Key Takeaways
- Record PAT margin, strong order start: PAT margin hit 5.4%, the highest in company history, while Q1 secured plus L1 orders reached INR5,000 crores, a first-quarter record.
- Growth guidance held at 20-25%: Management maintained its FY26 revenue growth range, supported by an INR18,880 crore order book and a INR15,000-16,000 crore order inflow target.
- Margin story is about bad jobs rolling off: EBITDA has moved from 8-9% to a consistent 10% as legacy loss-making projects ended; further improvement hinges on avoiding new one-off bad jobs.
- Scale is shifting toward bigger tickets: The company is exiting sub-INR300 crore jobs, which reduces competition and lifts operational efficiency, though it also raises concentration risk.
- What to watch next quarter: Whether the INR15,000 crore order inflow target stays on pace, the trajectory of EBITDA beyond 10%, and any new international execution surprises.
Order Book & Inflow
- Record Q1 secured + L1: Orders secured plus L1 reached INR5,000 crores, a level management says has never happened before in a first quarter.
- FY26 inflow target: Management expects INR15,000-INR16,000 crores of total orders in FY26, with INR4,000-INR5,000 crores already secured by Q1.
- Group contribution: Around INR1,000 crores of orders received so far are from the parent; management expects roughly 35% of new orders from group entities.
- Parent orders are arm's length: Despite the group relationship, parent contracts come through standard tenders where the company participates as the lowest evaluated bidder, same process as the last 15 years.
- Ticket size migration: The company is deliberately moving away from smaller jobs; hardly any job is now below INR300-500 crores, versus INR20-50 crore jobs in the past.
- Bigger tickets, fewer rivals: Larger orders mean only 2-3 competitors versus 26 for NHAI-type jobs, and running 30 projects for INR15,000 crores revenue is more efficient than 60 projects for INR10,000 crores.
- Order book duration: The current INR18,880 crore order book will be executed over approximately 1.5 years.
- Vadhvan Port visibility: The breakwater job tender may come any time, even tomorrow, per management.
Basu: "if you put L1 altogether, already have secured around INR5,000 crores job, either they have secured or L1. So that is something which is also very significant because in the first quarter is still securing INR5,000 crore job, which has never happened before."
Margins & Profitability
- PAT margin at record: PAT margin reached 5.4% on INR2,500 crores of revenue, described as probably the highest in company history.
- EBITDA stabilized at 10%: EBITDA has moved from 8-9% to a consistent 10% over the last 3-4 quarters, driven by the completion of loss-making legacy projects like Bangalore Metro and Delhi Metro.
- The upside case: Management believes that if no new one-off bad jobs enter the portfolio, EBITDA will increase further from the current 10% level.
- International margin double-edged: International jobs normally fetch better margins because global players operate on a high-price model with level terms, but they can be a killer if not accessed properly due to high quality and safety standards plus location risks.
- Segment margin hierarchy: Underground metro delivers the best margin, followed by marine, then specialized foundation work, then roads and buildings; airports vary by project size.
- Raw material risk managed: The company negotiates fixed raw material price intent into contracts, so input price surges get compensated with no significant margin impact.
- Operating leverage passed both ways: Management acknowledged that sometimes it prices operating leverage benefits into bids to win orders, and sometimes it retains better margin, with no fixed pattern.
Basu: "I strongly believe that if you do not have such one-off bad job, EBITDA will further increase. So let us see."
Revenue Growth & Execution
- Q1 revenue growth: Revenue grew 7% YoY with robust operational performance across projects.
- FY26 growth guidance: Management maintains 25% growth as a central figure but clarifies the range is 20% to 25%, acknowledging it cannot be perfectly accurate.
- Bangladesh back to full swing: The work stoppage from last year through October-December has resolved; operations are now running at full capacity with no execution problems.
- Bangladesh complexity: The company is handling 300-tonne piles for the first time, versus a typical 50-60 tonnes, and management says execution is going very well despite the challenge.
- Key project milestones: Chennai Metro TBM breakthrough completed; Dahej piling and foundation work started on time; Calcutta High Court Circuit Bench structure completed; precast work in Mundra appreciated by the customer.
- New project starts: Ruwais in Abu Dhabi, Bangalore Metro from a different agency, JSW port in Odisha, Vadhvan Port first package, Trivandrum and Jaipur Airport packages, and a Keventer multistory building in Kolkata are all starting.
- Capacity without constraint: The company has grown from 3,000 to over 9,000 people with almost the same manpower and machinery base; management says knowledge is the core requirement and plant and machinery can be bought, with support available from the Adani Group.
Basu: "I still maintain 25% growth, but it cannot be so accurate. So 25% has a range, 20% to 25%."
International Operations & Risk
- Abu Dhabi marine win: The company secured a marine work order via LOI for ADNOC in Abu Dhabi, marking a new geography for its marine segment.
- Bangladesh performing despite conditions: Operations are doing extremely well despite the country's issues, with the company executing pile work of a scale it has never attempted before.
- Political risk acknowledged: Management noted political risk in overseas countries is always present, citing past problems in Colombo and the start of issues in Bangladesh; if Bangladesh goes smooth, no other risk is seen affecting margin.
- International margin caution: While international jobs normally fetch better margins, management warned they can be a killer if not accessed properly, given higher quality and safety standards and location-specific risks.
Basu: "International job, provided you access it properly, you know the job properly. Otherwise, international job can be killer..."
Balance Sheet & Working Capital
- Working capital improvement: Net working capital days improved to 80 from approximately 100 previously.
- Interest cost decline: Interest cost fell from INR62-odd crores to INR50-odd crores QoQ despite higher debt, driven by a mix shift toward interest-free client advances secured through hard negotiation and lower bank guarantee costs.
- Financing cost outlook: Post the Adani and parental leverage, overall financing cost will optimize; as a percentage of revenue, it should come down as the top line grows and working capital is managed efficiently.
- Credit rating upgrade: The company's credit rating was upgraded from A to A+ during the quarter.
- Low tax rate explained: The 17% effective tax rate reflects tax-free income from one JV with a carryforward loss; the rate will stay in the same range, and this is just quarterly reporting.
- JV profit winding down: The INR7 crores share of profit from joint ventures is from Mumbai Metro, which is nearing completion; JV work is largely done and nothing significant is expected going forward.
- Capex plan: INR280-300 crores planned for FY26, though this could increase depending on work won.
Strategic Direction
- Adani Group platform: The basic idea is to grow using the Adani group's pipeline; the company is expanding from marine into airports and data centers, building capability in those segments.
- Subcontracting model: The company typically subcontracts 20-30% of work, mainly for electromechanical, HVAC, firefighting, large earthwork, and sometimes tunneling.
- Labor shortage managed: Labor shortage is a common industry problem, especially in labor-oriented building work; the company mitigates by understanding root causes of turnover, recruiting roughly 3,000 people annually for a 500-person requirement.
- Revenue recognition: Revenue is recognized from the start using the percentage of completion method; advance payments of 5-10% are separate contract terms.
- Interlinking of rivers: Management expressed interest if the project happens and the size is good, since it is a kind of marine job, but noted it needs to see when it happens and assess feasibility.
Basu: "What is required is our knowledge. Knowledge we have. So I don't see that much of a challenge."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| Revenue growth | 20% to 25% growth | FY26 |
| EBITDA margin | Around 10%, will try to maintain; aim to achieve more | FY26 |
| Order inflow | INR15,000-INR16,000 crores total | FY26 |
| Group entity order share | ~35% of new orders from group entities | FY26 |
| Capex | INR280-INR300 crores, could be higher depending on work won | FY26 |
| PAT margin | 5% is okay for the industry | Ongoing |
| Order book execution | Current INR18,880 crores executed | ~1.5 years |
Key Metrics
| Metric | Q1 FY26 |
|---|---|
| Total operating income | ₹2,542 cr, +7% YoY |
| EBITDA | ₹254 cr, +7% YoY |
| EBITDA margin | 10%, maintained at double-digit level |
| PAT | ₹137 cr, +37% YoY |
| PAT margin | 5.4%, highest in company history |
| Net debt to equity | 0.34x |
| Net working capital days | 80 days, improved from previous quarters |
| Gross debt | ₹960 cr as on 30th June |
| Net debt | ₹669 cr |
| Orders secured in Q1 FY26 | Over ₹2,900 cr |
| Orders secured in FY26 till date | ₹4,300 cr (including ₹1,300 cr+ in July 2025) |
| L1 in orders as on call date | ₹1,400 cr |
| Secured plus L1 in FY26 | Around ₹5,000 cr |
| Current order book | ₹18,820 cr (per an analyst's math), execution timeline 1.5 years |
| Opportunity pipeline | ₹87,000 cr to ₹90,000 cr, across 15-16 projects |
| Revenue growth guidance for FY26 | 20% to 25% |
| Order inflow guidance for FY26 | ₹15,000 cr to ₹16,000 cr |
| Capex plan for FY26 | ₹280 cr to ₹300 cr; ₹89 cr spent in Q1 |
| Mobilization advance | ₹835 cr as on 30th June, 80% non-interest-bearing |
| Total receivables | ₹1,600 cr, 64 days average |
| Interest cost | ₹50 cr, reduced from ₹62 cr QoQ |
| Effective tax rate | 17% for the quarter, due to tax-free JV income |