana; applies geospatial technology and AI~₹67 crores3 years
Bhandara Municipal Council LOIUltrasonic and electromagnetic AMR water meters under Amrut 2.0₹17 crores12 months
T Second purchase ordersNVMe drive supply, AI-powered building/road extraction via BRYCK AI platform, geospatial imagery repository₹30 crores aggregateNot specified
EKS InTec India orderDesign planning and simulation of 4 production lines~₹4 crores3 months
Emotiv Mobility USA orderBeta development of hybrid power transfer case for US subsidiary~₹4 croresNot specified
Abhay Kimmatkar: "Funnel is pretty strong and we'll see, we are surpassing our last year's numbers. That's for sure that I will maintain it and reiterate it, we have a very strong funnel across our order book."

Sovereign AI Cloud JV

Kaushik Khona: "We don't intend to be an EPC company. We intend to be the AI solutions company. That's the objective."

Mobility, International & Inorganic Growth

Amita Saxena: "Sir the solution which you are giving is a temporary thing. Share buyback generally happens when you have cash surplus from operations. Whatever funds we have is the promoters who are invested in the company because they are confident about the growth and the future prospects of the company."

Guidance & Commitments

CommitmentSpecificsTimeline
JJM receivables clearanceAll IoT and JJM project overdues clearedBefore 31st March (next 2–3 quarters)
Unbilled revenue reduction~₹320 crores UBR billed down as JJM funds receivedNext 2 quarters
Working capital improvementMeaningful improvement in working capital cycleNext 2–3 quarters
AI Fabric JV incorporationJV incorporated with AI Fabric USANext 1–1.5 months
AI Fabric JV due diligenceTechnical and market due diligence completed; business model frozen3–4 months after incorporation
AI Fabric JV second tranche₹20 crores invested after due diligencePost due diligence
Order book intakeSurpass last year's order book numbersFY27
Large "game changer" projectOne such project anticipatedThis year or Q1 next year
Transport domain developmentsPositive developments expectedNext 1–2 quarters
Margin maintenanceMaintain 22–23%+ EBITDA marginFY27

Key Metrics

MetricQ1 FY27
Operational revenue₹158 crores, marginal YoY growth of 1%
EBITDA₹39 crores, up 27% YoY
EBITDA margin24.4%, expansion of 505 bps YoY
PAT₹31 crores, marginal decline YoY
PAT margin19.6%, contraction of ~59 bps YoY
Geospatial Engineering Services revenue₹94 crores, up 30% YoY
Technology Solutions revenue₹63 crores, down ~25% YoY
Fresh contracts secured₹143 crores during the quarter
Order book₹990 crores at quarter end, up from ₹880 crores last quarter
Working capital cycle164 days, broadly in line with previous 2 quarters
Run-rate business not in order book~₹50 crores of turnover this quarter
IoT debtors from Jal Jeevan Mission~₹100 crores, expected to be received by end of Q3
Unbilled revenue~₹320 crores on 31st March balance sheet, ~50% of standalone revenue last year
JV investment approved with AI Fabric USAUp to ₹25 crores, in 2 phases: ₹5 crores for incorporation, ₹20 crores after due diligence
LOI from Madhya Pradesh for PMAY manpower agency~₹67 crores total contract value, to be gained over next 3 years