Key Takeaways
- Revenue momentum holds, margin story is about timing: Q2 revenue grew 28% YoY to ~₹1,035 crore, but reported EBITDA margin is distorted downward by JV accounting and conservative early-stage margin recognition on new jobs.
- The order book is building fast: ~₹1,000 crore of awards secured in the quarter, plus two overseas marine jobs at L1 worth ~₹2,500 crore combined, pointing to a steep revenue ramp ahead.
- Legacy losses are a known, finite drag: Two bad jobs are still consuming cash and suppressing margin, but management says the effect ends this year, with completion by March–April.
- FY24 is the year the math flips: Management guided to ~30% revenue growth and 10%+ margins next year, as new large jobs cross the 10% progress threshold and start contributing margin while legacy jobs roll off.
- What to watch next quarter: Whether the two L1 marine jobs (~₹2,500 crore) convert to awards, the pace of Chennai Metro capex deployment, and any signal that input cost moderation is actually flowing to margins.
The Margin Story: Accounting Distortions and Legacy Drag
- JV income sits below the line: Share of profit from JVs and associates, especially the Mumbai Metro project nearing completion, is reported below the EBITDA line while the associated top line is excluded entirely. If that top line were consolidated, EBITDA margin would be ~8.7% rather than the reported figure.
- Mumbai Metro margin release is a catch-up, not a run-rate: The project contributed ~₹60 crore of top line and ~₹36 crore pretax margin (~60% margin) this quarter because conservative margin recognition in earlier periods is now releasing as completion thresholds are met. This is not reflective of current-quarter operating performance.
- JV margin non-linearity is structural: Milestone achievements on JV projects nearing completion cause lumpy margin releases, so quarter-to-quarter comparisons can be volatile and misleading.
- New jobs carry zero margin until 10% progress: Four big jobs have not reached that threshold, so ~₹200 crore of revenue from these jobs has no margin recognized. This is a policy choice, not a performance problem, and the margin will flow once progress crosses the line.
- Two legacy jobs are the real margin killer: Two jobs secured in the recent past have lost significant money and are still in execution. The Bengaluru elevated metro project alone booked losses of ~₹25 crore in Q2. Management says the effect will not continue beyond this year, with completion by March–April maximum.
- Input cost relief is expected, not yet visible: Management expects margin improvement from Q4 onwards due to moderation in steel, cement and other input costs, but no quantification was offered.
Basu: "Actually, Prasad has explained a little bit. But even if you consider that around 8.8% is the margin or 9- point-something if you calculate in a different way. But basically, we have to consider that whatever job even we are executing now, it has got the legacy of a few bad jobs, and we are not drawing any margin from them. And whatever job -- good job we have secured now, they're yet to start producing results in terms of the revenue and therefore, the margin are low. We'll be see improvement from next year in our margin, EBITDA or debt, whatever."
Order Book and Pipeline
- Quarterly wins: ~₹1,000 crore of awards secured during Q2, spanning metro, marine and other segments.
- L1 positions: Two overseas marine jobs at L1 status with a combined value of ~₹2,500 crore, likely to be awarded in Q3 FY23.
- Pipeline depth: ~₹17,000 crore of jobs across segments are under pipeline or tender stage, giving visibility well beyond the current order book.
- Marine segment concentration: The pipeline includes Project Varsha (~₹4,200 crore plus) plus the two L1 overseas marine jobs (~₹2,500 crore), totaling ~₹6,000 crore in marine alone.
- Urban metro pipeline: CMRL 6 tenders worth ~₹6,000 crore and Kolkata Metro tenders worth ~₹3,000 crore are in the pipeline.
- Seabird pipeline: Two jobs comprising over ₹1,000 crore are in the tender stage.
- Railways still nascent: The company is not yet meaningfully present in railways, with only a few tunnel jobs in north Bengal and Sikkim.
- Road segment on hold: The company will not pursue further road jobs until the Ganga Expressway project (₹5,000 crore, from Adani Group) is substantially completed, citing high competition in NHAI tenders.
- Order book duration: Average completion time is ~3 years, with underground metro at 36–42 months and marine at 25–36 months.
Basu: "Railway, I don't think except the few tunnels of what we are doing north of Bengal and Sikkim, we're not very much in the railway side yet."
Project Progress and Milestones
- Mumbai Metro: Tunnel work is mostly completed; finishing work is ongoing. The project is expected to complete in approximately one year.
- Bengaluru Metro: Progress stands at 38% of the increased job scope (35% on the original scope). The elevated metro portion is loss-making, while the underground metro portion is performing well at ~₹30 crore per month turnover with a good margin profile.
- Chennai Metro: Two underground jobs have started. Tunnel boring machine and trenching machine procurement is in place, with tunneling expected to begin from May onwards.
- Udangudi marine job: Almost 75% progress achieved.
- Ganga Expressway: Financial closure has been achieved; construction has started with a zero date of 3rd November.
- Sri Lanka job: A job has been secured in Sri Lanka from Adani for the Colombo Container Terminal.
Revenue Trajectory
- H1 FY23: Total operating income grew 30% YoY to ₹2,130 crore, with Q2 (~₹1,035 crore) slightly subdued by monsoon but nearly matching Q1.
- H2 FY23 ramp: Q3 and Q4 revenue is expected in the range of ₹1,400 crore per quarter, as big jobs that have started operationally begin producing at scale.
- FY24 growth: Management expects a jump of around 25% to 30% throughout the year, with a later clarification pointing to close to 30%.
- FY25 growth: Expected to moderate slightly to around 25%.
- The growth engine: The ramp is driven by recently secured large jobs (Delhi Metro, Chennai Metro, marine) that are now moving into full execution, plus the conversion of the L1 pipeline.
Balance Sheet and Finance Cost
- Debt composition: Gross debt stands at ~₹500 crore. Some spike in debt is expected this year due to capex, particularly for Chennai Metro TBM and trenching machine procurement. Term debt will increase, while working capital is not expected to rise significantly.
- Chennai Metro capex: Total investment is likely ~₹250 crore, of which ~₹70–80 crore has been incurred so far. The remaining procurement and payment will fall mainly in Q3 and partly in Q4.
- Full-year capex: Expected at ₹250–300 crore.
- Finance cost has three layers: Interest on bank debt (~₹500 crore gross debt), interest on customer advances (contractual, mostly government clients at 9–10%), and cost of LCs and bank guarantees. Comparing finance cost only to on-book debt is misleading.
- Finance cost trajectory: Historically in the range of 3% to 4% of revenue. May see some increase due to rising interest rates in the economy, but expected to moderate as new orders start delivering cash flow and revenue. No specific forward quantum was provided.
- PAT: No material difference between stand-alone and consolidated PAT; the Bengaluru Metro project loss appears in consolidated numbers.
Patwardhan: "Comparing the finance cost only with the debt on our books would not really be appropriate. And it could lead to some wrong conclusion. If you say the interest cost for the quarter is INR35 crore on a debt of INR500 crore, whereas that is not really the case."
Parent Relationship and Strategy
- Royalty rationale: The company pays royalty to the parent for technical support (including Thai nationals for specialized work), brand and logo usage, and access to expertise in the airport and underground metro segments that has contributed to growth.
- Road segment discipline: The company is happy with the single large Ganga Expressway road job from Adani (~₹5,000 crore) and will not pursue further road work until that project is substantially complete, citing intense competition in NHAI tenders.
- Segment focus: The company is concentrated on underground metro, marine, and select elevated metro projects, with railways still a very small presence.
Basu: "First of all, there is a lot of technical support we got from the parent. We use their logo and the brands, and there are many facilities we enjoy because of the parent. And today, we have grown up so much, the support from them in the airport segment, underground metro segment. So there are several issues which contributes to our growth getting support from the parent. That is why we pay the royalty."
Guidance & Commitments
| Commitment | Specifics | Timeline |
|---|---|---|
| H2 FY23 quarterly revenue | ~₹1,400 crore per quarter | Q3 and Q4 FY23 |
| FY23 full-year margin | Around 9% to 10% | FY23 |
| FY24 revenue growth | Jump of around 25% to 30% (later clarified: close to 30%) | FY24 |
| FY24 margin | Around 10%, 10% plus | FY24 |
| FY25 revenue growth | Around 25% | FY25 |
| Legacy bad job completion | Both loss-making jobs completed | By March–April |
| Margin improvement start | Improvement visible as legacy jobs roll off and new jobs cross 10% threshold | From next year (FY24) |
| Chennai Metro tunneling start | Tunneling work begins | From May onwards |
| Mumbai Metro completion | Project completed | In a year or so |
| Full-year capex | ₹250–300 crore | FY23 |
| L1 marine job conversion | Two overseas marine jobs (~₹2,500 crore) awarded | Likely Q3 FY23 |
| Road segment expansion | No further road jobs pursued | Until Ganga Expressway is substantially completed |
Key Metrics
| Metric | Q2 FY23 |
|---|---|
| Total operating income | ₹1,035 cr, 28% growth YoY |
| PAT | ₹20 cr, 33% growth YoY |
| Total operating income (H1 FY23) | ₹2,130 cr, 30% growth YoY |
| PAT (H1 FY23) | ₹50 cr, vs ₹33 cr in H1 FY22 |
| EBITDA margin (including JV/associate top line) | 8.7%, more or less equal to last quarter |
| EBITDA margin guidance (FY23) | 9% to 10% |
| Revenue guidance (next year) | 25% to 30% jump throughout the year |
| Margin guidance (next year) | 10% plus |
| Work in hand | ₹21,000 cr plus |
| Order inflow (Q2 FY23) | ₹1,000 cr |
| Order inflow (H1 FY23) | ₹8,000 cr |
| Lowest bidder, orders likely awarded in Q3 FY23 | ₹2,500 cr |
| Gross debt | ₹500 cr |
| Full-year Capex expected | ₹250 cr to ₹300 cr |